#6 in English system of measurement for Reinforcing Bar is ________ of metric system equivalent.
12mm diameter
14mm diameter
16mm diameter
20mm diameter
Size of Rebar used for Stirrup:
8mm diameter
10mm diameter
12mm diameter
16mm diameter
Lateral ties is for ________.
Circular Column
Tied Column
Beam
Girder
Stirrups is for ____________.
Beam
Circular Column
Footing
Tied Column
Class B mix
1: 1.5: 3
1: 2: 3
1: 2: 4
1: 2.5: 5
Aluminum
Cool- rolled sheet
Non ferrous metal
Ferrous metal
Copper
One (1) cubic foot equivalent
0.567 cu.mtr.
0.0283 cu.mtr
0.0567 cu.mtr.
0.305 cu. mtr
1- Cu.Mtr. concrete having Class 'A' mix
6 bags of Cement
7 bags of Cement
8 bags of Cement
9.2 bags of Cement
Slab on Fill mix
Class A
Class B
Class C
It Depends
Minimum commercial length of Reinforcing Bars
12 ft.
5.0 m
6.0 m
21 ft.
Estimating method where size multiplied by a factor:
Quantity survey
Cubic Meter
Square meter
Linear meter
Estimating method which is normally used in earthworks, civil works, and ACU air:
Square Meter
Cubic Meter
Parametric method
Linear meter
Estimating method which found by multiplying the area of space times a cost factor:
User unit
Square meter
Linear method
Cubic meter
Estimating method which includes the description of a complete take-off of all materials in the project
User unit
Square meter
Quantity survey
Cubic meter
A method of estimating wherein cubage provides the basis for costs:
User unit
Square meter
Quantity survey
Cubic meter
Minimum diameter size of vertical bars for column spaced at 3.0m for Bungalow type structure:
8mm
10mm
12mm
16mm
A shortened type of horizontal support being attached and protruded to the side of the upper part of column used to hold horizontal structures:
Lintel beam
Post strap
Corbel
Floor beam
Minimum number of vertical bars for tied column of a bungalow type structure
3
4
5
6
Minimum diameter size of Main rebars for tied column footing for a Two-storey structure:
10mm
12mm
16mm
20mm
If concrete pouring for columns will stop, it shall be located:
Middle Part of Column
Before the Mid
Before the Beam
None @ All
If concrete pouring for beams will stop, it shall be located:
Within its L/4
Within the Midspan
Before the column
Before the L/5
1-Ton equivalent
2000 lbs
2200 lbs
2500 lbs
3000 lbs
none @ all
Type of load created by wind pressure:
Lateral load
Air load
Moving load
Live load
A type of load created by vehicles:
Moving load
Lateral load
Live load
Wheel load
Two cubic feet value in metric equivalence:
0.305 cube
0.093 m3
0.057 m3
0.06 m3
How many bags of cement required for 1 m3 concrete class A mix
7-bags
8-bags
9.2-bags
12-bags
Weakest Concrete mixture:
1:2:3
1:2:4
1:3:6
1:2.5:5
1-bag of cement approx. 1-cu.ft. is equivalent to ________:
0.0284 m3
0.305 m3
1-cu. yard
none @ all
1- meter is how many inches:
39.37"
100 centimeter
36"
40"
General condition is described under:
Substructure
Shell
Interior
Services
Minimum interval of rebars on the R.C. Structure
1/2 inch
1 inch
2 inches
3 inches
Free-fall ratio of a chute to avoid
concrete aggregates segregation:
1 is to 2
2 is to 3
. 1.5 is to 2.5
1 is to 3
Conveys concrete by means of air pressure:
Concrete Buggy
Hoist Bucket
Pump Crete
Transit Mixer
Water ratio tests for a fresh concrete
mixture:
Compression Test
Slump Test
Slurry Test
Boring Test
Used to check the horizontal level of
one object to the other in a distant:
Plumb Bob
Hand Level
Hose Level