Hot Work Quiz

Total questions: 15

Worksheet time: 9mins

Name
Class
Date
1.

How many Hot Work Permits can be used per day?

a)

1 Hot Work Permit

b)

2 Hot Work Permits

c)

3 Hot Work Permits

d)

4 Hot Work Permits

2.

Up to how long the inspection round must be carried out?

a)

Up to 1 hour after work

b)

Up to 2 hours after work

c)

Up to 3 hours after work

d)

Up to 4 hours after work

3.

Types of Hot Work Activities.

Select 3 answers.

a)

Electrical Work

b)

Milling

c)

Cutting

d)

Welding

e)

Grinding

4.

Do Hot Work activities generate Heat, Sparks, Smoke and Fire?

a)
b)
5.

Do the hot work operator always have a copy of the hot work permit with him?

a)
b)
6.

Who must sign a hot work permit before start the hot work? Choose 2 answers.

a)

Fire Watcher

b)

Hot work operator

c)

Supervisor

d)

Security Guard

e)

General Worker

7.

Is Hot Work in or near an ATEX zone must ALWAYS be signed by a third party who has sufficient knowledge of ATEX zones?

a)
b)
8.

Which example of fire fighting measures to be provided during hot work?

a)
b)
c)
d)
9.

Which actions required to take if a fire start, during or after hot work?

a)

Activate Emergency Fire Alarm Button

b)

Attempt to extinguish uncontrollable fire

c)

Block Evacuation Routes

d)

Continue Hot Work

10.

How many distance should the combustible materials be removed?

a)

9 m, both around, above and below me.

b)

10 m, both around, above and below me.

c)

11 m, both around, above and below me.

d)

12 m, both around, above and below me.

11.

What to do when Combustible Materials are still present?

a)

Do not start the hot work

b)

Proceed with Hot Work

c)

Call Security Guard

d)

Wear PPE for Welding

12.

What is the responsibility of Fire watcher/Observer?

a)

Leaving the Hot Work Area

b)

Lack knowledge of correct use of the appropriate fire extinguisher.

c)

Horseplay during Hot Work

d)

Detecting, containing and extinguishing all sparks and hot debris

13.

What is the responsibility of Maintenance and contractors?

a)

Ignore Safe Work Procedure

b)

Horseplay during Hot Work

c)

Did not wear Hot Work PPE

d)

Work to the requirement of Permit To Work

14.

According to CAP Prevention, an supervisor/work planner is ANALYTICAL BY:

a)

Ignoring necessary measures to carry out the hot work safely.

b)

Knowing the good practices of hot work and regularly checking that they have been applied on site.

c)

Ensuring for up to 30 minutes after the hot work, an inspection round is carried out.

15.

According to CAP Prevention, an employee is PROACTIVE BY:

a)

Carrying out hot work without an approved hot work permit.

b)

Starting the work although the situation is not safe.

c)

Reporting any situation in which hot work cannot be safely.