1.

________________ is the second major project phase, and the second of the five process groups identified in PMBOK.

a)

Project Planning

b)

Project Scope Planning

c)

Communication Planning

d)

Project Implementation

2.

________________ is the definition of all the work needed to successfully meet the project objectives.

a)

Project Planning

b)

Project Scope Planning

c)

Communication Planning

d)

Project Implementation

3.

When the project plan is approved by the sponsor, you are ready to proceed to _________________.

a)

Project Planning

b)

Project Scope Planning

c)

Communication Planning

d)

Project Implementation

4.

The purpose of _____________ is to verify progress, identify challenges and get assistance where needed.

a)

Procurement Planning

b)

Project Scope Planning

c)

Communication Planning

d)

Team Meeting

5.

The purpose of _____________ is to report progress, identify challenges and changes, get support for necessary changes or added resources.

a)

Procurement Planning

b)

Report to Management/Sponsor

c)

Communication Planning

d)

Team Meeting

6.

In this step, we are going to answer the question "Will equipment/supplies/software/etc. be purchased from another organization to carry out the project"?

a)

Procurement Planning

b)

Report to Management/Sponsor

c)

Communication Planning

d)

Team Meeting

7.

A ______________ includes the relationships or dependencies between the beginnings and ends of different activities.

a)

Procurement Planning

b)

Report to Management/Sponsor

c)

Communication Planning

d)

Project Schedule

8.

A ______________ is a clearly defined activity or group of activities whose duration can be estimated.

a)

Project Scope

b)

Work Package

c)

Wedding Deliverables

d)

Leads and Lags

9.

In __________ the task must start before the predecessor is done.

a)

Lag

b)

Work Package

c)

Lead

d)

Milestones

10.

In __________ one task must wait in relation to another task.

a)

Lag

b)

Work Package

c)

Lead

d)

Milestones

11.

Frequency, format and content of communications may be dictated by law or may be a provision of a (a)   .

12.

A (a)   is an important checkpoint, usually completion of a major task or a major set of tasks.

13.

What are the three types of Task Dependencies? (3 points)

(a)  

14.

Differentiate the three types of predecessors. (5 points)

4 lines
15.

Differentiate the synchronous and asynchronous communication. (3 points)

4 lines
16.

What do you mean by the acronym 'WBS' in project management?

(a)  

17.

Determining the (a)   is a key piece of being able to prepare a plan.

18.

In Scope Planning, we make it (a)   and measurable.

19.

What are the basic processes of project planning? (10 points)

4 lines
20.

What is the purpose of the project planning phase? (explain briefly)

4 lines
21.

(a)   breaks down the deliverables into smaller units, ending with the work packages.

22.

(a)   is a horizontal bar chart with a list of activities on the left and a timeline on the horizontal axis.

23.

What is the difference between the traditional Gantt Chart with the current one?

4 lines
24.

What are the three main resources required to carry out each task on the WBS?

(a)  

25.

When the project plan is approved by the sponsor, you are ready to proceed to (a)   .

26.

One of the main activities in the Project Planning phase is determining and (a)   the project scope.

27.

(a)   is the definition of all the work needed to successfully meet the project objectives.

28.

The scope statements should include how the results will be measured so you and your sponsor will know with certainty whether that part of the scope has been achieved.

a)

TRUE

b)

FALSE

29.

One of the main activities in the Project Planning phase is determining and (a)   the project scope.

30.

Project communication is the most complicated step in Project Management.

a)

TRUE

b)

FALSE

31.

Project communication is a key success factor?

a)

TRUE

b)

FALSE

32.

In a project completion, all contracts are signed off but not totally close.

a)

TRUE

b)

FALSE

33.

In the project communication stage, we must consider cultural issues when planning and carrying out project communication.

a)

TRUE

b)

FALSE

34.

Communication is a two-way process, not always “broadcast”.

a)

TRUE

b)

FALSE

35.

Identify whether the stated below is synchronous or asynchronous.

FACE-TO-FACE CLASSES

a)

SYNCHRONOUS

b)

ASYNCHRONOUS

36.

Identify whether the stated below is synchronous or asynchronous.

DOING ASSIGNMENTS AT HOME

a)

SYNCHRONOUS

b)

ASYNCHRONOUS

37.

Identify whether the stated below is synchronous or asynchronous.

MODULAR METHOD

a)

SYNCHRONOUS

b)

ASYNCHRONOUS

38.

Identify whether the stated below is synchronous or asynchronous.

VIDEO CONFERENCING

a)

SYNCHRONOUS

b)

ASYNCHRONOUS

39.

Identify whether the stated below is synchronous or asynchronous.

ONLINE CHATTING

a)

SYNCHRONOUS

b)

ASYNCHRONOUS

40.

Identify whether the stated below is synchronous or asynchronous.

ONLINE DATING USING KUMU APP

a)

SYNCHRONOUS

b)

ASYNCHRONOUS

41.

Identify whether the stated below is synchronous or asynchronous.

POSTING VIDEO THROUGH FACEBOOK

a)

SYNCHRONOUS

b)

ASYNCHRONOUS

42.

Identify whether the stated below is synchronous or asynchronous.

CLASS REPORTING VIA GMEET APPLICATION

a)

SYNCHRONOUS

b)

ASYNCHRONOUS

43.

Identify whether the stated below is synchronous or asynchronous.

POSTING QUIZ THROUGH MESSENGER APPLICATION

a)

SYNCHRONOUS

b)

ASYNCHRONOUS

44.

Identify whether the stated below is synchronous or asynchronous.

ORAL RECITATION VIA GMEET APPLICATION

a)

SYNCHRONOUS

b)

ASYNCHRONOUS

45.

Essay:

In your own opinion, how we are going to identify if our project has been successfully done?