1.

What method of selecting an architect is used if you want to choose based on reputation

a)

Comparative selection

b)

Evaluation and Ranking selection

c)

Selection through a Design Competivion

d)

Direct Selection

2.

The advantage of using this type of architect's selection is that the opportunity to be selected will be open to all PRC- registered and licensed architect or PRC registered Architectural Firms.

a)

Comparative Selection

b)

Direct Selection

c)

Architectural Design Competition

d)

Open Comparative Design Competition

3.

The jury of an Architectural Design Competition is composed of at least how many members?

a)

3

b)

4

c)

5

d)

6

4.

It covers a broad line of architectural services ranging from initial problem identification to activities that would allow the Architect to initially conceptualize an array of architectural allied solutions.

a)

Pre Feasibility Services

b)

Pre Design Services

c)

Architectural Design Services

d)

Comprehensive Architectural Services

5.

Your Friend, upon Learning that you are now a RLA, referred his aunt to you who was looking to design her dream house. You are going to meet your friend's aunt for the first time. What attire will you wear?

-From JPT Refresher

a)

Business Attire- A suit to show that you are a professional thereby establishing a professional relationship

b)

Presentable and Comfortable - To make the client comfortable and establish a friendly relation

c)

Rugged- To convey to the client that you are easy to talk to and is willing to negotiate to cut the cost

d)

Any Attire- The client will hire me based on my skills as an architect and not how I look

6.

You have just passed the 2020 SPLE board examination for Architects, what would you do next?

a)

You can now sign and seal any architectural plans in the Philippines since you already passed the exam

b)

Look for a greener pasture

c)

You can now establish your own Firm

d)

Get ready for oath taking

7.

When is the Architec't Creed not recited?

a)

IAPOA meeting

b)

Introductionto UAP

c)

Mass Oath taking

8.

To get a replacement PRC ID, you need to pay PHP250 and present your?

a)

Special Power of Attorney

b)

Affidavit of Loss

c)

4 pcs 2x2 picture

d)

Community Tax Certificate

9.

Juan and his friend Pedro wants to build a partnership and start an Architectural firm. Where should their company be registered?

a)

DTI

b)

SEC

c)

DTI, SEC and PRC

d)

DTI and SEC

10.

Three siblings decided to form their own Architectural Firm. One is an Architect, another is an Engineer and the last is an Interior Designer. How much should be the Architectural composition of the corporation?

a)

50%

b)

65%

c)

70%

d)

75%

11.

What is The DAEDS minimum basic fee for a Mausoleum Project?

a)

7.5 % of PCC

b)

10% of PCC

c)

12% of PCC

d)

7% of PCC

12.

An Architect makes a miniature model of the project for his own design study. Who should pay for it?

a)

Owner/client

b)

Contractor

c)

Architect

d)

Project Manager

13.

This method of compensation is based on technical hours spent and is only applicable to non creative work.

a)

PCC

b)

MDPE

c)

PFPE

d)

Lump Sum or Fixed Fee

14.

You had a Residential project for a client. After the construction, you found out that the client used your design for another project with a different Architect. What should you do?

a)

The rule of "Forgive and Forget"

b)

Inform the Mayor

c)

Report the case in the barangay and they will let you and the client to settle it in the Office of the local official

d)

File a case to the PRC

15.

Scope of Pre Design Services that involves the analysis of the space requirements of the project based on organizational structure and functional setup.

a)

Space Planning Studies

b)

Architectural Programming

c)

Space Management Studies

d)

Feasibility Studies

16.

For an MDPE compensation, what is the formula for a direct cost?

a)

AN + CN X M

b)

AN+CN+TN

c)

AN+CN+TN+M

d)

AN+CN/M

17.

Who's responsibility, under the SPP Document 204-B, is coordination adn supervision, cost and time control , quality control of work and keeping of records?

a)

Architect

b)

Construction Supervisor

c)

Contractor

d)

Construction Manager

18.

All contract documents are who's property?

a)

Owner/client because he/she paid for it

b)

Engineer

c)

Project Manager

d)

Architect

19.

What is SPPCC?

a)

Specification of Project Per Construction Cost

b)

Statement of Probation Project Construction Cost

c)

Statement of Project Probable Construction Cost

d)

Statement of Probable Project Construction Cost

20.

SPP Document that deals with specific expertise for further enhancement of the architectural interior and exterior components of a project.

a)

SPP Doc 202

b)

SPP Doc 203

c)

SPP Doc 204-a

d)

SPP Doc 204-b

21.

Services that involves the detailed planning and design to control sound transmission for compatibility with the architectural design concept,

a)

Acoustic Design

b)

Acoustical Design

c)

Sound transmission Design

d)

Specialized Acoustical Design

22.

Specialized Architectural services that involves space planning, architectural lay-outing and utilization of space within and surrounding a specific building/structure in relation with the existing natural and/or built environment.

a)

Comprehensive Site Development Planning

b)

Site Development Planning

c)

Site and Physical Planning

d)

Comprehensive Development Planning

23.

Service that are based on the concept of expanded physical planning services to include other activities necessary for the proper handling of the numerous components considered in the formulation of Master Development Plan

a)

Comprehensive Development with Planning Services

b)

Comprehensive Design Services

c)

Comprehensive Development Planning Services

d)

Comprehensive Development of Site Planning

24.

The Architect in this area of practice undertakes a scientific study on the built environment's well being, which allows the Architect to focus on the ways in which the building can best maintain itself and prolong it's life in a cost efficient manner

a)

Environment Architecture

b)

Appraisal Value

c)

Special Building Architecture

d)

Forensic Architecture

25.

The guaranteed bond is equal to how many percent of the contract price?

a)

30%

b)

50%

c)

75%

d)

80%

26.

How many days upon written notice can a contractor terminate a contract with a valid reason?

a)

7 days

b)

12 days

c)

15 days

d)

30 days/1 month

27.

A contract provision setting forth the damages a party must pay in the event of his breach

a)

Contract Pond

b)

Payment Bond

c)

Penalty Clause

d)

Notice of Penalty

28.

When rendering service as an expert witness, the architect is compensated by how much?

a)

200/ appearance

b)

500/ appearance

c)

1500/ appearance

d)

5000/ appearance

29.

What is under group 6 project classification?

a)

Housing

b)

Residential

c)

Repetitive

d)

Monumental

30.

A price given by a contractor, sub contractor, material supplier or vendor to furnish material, labor or both

a)

Fixed Price

b)

Quotation

c)

Quotation Receipt

d)

Price List

31.

A statute specifying the period of time within legal action must be brought for alleged damage or injury.

a)

Statutory Bond

b)

Statute of Liberty

c)

Statute of Limitation

d)

Statutory bond

32.

The person granting a possessory interest in buildings, property, etc. by lease

a)

Lesse

b)

Leasehold

c)

Lease

d)

Lessor

33.

Who shall have the responsibility of securing, but not liable for non-issuance of the final occupancy permit?

a)

Architect

b)

Engineer

c)

Owner

d)

Contractor

34.

Architect's fee for buildings of exceptional character and complexity of plan/design. DAEDS

a)

7%

b)

8%

c)

6%

d)

12%

35.

What is PRC?

a)

Professional Regulatory Commission

b)

Professional Regulation Commission

c)

Project Regulation Commission

d)

Professional Regulation Committee

36.

What is RA 9266?

a)

Intellectual Property Code

b)

National Building Code

c)

Architecture Law of 2004

d)

Accessibility Law

37.

Under what scope of services the Architect prepares technical specifications describing type and quality of materials?

a)

Bidding and Negotiation Phase

b)

Schematic Design Phase

c)

Design Development Phase

d)

Contract Document Phase

38.

The selection committee may visit buildings designed by the Architects and check references such as former clients and financial institutions

a)

Verification

b)

Pre-qualification

c)

Interview

d)

Negotiation

39.

The architect determines the adequate size and appropriate configuration for a proposed project

a)

Space Management Studies

b)

Architectural Programming

c)

Space Planning

d)

Space Allocation

40.

This method of compensation is used for government projects

a)

MDPE

b)

PCC

c)

Proffesional Fee pluss expenses

d)

Lump Sum or Fixed Fee

41.

When a client calls upon an Architect to give oral or written advice

a)

Professional Advice

b)

Consolation

c)

Consulation

d)

Consultation

42.

Method of compensation used where there is a continuing relationship involving series of projects

a)

MDPE

b)

Mixed Methods of Compensation

c)

Personal Fee Plus Expenses

d)

Professional Fee Plus Expenses

43.

Minimum basic fee of Direct Architectural Design projects for residential?

a)

6%

b)

7%

c)

8%

d)

10%

44.

Which of the following projects is under group 7 of project groups?

a)

Monuments

b)

Housing

c)

Warehouse

d)

Marina

45.

Architects fee upon signing the service agreement

a)

25%

b)

50%

c)

10%

d)

5%

46.

How much percent of professional fee is for Architect's Liability under construction phase

a)

10%

b)

5%

c)

15%

d)

8%

47.

Fee for periodic construction supervision (percentage from PCC)

a)

5%

b)

10%

c)

15%

d)

None. Because It is a separate fee from PCC

48.

What is the SPP Doc 204-A

a)

Specialized Architectural Services

b)

Construction Management Services

c)

Full time construction Supervision

d)

Regular Design Service

49.

Which among project belongs to group 2

a)

Bowlodromes

b)

Hotels

c)

Stadia

d)

Hangars

50.

Which among the projects belong to group 5

a)

Mortuaries

b)

Marinas

c)

Fair Buildings

d)

Restaurants

51.

What act does the RA 9266 re appealed?

a)

RA 545

b)

RA 9265

c)

RA 9514

d)

RA 845

52.

What is SEC?

a)

Security and Exchange Commission

b)

Security and Exchange Committee

c)

Safety and Exchange Commission

d)

Security and Economic Commission

53.

What is considered as the IAPOA?

a)

PRC

b)

PRBOA

c)

UAP

d)

Board of Architecture

54.

Who have the power to revoke certificate of registration, special permits and personal identification cards or architects

a)

PRC

b)

PRBOA

c)

UAP

d)

Building Official

55.

If a person/s falsely impersonate any registered and licensed architect, what is he/she guilty of?

a)

Magna Carta

b)

Fraud

c)

Slander

d)

Misdemeanor

56.

After the RA 9266 is passed and approved, when is the effectivity of the Act?

a)

It is effective the moment it is approved

b)

10 days after publication in the official Gazette

c)

After it is published in atleast 1 major newspaper

d)

15 days after publication in the official Gazette

57.

An Architect who is professionally and academically qualified and with exceptional expertise in any branch of architecture

a)

Architect of Record

b)

Consulting Architect

c)

Architect in Charge of Specialty

d)

Architect

58.

The architect shall receive how much percent of SPCC for the design development of the project?

a)

5%

b)

15%

c)

20%

d)

50%

59.

Means to purchase and/or fabricate and deliver to jobsite

a)

Furnish

b)

Provide

c)

Install

d)

Procure

60.

Written or printed description of work to be done describing the materials to be used

a)

Specification

b)

Working drawings

c)

Proposal

d)

Schedule