Plant Operation Chapter 8

Total questions: 12

Worksheet time: 24mins

Name
Class
Date
1.

(a)   is a scheduled shutdown of a processing unit for major repairs and or upgrades.

2.

Select the correct purpose of unit turnaround.

a)

To open, inspect, and repair all equipment in a process unit that cannot be worked on while the unit is running

b)

To assuring that all systems are designed according to the operational requirements

c)

To check of functional operability of elements within the system to achieve a state of readiness

d)

To sourcing and acquiring the goods and services a company needs to fulfill its business model

3.

Select two (2) critical objectives during unit turnaround

a)

Complete the TAR in the shortest possible time

b)

Achieve the best quality of workmanship

c)

Complete the TAR at the higher possible cost

d)

Execute the TAR with the highest possible accident record

4.

Select two (2) criterias to successfully perform unit turnaround

a)

Schedule

b)

Budget

c)

People

d)

Environment

5.

Select two (2) responsibilities for operational person during turnaround planning

a)

Detailed work lists

b)

Checklists for lockout/tagout

c)

Verify good unit housekeeping

d)

Verify flanges are tightly bolted

6.

Select two (2) activities to be completed during final turnaround planning.

a)

Schedule and conduct pre-TAR meetings

b)

Review environmental compliance procedures

c)

Introduce process materials into the unit

d)

Verify unit product is on specification

7.

Select two (2) activities to be conducted during the last few weeks before turnaround

a)

Pipe that will be removed during the TAR needs to be marked

b)

Blinds and gaskets need to be spotted in the field

c)

Check that the instrument air is clean and dry

d)

Verify all systems are air-free and pressure tested

8.

Select two (2) planned work category for the maintenance group during unit turnaround.

a)

Testing and inspection

b)

Installing new equipment

c)

Administrative work

d)

Research and development

9.

Select two (2) equipment to be repaired or cleaned during preventive equipment maintenance

a)

Polymer separators coated with gel

b)

Cooling towers with fouling problems

c)

Civil structured damaged

d)

Logistic and transportation services

10.

Select two (2) factors that contribute rash accidents during turnaround.

a)

Maintaining the TAR schedule creates a hurry up and get it done work attitude

b)

Working conditions are crowded and confusing

c)

A few number of contractors are involved in the TAR work

d)

Avoiding personal protective equipment

11.

Select two (2) correct practices to maintain good housekeeping as part of safety concern

a)

All refuse is to immediately be placed in waste containers.

b)

Sewer drains clogged or choked increase the danger of fires and should be cleared

c)

Fire lanes should be obstructed at all times

d)

All spills, no matter how small, to be cleaned up after repair work is done

12.

Select two (2) methods to evaluate the successfully of turnaround.

a)

Determine if accidents occur and people are injured during the TAR

b)

Unit performance must be measured to determine if the improvements that were planned is achieved

c)

Determine the TAR cost must on over budget

d)

Determine the actual TAR length must exceed the scheduled time objective.