CONTRACT MODIFICATION & CHANGE ORDER

Total questions: 11

Worksheet time: 8mins

Name
Class
Date
1.

Below are the statement of purposes of writing changes orders, except;

a)

Change contract plans and/or specifications

b)

Make adjusments in compesantion

c)

Clarify term of the contract

d)

Discussion between parties to

determine who is right or wrong

2.

What is the meaning of the term "Change Order"?

a)

unprecedented times

b)

client has to pay for the damage

c)

the client adds or deletes something from the approved blueprint

d)

unforeseeable circumstances that prevent someone from fulfilling a contract

3.

What make a project do the normal change order? (choose 3)

a)

Error in contract documents

b)

Unexpected site condition

c)

To detecting flaws in a project

d)

Changes requested by the client

4.

In what situation eligible to do emergency change order?

a)

Sinkhole at construction site

b)

Contractor build inaccurate specification

c)

Additional of door that are not available in early design

d)

Bad soil condition

5.

What are characteristics of unilateral contract modification? (choose 2)

a)

Signed by contracting officer

b)

A promise by one party in exchange for an action by another party

c)

A supplemental agreement

d)

Signed by both contractor and contracting officer

6.

"Protect Historical or archeological monuments" , which common causes fit for statement above?

a)

Differing Site Condition

b)

Error and Omission in plans and specification

c)

Changes institute by regulatory agencies

d)

Cost Estimation

7.

Conditions to issue a change order are(choose 3):

a)

If the method of performance is not proper

b)

If the estimated cost of the project is not according to contract agreement

c)

If the work performance is going to be according to contract document.

d)

If the plan and specification of the project is defective

8.

When is changes by change order occur?

a)

After completion of construction

b)

After sign agreement

c)

After advertising date

d)

After award date

9.

Which of the following statements referring to contract modification? (choose 2)

a)

Contracting officer prepared the documentation and signed by contracting officer and owner

b)

The document prepared by the architect and signed by the architect, owner, and contractor

c)

Any written changes according to term and condition

d)

Can be either written or oral , with some exceptions

10.


 X=b±(b24ac)2aX=\frac{-b\pm\sqrt{\left(b^2-4ac\right)}}{2a} 
Not referring to equation above, what are the purposes of notification of contract changes? (choose 3)

a)

Confirm that it is a change, direct the mode of further performance, and plan for its funding

b)

Countermand the allenged change

c)

Notify the contractor that no change is considered to have occured

d)

Describe the performance problems and attach documents

which support the conclusions

11.

On 30th December 2020, Perunding Seri Yakin has been awarded a contract on "Projek Menaiktaraf Terminal Wawasan (Pusat Bandar) Kota Kinabalu, Sabah". What changes can be issued during the award date?

a)

No changes can be issued

b)

Changes by change order

c)

Changes by Addende

d)

Changes by field order