1.
Mark the LLI gate(s) when project risks must be formulated, analyzed and mitigation be planned.
a)
L1
b)
L2
c)
LLR
2.
When does R&D first commit to develop the product for LLI?
a)
L1
b)
L2
c)
LLR
3.
What does LLI stands for?
a)
Long Lead Item
b)
Long Lead Information
c)
Long Least Item
4.
What does M2 mean?
a)
GA
b)
Release commitment
c)
R&D is ready
5.
At what M gate is R&D committing content, resources and budget?
a)
M4
b)
M1
c)
M2
6.
What is DM?
a)
Development Maturity
b)
Design Maturity
c)
Delivery Maturity
7.
What is not expected to start after DM?
a)
Release testing
b)
Pilot HW Production
c)
First Customer Shipment(FCS)
8.
What needs to be ready at M3?
a)
Transfer of Information to Service
b)
The Manuals
c)
Verification of Pilot HW
9.
What volumes do we normally in stock for HW-card at M3?
a)
5-10
b)
10-200
c)
200+
100 %