Which of the following documents covers the deliverables in a project?
Work Breakdown Structure
Close Out Document
Risk Identification Matrix
Stake Holder Listing
Aaron, the project manager is using the 3-point estimation to calculate the estimated duration of a project. The optimistic, most likely and pessimistic durations are respectively: 4, 6 and 9 days. Which is the correct formulae Aaron should use for his calculation?
(4 + 6 + 9)/3
(4*4 + 6 + 9)/6
(4 + 6*4 + 9)/6
(4*2 + 6*2 + 9)/6
Which of the following will NOT affect the estimation of a project’s cost resulting in negative consequences?
The political situation
A scope statement that is not specific
A Bottom-up approach to cost estimation
Additional deliverables that the client really wants
A Work Breakdown Structure (WBS) is an important tool used during the Planning phase of project management. Which of the following statements correctly identifies what is broken down in a WBS?
The team member’s leave plans during the duration of the project
Project costs are broken down into the various departments that they need to be charged against
Project tasks are broken down into tasks and activities
Major risks that need to be mitigated in order for the project to be completed on time
What does RACI stand for ____________ ?
Reasonable, Accountable, Considered, Informal
Responsible, Accountable, Consulted, Informed
Reasonable, Accountable, Communicative, Informed
Responsible, Accurate, Consulted, Informative
Zootopia Café is implementing a cashless payment system. Hamid, the HR Manager, has been copied on all the meeting minutes by the project team. What role does Hamid play in a RACI Matrix?
Responsible
Accountable
Consulted
Informed
How are dependencies between tasks denoted in a network node diagram?
A box
An arrow
By a dot
A diamond-shaped box
In a network node diagram, an activity with two or more successor activities is known as a _____ activity.
Merge
Burst
Critical Path
Float
Which of the following technique is used to calculate the Late Finish and Late Start in a Network Node diagram?
Forward Pass
Backward Pass
Depends on the time schedule
Depends on the project
How do we determine which is the Critical Path in a Network node diagram?
It is the path through the network node diagram with the shortest duration
It is the path that contains all the activities/tasks of the network node diagram
It is the path through the network node diagram with the longest duration
It is the path where a Float occurs
The project team failed to show the new variety programme to a focus group first. The focus group's feedback has to be analysed and addressed before the programme can be allotted a time slot on the station’s channel.
What type of risk does this best describe?
Resource Risk
Schedule Risk
Technology Risk
Performance Risk