Section 4- Project Integration Management

Total questions: 19

Worksheet time: 10mins

Name
Class
Date
1.

48.Which of the following processes is included in Project Integration Management?

a)

A. Develop project management plan.

b)

B. Control scope definition.

c)

C. Review scope validation.

d)

D. Conduct procurement surveillance.

2.

49. All of the following are characteristics of the project charter EXCEPT :

a)

A. It formally authorizes the existence of a project.

b)

B. Projects are initiated by an entity external to the project. The project initiator or sponsor should be at the level that is appropriate to procure funding and commit resources to the project.

c)

C. It is used primarily to request bids for a project or a specific phase of a project.

d)

D. It provides the project manager with the authority to apply organizational resources to project activities.

3.

50.All of the following are characteristics of the Project Management Information System (PMIS) EXCEPT :

a)

A. Automated gathering and reporting on key performance indicators (KPIs) can be part of this system.

b)

B. It provides access to information technology (IT) software tools, such as scheduling soft ware tools, work authorization systems, and configuration management systems.

c)

C. It is used as part of the Direct and Manage Project Work.

d)

D. It is used by the project manager and the project management team primarily to generate presentations to key stakeholders.

4.

51.Which of the following is NOT true about tools and techniques of Perform Integrated Change Control?

a)

A. They include expert judgment.

b)

B. They include change control meetings.

c)

C. A change control board (CCB) is responsible for meeting and reviewing the change requests and approving, rejecting, or other disposition of those changes.

d)

D. They include project plan updates.

5.

52. You are managing a $10 million project . Which of the following is an acceptable cause for "re-baselining" this project?

a)

A. The client has approved an addition to the scope of the project with a $150,000 budget increase and a two-week extension of the scheduled completion.

b)

B. The contractor’s company has instituted a quality assurance program in which it has pledged to spend $1 million during the next year.

c)

C. The productivity in the design department is lower than estimated, which has resulted in1,000 additional hours over what was budgeted and a forecasted two-week delay of the scheduled completion.

d)

D. The engineering department of the performing organization has converted to a new $250,000 CAD system.

6.

53. Configuration management is focused on :

a)

A. The identification and correction of problems arising in functional areas of project implementation.

b)

B. The specification of both the deliverables and the processes, while change control is focused on identifying, documenting, and approving or rejecting changes to the project documents, deliverables, or baselines.

c)

C. Testing new systems.

d)

D. Identifying, documenting, and controlling changes to the project and the product baselines, while change control is focused on the specifications of both the deliverables and the processes .

7.

53. A change control board (CCB) is

a)

A.A formally chartered group of stakeholders responsible for ensuring that only a minimal amount of changes occurs on the project.

b)

B.A formal or an informal group of stakeholders that has oversight of project execution.

c)

C.A formally chartered group responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project, and for recording and communicating such decisions.

d)

D.A dashboard that provides integrated information to help control changes to cost, schedule, and specifications throughout the life of the project

8.

54.Some of the configuration management activities included in the Perform Integrated Change Control process include all of the following activities EXCEPT:

a)

A. Identification and selection of a configuration item to provide the basis for which the product configuration is defined and verified, products and documents are labeled, changes are managed, and accountability is maintained.

b)

B. Monitoring changes in resource-leveling heuristics to ensure efficient resource utilization throughout the life cycle of the project.

c)

C. Configuration status accounting, in which information is recorded and reported as to when appropriate data about the configuration item should be provided.

d)

D. Configuration verification and configuration audits that ensure that the composition of a project’s configuration items is correct and that corresponding changes are registered, assessed, approved, tracked, and correctly implemented.

9.

56.Actions and activities necessary to transfer the project's products, services,or results to the next phase or to production and/or operations are add ressed:

a)

A. As part of the Close Project or Phase process.

b)

B. Following the plan outlined in the Quality Management process.

c)

C. As requested by senior executives.

d)

D. As the last step in project management.

10.

57.Outputs of the Monitor and Control Project Work process include all of the following EXCEPT :

a)

A. Change requests.

b)

B. Project management plan updates.

c)

C. Work performance reports.

d)

D. Final product, service, or result transition.

11.

58. All of the following are inputs to Manage Project Knowledge EXCEPT :

a)

A. Deliverables.

b)

B. Knowledge management.

c)

C. Lessons learned register.

d)

D. Project management plan.

12.

59.All of the following are Knowledge Management tools and techniques EXCEPT:

a)

A. Discussion forums.

b)

B. Storytelling.

c)

C. Work shadowing and reverse shadowing.

d)

D. Regression analysis.

13.

60.Lessons learned documentation generally includes all of the following EXCEPT:

a)

A. The causes of issues.

b)

B. Updates of the statement of work to reflect training and learning requirements.

c)

C. Reasoning behind the corrective action chosen.

d)

D. Other types of lessons learned about communications management .

14.

61.All of the following are true about the project scope management plan EXCEPT:

a)

A. It enables the creation of the WBS from the detailed project scope statement.

b)

B. It describes how the scope will be defined, developed, monitored, controlled, and validated.

c)

C. It can be formal or informal, broadly framed or highly detailed, based on the needs of the project.

d)

D. It is not related to the project management plan .

15.

62. Collect Requirements is the process of determining, documenting, and managing stakeholder needs and requirements to meet project objectives. All of the following are true about this process EXCEPT :

a)

A. The project's success is directly influenced by active stakeholder involvement in the discovery and decomposition of needs into requirements and by the care taken in determining, documenting, and managing the requirements of the product, service, or result of the project.

b)

B. Requirements become the foundation of the WBS. Cost, schedule, quality planning ,and sometimes procurement are all based upon these requirements.

c)

C. The development of requirements begins with an analysis of the information contained in the project charter, the risk register, and the stakeholder engagement plan.

d)

D. Requirements need to be elicited, analyzed, and recorded in enough detail to be included in the scope baseline and to be measured once project execution begins.

16.

63.You are involved in collecting requirements for your project. You are likely to use the stakeholder register for all of the following EXCEPT :

a)

A. Identifying stakeholders who can provide information on the requirements.

b)

B. Capturing major requirements that stakeholders may have for the project.

c)

C. Capturing main expectations that stakeholders may have for the project.

d)

D. Evaluating the product breakdown structure (PBS) associated with each of the key stakeholders

17.

64. You are developing a document that links product requirements from their origin to the deliverables that satisfy them to help ensure that each requirement adds business value and to manage changes to the product scope This is known as the :

a)

A. Configuration management system.

b)

B. Business case.

c)

C. New product development matrix.

d)

D. Requirements traceability matrix.

18.

65. An output of the Define Scope process

a)

A. Work breakdown structure (WBS).

b)

B. Resource breakdown structure (RBS).

c)

C. Project scope statement.

d)

D. Scope and schedule delays control plan.

19.

66. All of the following are true about the project scope statement EXCEPT

a)

A. It is an output of the Validate Scope process.

b)

B. It describes, in detail, the project’s deliverables and the work required to create those deliverables.

c)

C. It provides a common understanding of the project scope among project stakeholders.

d)

D. It may contain explicit scope exclusions that can assist in managing stakeholder expectations .