WorksheetsCONTRACT MODIFICATION & CHANGE ORDER
Total questions: 11
Worksheet time: 8mins
Below are the statement of purposes of writing changes orders, except;
Change contract plans and/or specifications
Make adjusments in compesantion
Clarify term of the contract
Discussion between parties to
determine who is right or wrong
What is the meaning of the term "Change Order"?
unprecedented times
client has to pay for the damage
the client adds or deletes something from the approved blueprint
unforeseeable circumstances that prevent someone from fulfilling a contract
What make a project do the normal change order? (choose 3)
Error in contract documents
Unexpected site condition
To detecting flaws in a project
Changes requested by the client
In what situation eligible to do emergency change order?
Sinkhole at construction site
Contractor build inaccurate specification
Additional of door that are not available in early design
Bad soil condition
What are characteristics of unilateral contract modification? (choose 2)
Signed by contracting officer
A promise by one party in exchange for an action by another party
A supplemental agreement
Signed by both contractor and contracting officer
"Protect Historical or archeological monuments" , which common causes fit for statement above?
Differing Site Condition
Error and Omission in plans and specification
Changes institute by regulatory agencies
Cost Estimation
Conditions to issue a change order are(choose 3):
If the method of performance is not proper
If the estimated cost of the project is not according to contract agreement
If the work performance is going to be according to contract document.
If the plan and specification of the project is defective
When is changes by change order occur?
After completion of construction
After sign agreement
After advertising date
After award date
Which of the following statements referring to contract modification? (choose 2)
Contracting officer prepared the documentation and signed by contracting officer and owner
The document prepared by the architect and signed by the architect, owner, and contractor
Any written changes according to term and condition
Can be either written or oral , with some exceptions
Not referring to equation above, what are the purposes of notification of contract changes? (choose 3)
Confirm that it is a change, direct the mode of further performance, and plan for its funding
Countermand the allenged change
Notify the contractor that no change is considered to have occured
Describe the performance problems and attach documents
which support the conclusions
On 30th December 2020, Perunding Seri Yakin has been awarded a contract on "Projek Menaiktaraf Terminal Wawasan (Pusat Bandar) Kota Kinabalu, Sabah". What changes can be issued during the award date?
No changes can be issued
Changes by change order
Changes by Addende
Changes by field order