Given the following sets of test management terms (v-z), and activity descriptions (1-5), which one of the following best pairs the two sets?
v – Test control 1 – Calculation of required test resources
w – Test monitoring 2 – Maintenance of record of test results
x – Test estimation 3 – Re-allocation of resources when tests overrun
y – Incident management 4 – Report on deviation from test plan
z – Configuration control 5 – Tracking of anomalous test results
v-3,w-2,x-1,y-5,z-4
v-2,w-5,x-1,y-4,z-3
v-2,w-1,x-4,y-3,z-5
v-3,w-4,x-1,y-5,z-2
——————-are the Testers of Unit Testing?
Developers
Business Analysts
Independent Testers
Customers
Increasing the quality of the software, by better development methods, will affect the time needed for testing (the test phases) by:
Reducing test time
Increasing test time
No change
Can’t say
What is the important criterion in deciding what testing technique to use?
How well you know a particular technique
How appropriate the technique is for testing the application
The objective of the test
Whether there is a tool to support the technique
——————- are the Testers of System Testing?
Developers
Business Analysts
Independent Testers
Customers
What is Decision Table Testing?
Black Box Test Design Technique
White Box Test Design Technique Technique
Gray Box Test Design Technique
Experience based Test Design
What is Sanity Testing?
Test Level
Test Type
Test Design Technique
Test Execution Level
Which one of the following is not a check to be applied to import data during a validation run?
Parity Check
Image Check
Sequence Checks
Passwords
The Pahse of system Development Associated with Creatin of the test data is
System Analysis
Physical Design
System Acceptance
Logical Design
TestRail™ is modern, flexible, ----------------------------- tool
web-based
Cloud & server based
both
Its not a Software
Selenium WebDriver is an open source testing tool for Web applications
true
false
Product Backlog should be ordered on the basis of?
Value of the items being delivered
The complexity of the items being delivered
Size of the items being delivered
The risk associated with the items
Who is responsible to measure the Project’s performance?
The Scrum Master
The Delivery Manager
The Product Owner
The Development Team
User Acceptance Testing (UAT), also known as ----------------------------------------- is defined as testing the software by the user or client to determine whether it can be accepted or not
alpha or end-user testing
beta or end-user testing
alpha-beta Testing
Incremental Testing
___________________ is a testing framework to perform web application testing across various browsers and platforms like Windows, Mac, and Linux.
STS
SELENIUM
ECLIPSE
Appium