WorksheetsDelivery, Inspection & Quality
Total questions: 10
Worksheet time: 6mins
In which project delivery method, construction manager act as consultant to the owner?
Design-Bid-build
Construction Manager at-Risk
Design-Build
Construction Management Multi-Prime
Choose the correct statement.
In Design-Bid-Build the contract for design and construction is separated
In Construction Management Multi-Prime the financial risk is on the construction manager
Delivery is defined as method for assigning responsibility to an organization or an individual for providing design and construction services
In Construction Management Multi-Prime owner will choose contractors the based on project cost only
Choose types of building inspection
electrical inspection
mechanical inspection
on site inspection
specification inspection
Which of following is the correct process for carried out inspection?
receive request for inspection-inspection 1-inspection pass- receive certificate of completion
receive request for inspection-inspection 1-inspection pass-receive certificate of occupancy
receive request for inspection-inspection 1-inspection pass-inspection 2- receive certificate of occupancy
receive certificate of occupancy-inspection 1-inspection pass- inspection 2- receive request for inspection
These are the skills needed by a construction inspector except
Honest
Know how to read plans , specifications and related document
Indecisive
Have good writing skills
Choose the things that need to be inspected during inspection
Job Interface Record
Daily Inspection Record
Notice of Noncompliance
All above
It involves monitoring the work processes to ensure that they will produce good quality in final product which are laid out before the construction process started
Quality Assurance
Quality Control
Below are the 6c’s of The Total Quality Management except
Commitment, Customer focus
Cooperation, competitive
Continuous Improvement, Control
“Decide whether the proposed change is really needed and what to do next” refer to which phase in PDCA cycle?
Plan
Do
Check
Act
What is the meaning of Corrective Action?
The action taken to eliminate the cause of a potential nonconformity, defect, or other undesirable situation in order to prevent occurrence.
To monitor and track any quality issues in order to make sure there are no defects.
Steps taken to eliminate the causes of an existing nonconformity, defect or other undesirable situation in order to prevent recurrence.
Review of various aspects of a project to ensure they are performing appropriately and in keeping with the contract