NEW
Font size
Worksheets*Profprac
Total questions: 25
Worksheet time: 13mins
Defining open space in residential subdivision
PD 1296
PD 1298
RA 1298
RA 1296
Architectural programming is one of the architect’s services that falls under
Pre-Design Services
Regular Design Services
Specialized Architectural Services
Construction Management Services
Condominium & Subdivision, Bridges Protective Law.
PD 957
BP 220
PD975
This services giver full meaning to what the professional calls comprehensive Architectural Service. It wraps-up the whole range of architectural services.
Post-Construction Services
Construction Management Services
Fulltime Supervision Service
Specialized Architectural Services
Contract Documents shall be the property of the
Architect
Owner
Contractor
Client
Defining open space
PD 1216
PD 1612
PD 1261
PD 126
is an agreement in which each of the parties to the contract makes a promise or promises to the other party.
Bilateral Contract
Unilateral Contract
Expressed Contract
Implied Contract
only one party to the contract makes a promise.
Unilateral Contract
Bilateral Contract
Expressed Contract
Implied Contract
is one in which the terms are expressed verbally, either orally or in writing
Expressed Contract
Bilateral Contract
Unilateral Contract
Implied Contrac
is one in which some of the terms are not expressed in words.
Implied Contract
Expressed Contract
Unilateral Contract
Bilateral Contract
The _____ pays for the structural, utilities & other tests as may be required for the project.
Conctractor
Owner
Architect
Client
The fee of the architect for design-build services on a guaranteed maximum cost aside from his fee for regular design services.
10%
5%
15%
For interior design services, the architect shall be paid what percentage of the fee upon submission of the final design.
50%
30%
25%
10%
When the owner fails to implement the plans and documents for construction as prepared by the architect, the architect is entitled to receive what percentage of his fee.
85%
75%
65%
50%
The minimum basic fee for specialized decorative building.
12%
6%
8%
The minimum basic fee for industrial buildings with a project cost below 50 million pesos.
12%
6%
8%
The minimum basic fee for hospitals with a project cost below 50 million pesos.
8%
6%
12%
The release of 10% retention by the owner shall be done after how many months from the date of final payment.
3 months
6 months
12 months
8 months
How many days shall the Building Official issue a certificate of occupancy after final inspection of the project.
30 days
7 days
15 days
Supervision Work is a non-creative work, true or false.
TRUE
FALSE
True or false, based on the Civil Code, the Project Manager has no legal responsibility insofar as design and construction is concerned.
True
false
What PD created the PRC which regulates the practice of various professionals.
PD 223
PD 233
PD 323
How many days upon written notice can a contractor terminate a contract with a valid reason?
7 Days
15 Days
9 Days
30 Days
Suspension of work for ___ days by order of any court or other public authority through no act or fault of the contractor gives the him the right to terminate contract.
120 Days
30 Days
60 Days
90 Days
the contractor can terminate contract if the owner should fail to act upon any request for payment within ____ after its certification by the architect
15 days
7 days
30 days
90 days