Worksheets

unvented hot water

Total questions: 20

Worksheet time: 10mins

Name
Class
Date
1.

Building regulation approved document G3 states that the temperature of the water in a storage hot water system must not exceed:

a)

65 0C

b)

85 0C

c)

98 0C

d)

100 0C

2.

Building regulation approved document G3 requires notice to be given to the local authority building control by means of a building control notice unless:

a)

the installation is 250 litres or above and the individual / business is registered with a competent persons scheme for self certifying UVHW systems

b)

The individual / business is registered with a competent persons scheme for self certifying UVHW systems

c)

The system is a 'package' type

d)

The system is a 'unit' type

3.

The boiling point of water at sea level is:

a)

80 0C

b)

90 0C

c)

100 0C

d)

110 0C

4.

with reference to the chart, what is the approximate temperature at which water will boil at 2000m above seal level

a)

90 0C

b)

80 0C

c)

84 0C

d)

94 0C

5.

With reference to D2 discharge pipework, what is the minimum vertical drop from the tundish to the first change of direction

a)

50 mm

b)

150 mm

c)

300 mm

d)

350 mm

6.

What component device needs to be installed on the cold supply to an unvented cylinder to prevent grit and debris damaging other components

a)
b)
c)
d)
7.

Which type of primary circulation system can not be used to heat an unvented cylinder

a)

Fully pumped

b)

Gravity

c)

S plan

d)

Y plan

8.

What regulation covers insulation and performance of Hot water cylinders

a)

Approved document L1

b)

Approved document G3

c)

water regulations 1999

d)

Approved documents P

9.

What is fitted to the bottom of a cylinder to help prevent corrosion ?

a)

Sacrificial anode

b)

Sacrificial cathode

c)

Brass Block

d)

Air vent

10.

At what height should a thermostat be fitted on a cylinder?

a)

1/3 from the top

b)

1/3 from the bottom

c)

1/2 way up

d)

In the middle

11.

Building Regulations part G now states that hot water delivered to a bath should not exceed?

a)

43

b)

48

c)

38

d)

60

12.

This picture shows a?

a)

Temperature pressure relief valve

b)

Pressure relief valve

c)

Blending valve

d)

Immersion stat

13.

This picture shows a?

a)

Temperature pressure relief valve

b)

Pressure relief valve

c)

Blending valve

d)

Immersion stat

14.

It is important that the height of the open vent pipe over the CWSC is measured correctly this is done by?

a)

150mm + 40mm per metre of system height (m)

b)

100mm + 50mm per metre of system height (m)

c)

150mm + 50mm per metre of system height (m)

d)

100mm + 40mm per metre of system height (m)

15.

What is the maximum length of dead leg for a 15mm or 22mm pipe before a secondary return system has to be installed?

a)

5m

b)

8m

c)

10m

d)

12m

16.
The connection for a secondary circulation system return should be made at what point in the hot water cylinder?
a)
Bottom third of the cylinder
b)
Top third of the cylinder
c)
Middle point of the cylinder
d)
Just prior to the open vent connection
17.

The two port motorized valve fitted to the primary flow on a UVHW cylinder must be wired in series with the energy cut off thermostat:

a)

True

b)

false

18.

A UVHW cylinder supplied as a package has all safety devices factory fitted with all other components supplied loose.

a)

True

b)

False

19.

A UVHW cylinder supplied as a unit has all safety and other functional devices factory fitted.

a)

True

b)

false

20.

A sacrificial anode does what?

a)

prevent hard water

b)

soften water

c)

fail safe in the event of overheat

d)

corrode instead of the vessel corroding