Worksheetshigh volume production
Total questions: 10
Worksheet time: 2mins
Controlling an automated flow line is a ------------ problem
easy
complex
simple
critical
There are ---------- main functions that are utilized to control the operation of an automotive transport system.
5
2
3
4
The first control is an ------------control.
operational
safety
quality
production
The second control function is ----------- controi.
quality
safety
sequence
production
The third operational control is ------------ control.
quality
operational
operation
safety
Hoppers are used to ---------- parts for further processing
control
store
check
process
Lead time is the time interval between customer order to -------------time.
production finish
delivery
inspection
production start
Tact time is always ---------- to/than lead time.
equal
more
less
none
Throughput time is a part of ----------- time.
tact
lead
cycle
none
TACT which means ----------.
time
pulse
stop
idle