1.

If your grid size is 40 ft x 20 ft, what is the area of each grid?

a)

800 sq ft

b)

80 sq ft

c)

600 sq ft

d)

60 sq ft

2.

If your Grid Area is 1600 sq ft, what is the Area constant?

a)

A/4

b)

400

c)

44

d)

4

3.

What modern ways does an estimator use to do a site takeoff? (choose all that apply)

a)

Sonic digitizer

b)

Sonic burger

c)

Tablet digitizer

d)

On Screen Takeoff

e)

SWAG

4.

To get the trench volume, the following are used to calculate

a)

centerline length, average footing width, cutback slope

b)

centerline width, deepest excavation, footing width

c)

centerline length, average width, average depth

d)

centerline length, centerline width, cutback slope

5.

On grid method, the top 2 sections denote New Grade and Existing Grade, what is shown in the bottom 2 sections?

a)

Depth of footing, width of footing

b)

Area constant, volume cut

c)

Depth of cut, depth of fill

d)

Area constant, average depth

6.

The trench excavation calculated is 300 cu. yds and the backfill amount is 180 cu. yds. How much dirt do you need to have delivered?

a)

120 cu. yds

b)

480 cu. yds

c)

0

d)

100 cu. yds

7.

If your new elevation is 5.4 ft and existing elevation is 9.4 ft. What change needs to be recorded on the grid?

a)

4 ft cut

b)

4 ft fill

c)

4.4 ft cut

d)

0

8.

Piles can be timber, steel or precast concrete

a)

True

b)

False

9.

If a vertical or near-vertical excavation needs to be done, it does not require to be supported by piles, soil nails or some other engineered method.

a)

True

b)

False