WorksheetsECV LAB - II CIE - 1 PART 1 & 2 - 12 Mk
Total questions: 11
Worksheet time: 6mins
Which tender allows anyone to submit a tender to supply the goods or services that are required.
Framework tendering
Selective tendering
Open tendering
Close tendering
________________involves the preparation of tenders based on a typical or notional bill of quantities or schedule of works.
Framework tendering
Selective tendering
Negotiated tendering
Serial tendering
_______________tendering is used when all the information necessary to calculate a realistic price is available when tendering commences
Single-stage
Double-stage
Framework
Serial
____________ is a list or schedule of quantities of all the possible items of work required for construction of any building or structure.
Quality survey
Rate list
Quantity survey
Rate schedule
Mutual mistake occurs when both parties of a contract are mistaken as to the terms.
False
True
A tender is in the nature of:
A contract
An offer
An invitation to offer
A proposal
Which of the following is a disadvantage of a formal tender process?
The tender process generally eliminates the opportunity for negotiation
The design must be essentially finalized before tender documents can be prepared
All of the above
The tender process is time consuming in terms of document preparation, question answering, and tender evaluation
A contractors prepares for the tender/ Bid in ________ stage
Post tendering
Pre tendering
Contract
Commissioning
A construction team consists of
Contractor
Engineer
Owner
All of Above
The rate of an item of work depends on
. Specifications of works
Specifications of material
Proportion of mortar
All the above
An agreement not enforceable by law is called
Void agreement
Valid agreement
Voidable agreement
None of above