Plant Operation Chapter 7

Total questions: 10

Worksheet time: 20mins

Name
Class
Date
1.

Select two (2) situation required a shutdown activity in process plant.

a)

Major equipment problems

b)

Business downturn

c)

Touch up painting

d)

Sampling and sample analysis

2.

Select two (2) main reasons accident and injury occur during shutdown process

a)

Production exceeds product sales

b)

the increased potential for chemical exposure

c)

the less of work being done

d)

time pressure created by these situations

3.

Select the alternative action to be taken when hazards cannot be eliminated during the shutdown activities

a)

Procedures must be created, to include hazard avoidance or hazard prevention in existing procedures

b)

The operators and technicians are sent to other division

c)

Reduces the production off-specification product

d)

Reported to the lead technician or the shift supervisor

4.

Select two (2) hazards of unit shut down

a)

Mixing of air and hydrocarbon to form explosive mixture

b)

High temperature

c)

Inadequate lighting

d)

Thunderstorms

5.

Select the correct activities in preparation phase for unit shut down

a)

Management determines what repair work and upgrades are to be done 

b)

Unit feed and temperatures are slowly decreased to prevent damage from thermal shock

c)

After all hydrocarbons have been pumped out or drained from piping and vessels, purge with an inert gas

d)

Insert blinds, aerate and use gas detectors to check the lower explosive limits (LEL)

6.

Select the correct activities in shutdown phase for unit shut down

a)

Unit vessels and piping are deinventoried as much as possible to recover all unit hydrocarbons

b)

Engineering planning, diagrams and so on are completed on repair and project work for the turnaround

c)

Prepare shutdown procedures, blind lists and check off lists are verified as up to date

d)

Logistics of materials, supplies, and tools needed for shutdown are determined

7.

Select two (2) the materials that will be eliminating due to purging process

a)

Flammable material

b)

Toxic material

c)

Infectious material

d)

Non toxic material

8.

Select two (2) benefits of using steam as inert gas while purging process

a)

Removal of air

b)

Evaporation of water trapped in equipment

c)

Vapourizing heavy liquids

d)

Environmentally benign

9.

(a)   are metal plates that completely block flow in piping and vessels

10.

Select the correct purpose to prepare blind list.

a)

To ensure all required blinds have been installed before anyone enters equipment

b)

To protect personnel and equipment from explosions and fires

c)

To protect all sorts of equipment from the effects of water and sun.

d)

To control the purchasing of products and services from external suppliers