Scheduling Quiz - Forecast & Resources

Total questions: 10

Worksheet time: 6mins

Name
Class
Date
1.

An activity duration is 5 days and the total cost for that activity is $35,000. What is the daily rate of that activity?

a)

$7,000

b)

$5,000

c)

$6,000

d)

The daily rate cannot be calculated

2.

A crew of 5 requires 4 days to complete a task. The daily rate for each member is $1,000. What would be the total labor cost for the activity?

a)

$10,000

b)

$5,000

c)

$20,000

d)

$4,000

3.

Changing the duration of a critical activity will not affect the overall completion time.

a)

True

b)

False

4.

The backward pass calculation cannot proceed if the forward pass had not completed.

a)

True

b)

False

5.

The LS and LF is the result of forward pass calculation.

a)

True

b)

False

6.

Activities on critical path will have float.

a)

True

b)

False

7.

The S-curve is used to illustrate cumulative costs of a project rather than daily or weekly costs.

a)

True

b)

False

8.

Which US President established Thanksgiving as a national holiday in 1789?

(a)  

9.

The following scheduling methods are used to assess total costs, labor resources and daily costs on a project (choose all that apply)

a)

Logic chart

b)

S-curve

c)

Histograms

d)

Bar chart for Owner

10.

If you have $30,000 worth of material & labor used up on a project and the total cost of the project is $120,000, what percent complete would you be?

a)

30%

b)

40%

c)

25%

d)

75%