Total questions: 25
Worksheet time: 8mins
A statue specifying the period of time within which legal action must be brought for
alleged damage or injury
Performance bond
Statue of Limitation
Written notice
None of these
A price given by a contractor, sub-contractor, material supplier or vendor to furnish
material, labor or both
Bidding
Quotation
Price list
Bill of quantity
Which of the following methods of compensation is not covered by UAP Document
208?
Percentage of construction cost
Commission on cost of materials
Multiple of direct personnel expense
Per diem plus reimbursable
It is the binding resolution of disputes by one or more neutral persons as a
substitute for judicial proceeding.
Agreement
Arbitration
Bid Bulletin
Proposal
In design-build services, the single point responsibility of project delivery puts the
legal liability for both the design and construction on the
Designer
Architect
Contractor
Client
How many days shall the building official issue a certificate of occupancy after final
inspection of the project
5 days
15 days
30 days
120 days
What type of specifications specifies a number corresponding to a number in a
published specification?
Performance specifications
Reference specifications
Descriptive specifications
Multi-product specifications
The third phase of an architects regular services
Schematic Design Phase
Design Development Phase
Contract Documents Phase
Construction Phase
For interior design services, the architect shall be paid what percentage of the fee
upon submission of the final design
25%
50 %
75%
100%
How many sets of drawings and specifications will the owner furnish the contractor
free of charge?
2 sets
3 sets
5 sets
1 copy only
All except one of these are documents for bidding
General conditions
Technical specification
Instructions to bidders
Invitation to bid
Comprehensive planning falls under what service of the architect
Design services
Specialized allied services
Comprehensive planning
None of these
One of the methods of compensating the services of the architect, which is
applicable only to non-creative work such as accounting, supervision and data
gathering
Professional plus reimbursing expenses
Multiple of direct personnel expenses
Per Diem plus reimbursable expenses
Percentage of construction cost
The minimum basic fee for specialized decorative building
6 %
7%
10%
12%
A method of selection most often employed by committees representing
institutions, corporations and government agencies.
direct selection
comparative selection
design competitions
none of the above
It is supervised by the architect and the structural engineer.
Finishing
Concreting
Reinforcements
Excavation
When the owner fails to implement the plans and documents for construction as
prepared by the architect, the architect is entitled to receive what percentage of the
fee upon submission of the final design
25%
50%
85 %
100%
Architect’s minimum fee for Group 5 projects that include monumental buildings
and other facilities requiring consummate design skill and much precise detailing.
12% of project construction cost
5% of project construction cost
10% of project construction cost
14% of project construction cost
Architects fee for furniture and cabinets detailing.
6%
10%
12%
15%
Under PD 1185 or Fire Code of the Philippines, a term use as any act that would
remove or neutralize a fire hazard.
Blasting agent
Curtain board
Abatement
Flash point
The person granting a possessory interest in building, property, etc. by lease
Lessor
Lesse
Tenant
Client
The fee of the architect for design-build services on a guaranteed maximum cost
aside from his fee for regular design services
6%
10 %
12%
15%
Name the new Architecture Law
RA 9160
RA 545
RA 9266
RA 546
The person receiving a possessory interest in buildings, property, etc. by lease
Lessor
Lesse
Tenant
Client
In a CPM, the maximum amount of time that an activity can be delayed without
exceeding the completion time of the whole project
Free float
Maximum float
Total float
Absolute float