WorksheetsMachine Availability & Reliability
Total questions: 20
Worksheet time: 5hrs 0mins
Which of the following is NOT part of the 4 new tasks that Autonomous Maintenance practice introduces to the Operation?
Apply new analysis tools
Support to develop new equipment
Educate and train operators
Develop know-how to become a specialist
Learn how to operate the machine
There are 7 types of Abnormalities as above list. From the options below, choose the abnormality that is missing.
Source of cleaning
Source of contamination
Source of breakdown
Source of Abnormality
Source of Repair
Which of the following is NOT an objective from carrying out cleaning/ inspection when implementing AM?
Prevent forced deterioration
Expose hidden abnormalities
Trace sources of dirt, dust, etc.
Detect abnormalities
Identify machine lifespan
From the list below select the reaction that is most likely NOT caused when a machine incurs problems :
Overtime
Fire Fighting
Progress chasers
Flexibility
Additional Shifts
Autonomous Maintenance is applied to identify 2 types of deterioration, Natural Deterioration & Forced Deterioration. From the list below, select the reason that DO NOT contribute to Forced Deterioration :
Design Weakness
Corrosion
Environment
Failure to maintain basic conditions
Conditions of use not needed
Choose the best sentence to define changeover time?
The time from running the last product to the time of running the current product
The time between the machine was functional to the time the machine breakdown
The time from running qualified product at the standard rate of the last batch to running qualified product at the standard rate of the next batch
The time from running the machine when operation start to the time when the machine is switched off upon completion of the operation
The time between startup of the operation until the time the operations ends for the day
Which of the following are Tools used for improving the changeover process?
Spaghetti Diagram
Action Log
Changeover Checklist
Video camera and stopwatch
All of above
Which is the following is one of the key QCO step?
5S
Visual Management
Autonomous Maintenance
OEE
Optimize internal & external activities
From the list below, select 2 benefits of implementing Quick Change Over (QCO)?
Increases production time
Improves 5S
Detects abnormality
Increases flexibility
Improves safety
Which of the following is NOT a benefit from improving OEE?
Greater system availability
Reduced cycle time
Reduced number of workers
Reduced cost of operation
Reduced inventories
Machine Availability = 99%
Machine Performance = 98%
Quality = 95%
Operation Cost = 92%
RFT = 99%
Calculate the OEE for the above operation :
92%
85%
89%
96%
86%
OEE is a method to measure the efficiency of the equipment in an operation. From the below, select a situation where OEE is not recommended :
OEE is a tool to analyze, and improve your production process
OEE measures inefficiencies and groups them to aid with analyzing the machine
OEE data focuses on factors that adversely affect the value of a machine.
The OEE rate is the maximum potential which a machine can produce set in proportion to the actual value-added time
OEE should be measured on a brand-new equipment to determine the return of investment on this equipment
Select from list below the missing step in Reliability Based Maintenance implementation process according to the order showed above :
Autonomous Maintenance
Improves 5S
Define Asset Criticality
Measure OEE
Improves Quality
Based on the Maintenance Strategy chart provided, which is the correct Maintenance strategy in the blue column?
High Risk – Corrective Action
High Risk – Preventive Maintenance
Low Risk – Preventive Maintenance
Moderate Risk – Predictive Maintenance
Moderate Risk – Corrective Maintenance
In the right sequence, list down the 3 types of Maintenance Strategy defined in RBM?
Corrective, Preventive, Predictive
Preventive, Predictive, Corrective
Predictive, Preventive, Corrective
Corrective, Predictive, Preventive
Correction, Prevention, Prediction
Which of the following defines Risk?
Risk equals the result of the consequence multiplied by the probability the event will occur
Risk equals the result of the availability multiplied by the probability the event will occur
Risk equals the result of the occurrence multiplied by the probability the event will occur
Risk equals the result of the consequence multiplied by the accuracy the event will occur
Risk equals the result of the consequence multiplied by the repeatability the event will occur
Investments are defined into 2 categories. List the missing type of Investment :
1. ___________________________
2. Offensive Investment
Defensive Investment
Investment Decision
Defenseless Investment
Defective Investment
Investment Opportunity
Project A - Decision to be taken within the limits of total investment
Project B - Immediate decisions to be taken, realization in short term & within budget
Project C - Immediate actions to stop a critical situation
For the projects listed above, prioritize the projects in the category of High, Medium and Low risk :
A, B, C
C, B, A
A, C, B
B, C, A
C, A, B
Which of the following if NOT a benefit of carrying out Risk Based Project Selection?
Site Investment Evaluation
Risk Evaluation
Fit to Business Strategy
Fit to Operations and Footprint strategy
Cost avoidance
Choose from the list below, the basic requirement before implementing Reliability Based Maintenance?
5S
Equipment Master List
Visual Management
Autonomous Maintenance
OEE