158.225 Business Process Model and Notation (BPMN)

Total questions: 12

Worksheet time: 6mins

Name
Class
Date
1.

Which element cannot accept incoming message flow?

a)

pool

b)

activity

c)

start event

d)

end event

2.

What are flow objects?

a)

gateways, activities, events

b)

any BPMN element

c)

message flow and sequence flow

d)

elements inside a pool or lane

3.

Which types of connecting objects can connect elements of two different lanes in the same pool?

a)

sequence flow

b)

association

c)

message flow

d)

group

4.

What statement is correct?

a)

The BPMN specification includes the specification of BPEL4WS.

b)

BPEL4WS is a machine executable process language.

c)

BPMN is a notation only for business people.

d)

BPMN 1.1 is a shortcut for Business Process Model and Notation.

5.

Which notation represents a text annotation?

a)

Symbol a)

b)

Symbol b)

c)

Symbol c)

d)

Symbol d)

6.

Which is an alternative representation to the given process?

a)
b)
c)
d)
7.

Which graphical element describes an association?

a)

Graphical element a)

b)

Graphical element b)

c)

Graphical element c)

d)

Graphical element d)

8.

Which statement about pools and lanes is true?

a)

An empty pool is not allowed.

b)

A collaboration process is a process inside a pool.

c)

A pool represents a subprocess.

d)

An embedded subprocess cannot contain pools and lanes.

9.

What is a generic term for work that a company performs?

a)

event

b)

gateway

c)

activity

d)

group

10.

At first a customer wants to book a hotel. Then he wants to book a flight and a car or only a car or only a flight. Which diagram describes this situation?

a)
b)
c)
d)
11.

Which statement about the diagram is NOT correct?

a)

The diagram shows a collaboration between customer and company.

b)

The pool “customer” is a black box.

c)

Message “M1” is sent before message “M2.”

d)

Start and end events are missing. The diagram is not correct.

12.

Which diagram describes the interrupt of task A if message M arrives and starts Task C next?

a)
b)
c)
d)