Line Balancing

Total questions: 10

Worksheet time: 5mins

Name
Class
Date
1.

The Production rate of an assembly line is determined by its

a)

Slowest station

b)

Fastest station

c)

Idle station

d)

None of these

2.

General principles of Design For Assembly includes

a)

Use the fewest number of parts possible to reduce the amount of assembly required

b)

Reduce the number of threaded fasteners required

c)

Standardize fasteners

d)

Reduce parts orientation difficulties

e)

All of the above

3.

Which is referred to as the bottleneck station

a)

Lead time for the entire line

b)

cycle time for the one station

c)

cycle time for the entire line

d)

Lead time for the one station

4.

Maximum service time must be

a)

No greater than the difference between the cycle time Tc and the repositioning time Tr

b)

Greater than the difference between the cycle time Tc and the repositioning time Tr

c)

Greater than the cycle time Tc and less than repositioning time Tr

d)

Greater than the repositioning time Tr and less than cycle time Tc

5.

Cycle time is not:

a)

daily operating time divided by desired production

b)

the maximum allowable time at each work station

c)

how often items roll off the assembly line

d)

the time required to complete a product from start to finish

6.

An assembly line consists of 5 tasks with times of 12, 9, 8, 7, and 11 minutes. The cycle time for the line is 25 minutes. The theoretical minimum number of workstations for this situation is

a)

1

b)

2

c)

3

d)

4

e)

5

7.

The process of equalizing the amount of work at each workstation is called precedence diagramming.

a)

True

b)

False

8.

For an assembly line if balance delay is high then efficiency will be low and vice versa.

a)

True

b)

False

9.

Automation is preferred because it:

a)

Offers lesser dependence on workers

b)

Results in reduction in variable cost

c)

Offers easy handling of repetitive work

d)

All of the above

10.

Balanced Assembly line effects in

a)

Minimizes Wastes

b)

Minimizes Idle time

c)

Reduces Variation

d)

Increases Effeciency

e)

All the above