B339_L07_Quiz to Recap L05 to L07

Total questions: 11

Worksheet time: 6mins

Name
Class
Date
1.

Which of the following documents covers the deliverables in a project?

a)

Work Breakdown Structure

b)

Close Out Document

c)

Risk Identification Matrix

d)

Stake Holder Listing

2.

Aaron, the project manager is using the 3-point estimation to calculate the estimated duration of a project. The optimistic, most likely and pessimistic durations are respectively: 4, 6 and 9 days. Which is the correct formulae Aaron should use for his calculation?

a)

(4 + 6 + 9)/3

b)

(4*4 + 6 + 9)/6

c)

(4 + 6*4 + 9)/6

d)

(4*2 + 6*2 + 9)/6

3.

   Which of the following will NOT affect the estimation of a project’s cost resulting in negative consequences?

a)

The political situation

b)

A scope statement that is not specific

c)

A Bottom-up approach to cost estimation

d)

Additional deliverables that the client really wants

4.

A Work Breakdown Structure (WBS) is an important tool used during the Planning phase of project management. Which of the following statements correctly identifies what is broken down in a WBS?

a)

The team member’s leave plans during the duration of the project

b)

Project costs are broken down into the various departments that they need to be charged against

c)

Project tasks are broken down into tasks and activities

d)

Major risks that need to be mitigated in order for the project to be completed on time

5.

What does RACI stand for ____________ ?

a)

Reasonable, Accountable, Considered, Informal

b)

Responsible, Accountable, Consulted, Informed

c)

Reasonable, Accountable, Communicative, Informed

d)

Responsible, Accurate, Consulted, Informative

6.

Zootopia Café is implementing a cashless payment system. Hamid, the HR Manager, has been copied on all the meeting minutes by the project team. What role does Hamid play in a RACI Matrix?

a)

Responsible

b)

Accountable

c)

Consulted

d)

Informed

7.

How are dependencies between tasks denoted in a network node diagram?  

a)

A box

b)

An arrow

c)

By a dot

d)

A diamond-shaped box

8.

In a network node diagram, an activity with two or more successor activities is known as a _____ activity.

a)

Merge

b)

Burst

c)

Critical Path

d)

Float

9.

Which of the following technique is used to calculate the Late Finish and Late Start in a Network Node diagram?

a)

Forward Pass

b)

Backward Pass

c)

Depends on the time schedule

d)

Depends on the project

10.

How do we determine which is the Critical Path in a Network node diagram?

a)

It is the path through the network node diagram with the shortest duration

b)

It is the path that contains all the activities/tasks of the network node diagram

c)

It is the path through the network node diagram with the longest duration

d)

It is the path where a Float occurs

11.

The project team failed to show the new variety programme to a focus group first. The focus group's feedback has to be analysed and addressed before the programme can be allotted a time slot on the station’s channel.

 

What type of risk does this best describe?

a)

Resource Risk

b)

Schedule Risk

c)

Technology Risk

d)

Performance Risk