TOPIC 4 MONITORING CONTRACT PERFORMANCE

Total questions: 8

Worksheet time: 2mins

Name
Class
Date
1.

Which of the following is Role of Contract Administrator

a)

To make regular site visits to the project, record observations compliance with the contract documents

b)

To be responsible for the full and timely administration of all project-related documents, paperwork transmission and project information

c)

To represent the employer/client/owner in all project meetings and other field matters relating to the construction of the project

d)

All of the above

2.

When should we start monitoring contractor performance?

a)

From date before possession of site

b)

During the construction of the project

c)

From date of possession of site

3.

Who is the personnel in charge for site visit to make sure the project compliance with the Contract Documents ?

a)

Project manager

b)

Site engineer

c)

Contract administrator

d)

Client

e)

Site supervisor

4.

In frequency and nature of checks, if at any time it is discovered that the contractor is behind schedule he must ?

a)

Immediately speed up work

b)

Identify the causes of delay

c)

Revise the work programme and resubmit for approval

d)

All of the above

5.

Which of the following is false during the handover various contract documents on the site possession meeting ?

a)

The letter of delegation of powers

b)

A copy of contract documents

c)

A priced copy of the B.Q

d)

A set of construction drawings

e)

Claim procedures

6.

What is the participant of project management meeting?

a)

Contractor

b)

Contractor & Consultant

c)

Contractor, Consultant & Client

d)

Consultant & Client

7.

What is the issue will be discussed in NSC coordination meeting

a)

Design and work & Financial

b)

Financial & Issues involving 3rd party parties

c)

Design and work, Financial & Issues involving 3rd party parties

d)

Issues involving 3rd party parties & Contract administration

8.

Site records must be properly prepared and endorsed/signed off immediately on preparation by site agent or contract administrator or sub-contractor’s representative. Site records consist of ?

a)

Weather condition of specific day

b)

List name of labor

c)

Safety regulations

d)

Financial issues