1.

The lowest part of a structure which transmits the load to the soil is known as....

a)

(a) super -structure

b)

(b) plinth

c)

(c) foundation

d)

(d) basement

2.

When the foundation is placed immediately beneath the lowest part of the Super-structure, it is called (a)   Foundation.

3.

A foundation consisting of thick reinforced concrete slab covering the entire area of the bottom of the structure, is known as......

a)

(a) pile foundation

b)

(b) pier foundation

c)

(c) raft foundation

d)

(d) machine foundation

4.

The function of lintel is......

a)

(a) To protect from rain and sun rays

b)

(b) To transfer load of wall above openings on side walls

c)

(c) To protect from capillary water.

d)

(d) To transfer load of superstructure on foundation

5.

Foundation for steel structure is normally......

a)

(a) Column footing

b)

(b) Pile foundation

c)

(c) Raft foundation.

d)

(d) Grillage foundation.

6.

The load is transferred to the foundation in framed structure in the following sequence

a)

a)Beam-Column-Foundation-Slab

b)

b) Slab-Column-Beam-Foundation

c)

c) Slab-Beam-Column-Foundation

d)

d) Column-Slab-Beam-Foundation