1.
A smartphone manufacturer is re-assessing its product development methods in response to a sharp increase in user complaints. Analysis of the complaints indicates that the users try to use some features in ways that designers did NOT anticipate.
Given these findings, which agile practice would most effectively prevent the problem?
a)
Acceptance Test-Driven Development
b)
Smoke Testing
c)
Behavior-Driven Development
d)
Red, green, refactor
2.
An agile team is struggling to solve a blocking issue with packaging design. Eventually, they find a solution, but it requires a different product format.
What should the team do before further developing the solution?
a)
Create a prototype and demo it to the end customer.
b)
Ask the product owner to approve the change.
c)
Run a cost/benefit analysis to determine its value.
d)
Check if the change is consistent with the product vision.
3.
A Project Manager has been asked to conduct a risk analysis that is based on a high-level scope. As part of the this analysis, the Project Manager must use expert judgment to prepare a document.
Which document-based action is being performed?
a)
Creating the project charter.
b)
Preparing the scope statement document.
c)
Creating a project management plan.
d)
Documenting the risk management plan.
4.
A Project Manager overhears a conversation in the company's cafeteria. The speaker says that a possible union action will occur within the next two weeks. The Project Manager knows that any union action will affect the project team, and at this stage of the project, any project delays will cause substantial harm to both budget and schedule. Earlier, the probability of a union action was considered minimal. Thus, it was unanticipated.
What should the Project Manager do?
a)
Inform relevant stakeholders and update the risk register with the new information.
b)
Ask stakeholders for additional information regarding the likelihood of the union action, then act on what is heard.
c)
Set up an information session for the project team, letting them know of possible disciplinary sanctions for those who participate in the union action.
d)
Meet with union members and the union leader to resolve this conflict.
5.
Six months into a strategic agile project, company exectives are closely monitoring its progress. The COO expresses his frustration that the last weekly burn-down charts show the projected completion date significantly moving back and forward several times.
How can the project manager forecast the completion date with more accuracy and stability?
a)
Ensure upcoming backlog items are elaborated in more detail with the team.
b)
Educate the executive committee on the flexible nature of agile planning.
c)
Plan for variable-size iterations according to story complexity and load.
d)
Reduce frequency of the progress reports sent to senior stakeholders.
6.
The Project Manager shifts to an agile approach for a project with an aggressive go-to-market timeline. The Project Manager needs to revise the stakeholder engagement plan so that it follows agile principles.
What should the Project Manager do to meet this need (choose two)?
a)
Design a digital communication system that allows for virtual submission, logging, reviewing, and escalation of issues.
b)
Remove unnecessary layers of management to promote direct communication between the project team and stakeholders.
c)
Modify templates to include product backlog progression and the burndown rate, and encourage use of standups.
d)
Increase the number of formal training workshops to cover all relevant issues for all stakeholders, including the project sponsor and client.
7.
A high-level manager in an organization would like to use a critical project resource for a new project.
Which action should the Project Manager take?
a)
Contact the program manager to resolve the issue.
b)
Request that the high-level manager provides a replacement.
c)
Use the Legitimate form of power to deny the request
d)
Tell the team and reassign that resource's responsibilities to other team members.
8.
A software vendor is behind on a key project deliverable. There is a 21% buffer in the budget for cost overruns. The Project Manager needs to mitigate the issue.
Which action should the Project Manager take next?
a)
Evaluate alternative software vendors that can help project deliverables despite resource constraints.
b)
Remove the current vendor and have the new vendor send a contract.
c)
Ask the vendor to meet to discuss legal issues regarding the slippage.
d)
Accept the cost overrun and update the project schedule
9.
A project that should have been 95 percent complete by now is only 80 percent complete. The total project budget is US$140,000 and the total spent to date is US$95,000.
What is the schedule performance index (SPI) and a cost performance index (CPI) of the project?
a)
The SPI is 0.86, and the CPI is 1.14.
b)
The SPI is 1.19, and the CPI is 0.96.
c)
The SPI is 0.84, and the CPI is 1.18.
d)
The SPI is 0.94, and the CPI is 1.16.
10.
A project has the following budgetary features:
-Total budget of US$3 million
-Planned value of US$630,000
-Actual cost of US$650,000
-Earned value of US$540,000.
Which statement is true about this project?
a)
It is under budget, and ahead of schedule.
b)
It is over budget and behind schedule.
c)
It is over budget and ahead of schedule.
d)
It is under budget and behind schedule.
11.
The Project Manager learns that one team member needs to complete a critical task that is outside of the project, resulting in a scheduling risk for the project.
How can the Project Manager eliminate this risk?
a)
Replace the team member with a new resource from another department.
b)
Schedule a meeting with the team member’s manager to negotiate for additional time to complete the other task.
c)
Notify the project sponsor, documenting the conflict caused by the member’s manager.
d)
Notify the team member’s manager of project needs, and require the release of the member until the project activity is completed.
12.
A Project Manager is uncertain about the project duration for a new product and consults several groups of subject matter experts (SMEs). The first group advises that it can be finished in 25 days. The second group identifies some risks that could make the duration up to 40 days. The third group proposes a new method that can shorten the time to 10 days.
Using the triangular estimating technique, what is the duration for the new project?
a)
23 days
b)
25 days
c)
27 days
d)
30 days
13.
A merger of two companies results in combining an agile software project and a predictive electronics project into a single hybrid project. Two months later, requirements have changed in both tracks but NEITHER has a full picture on status or importance of the requirements.
How can the project manager best resolve the problem?
a)
Integrate the product backlog into the requirements specification and educate the software team on working with the new document.
b)
Create a requirements traceability matrix by combining the product backlog with the requirements specification and define both documents as input.
c)
Integrate the requirements specification into the product backlog and educate the electronics team on working with the new document.
d)
Integrate the revised work packages and updated product backlog items into a new master WBS for progress tracking.
14.
A Project Manager is working on a data center migration project and is developing the schedule management plan. Per the project sponsor's request, the schedule must plan for all tasks as soon as possible. Additionally, the Project Manager is presented with modified resource availability that should not violate schedule constraints. The Project Manager needs to select the appropriate leads and lags relationship for this situation.
Which type should the Project Manager choose?
a)
Early start is smaller than the late start in all activities.
b)
Early start equals the late start in some activities.
c)
Early start equals the late start in all activities.
d)
Early start is smaller than the late start in some activities.
15.
A new product is released. When a customer identifies performance issues with this product, the Project Manager realizes that cost of quality (COQ) should have been used to estimate this cost.
Which category of COQ should the Project Manager have used?
a)
Prevention costs.
b)
External failure costs.
c)
Appraisal costs.
d)
Cost-benefit analysis.
16.
A Project Manager is attending a periodic review with stakeholders. The project sponsor asks the project manager how deliverables will be verified for accuracy and accepted.
In which project document is this information found?
a)
Scope management plan.
b)
Requirements management plan.
c)
Quality management plan.
d)
Work performance reports.
17.
A product passes 96% percent of the functional requirements defined in the scope. A customer is unwilling to accept the product since it did not pass 100%. A Project Manager is assessing what could have been done differently to avoid this.
What should the Project Manager have done?
a)
Assessed and evaluated the test management plan.
b)
Created the work breakdown structure (WBS).
c)
Ensured that the quality metrics were defined.
d)
Reviewed the requirements documentation.
18.
During user testing a client agreed to a final product. A few days later the client is reconsidering their agreement.
What should the Project Manager do?
a)
Refer to the project’s quality management plan.
b)
Review the project’s acceptance criteria.
c)
Review the requirements documentation.
d)
Refer to the project's project charter.
19.
A project has the following characteristics:
-It's being executed by the project team.
-500 products have been developed based on the originally-approved blueprint.
-The project team randomly selected 50 products to evaluate against the quality plan.
What is occurring in this scenario?
a)
The project team is performing inspections.
b)
The project team is utilizing statistical sampling.
c)
The project team is conducting audits.
d)
The project team is undertaking a manage quality measure.
20.
A product deliverable is undergoing acceptance testing. A senior-level stakeholder raises concern that an essential product feature for their department was not developed. The Project Manager wants to avoid this issue in the future.
What is one way to accomplish this goal?
a)
Properly manage stakeholder expectations.
b)
Prepare a change management plan.
c)
Ensure a scope management plan gets approved.
d)
Hold a product demo with stakeholders.
21.
A project has the following characteristics:
-A change request was approved to develop another product that contradicts the original requirements.
a)
Which action should the Project Manager take?
b)
Execute the change request.
c)
Decline the change request.
d)
Ask for a detailed report of the data analysis.
e)
k for a feasibility study of the new product.
22.
To determine which product to create, a project feasibility study was conducted. However, a change request was recently approved to develop another product that contradicts the original requirements. Data specialists conducted an analysis before the change request was approved.
What is an appropriate action for the Project Manager to take?
a)
Perform the change request.
b)
Do not accept the change request.
c)
Review a detailed report of the data analysis.
d)
Review a feasibility study of the new product.
23.
A company’s products will be affected by a new law that might be passed in the next four months. A new product launch is starting, and should be completed within three months. If the proposed law is passed, the new product will not meet the new requirements.
How should the Project Manager address this potential problem?
a)
1. Update the risk management plan.
2. Move ahead with project planning.
b)
1. Discuss risks with the sponsor and key stakeholders.
2. Using the results of the discussion, update the assumption log and project charter.
c)
1. Move forward with the project and project planning.
2. Meet all deadlines, ensuring that the product will be complete prior to potential change in the law.
d)
1. Warn the sponsor and key stakeholders about the implications of the possible law.
2. Advise them to put the project on hold until the legislation is passed.
24.
A marketing team is developing a new website for an existing product range. The team reads through some customer comments submitted on the current website:
"Too much clicking!"
"More and better please."
"Make it easier."
Which tool or technique should the marketing team use to identify the target audience's style preferences?
a)
Focus groups
b)
Brainstorming
c)
Product analysis
d)
Benchmarking
25.
A Project Manager receives the following information for a new project:
-assumptions
-preliminary scope
-restrictions.
After receiving this information, what is the first step the Project Manager should take?
a)
Discern the project goals as well as the business case.
b)
Determine the project team and provide the team with tasks.
c)
Decide on the project schedule and determine the critical path.
d)
Seek approval for the project charter from the sponsor.
26.
A new team member, unaccustomed to agile practices, becomes nervous when an operations engineer who often criticized his previous work appears at the morning standup meeting.
What could justify the project manager's invitation to the operations engineer?
a)
It is an agile practice used to prevent routine setting in to daily meetings
b)
It is a way to boost the new member's performance and keep him on his toes
c)
It is a standard practice in agile to proactively correct misalignments
d)
It is a way for the project manager to learn more about the new member
27.
A client selected a software company to develop a smartphone application. The client's legal team required a detailed source code register for all builds, and refused the company's counter-offer for walk-through meetings and free developer support. 60% of the project effort was spent on documentation and 15% on implementing 38 feature changes.
How many of the of the Four Values of the Agile Manifesto were upheld in this project?
a)
zero
b)
one
c)
three
d)
four
28.
User testing on the last product release revealed low user interest in certain features that required significant effort to develop. What can the agile team do to prevent this disparity in the future?
a)
Ask the product owner ensure all stories in the backlog support the product vision
b)
Ensure that user stories in the backlog are broken down into the smallest possible form
c)
Remove all stories from the backlog that are not selected for the Minimal Viable Product
d)
Perform stakeholder analysis to find SMEs who can guide the backlog value ranking process
29.
A client stakeholder shows signs of resistance when coordinating delivery work. The agile project manager suspects that the automation in the delivered product might make the stakeholder's role obsolete.
Which approach would be most effective to reduce resistance?
a)
Request the client to change the project counterpart to avoid project delays
b)
Ask the stakeholder to express concerns and ensure full transparency
c)
Express empathy directly to the stakeholder to gain cooperation
d)
Tell the stakeholder that their cooperation and patience are appreciated
30.
A project manager is using a suitability assessment tool to find the right project approach for a new project. The tool ranks on the following criteria:
- Change: rate of change to requirements
- Criticality: Criticality of product, processes and impact of defects
- Buy-in: Executive support for adaptive methods
- Team size: Number of members in project team
- Team skill: Project team experience
- Access: Direct collaboration/feedback with clients/sponsors.
Which combination of these factors would be best suited to a fully agile project approach?
a)
Change: medium
Criticality: high
Buy-in: medium
Team size: medium
Team skill: high
Access: high
b)
Change: high
Criticality: low
Buy-in: high
Team size: low
Team skill: high
Access: medium
c)
Change: low
Criticality: medium
Buy-in: high
Team size: low
Team skill: medium
Access: high
d)
Change: low
Criticality: low
Buy-in: high
Team size: medium
Team skill: high
Access: high
31.
The product owner needs a more precise view of actual time spent on tasks in order to apply more accurate business value estimates in the product backlog.
How should the project manager propose to address the problem?
a)
Halve the iteration length to one week to increase precision of time usage calculations
b)
Replan the remainder of the project to use flow-based agile and standard hourly scheduling
c)
Explain that flexible estimating units enable agile to accelerate delivery of business value
d)
Train the team on using ideal hour units and work with them to restimate the backlog
32.
In an agile project, too many meetings have made the product owner's schedule unworkable. The product owner wants to prioritize some meetings and decrease frequency of others.
Which meetings should be prioritized to better ensure successful product development? (Choose TWO.)
a)
Project performance reviews
b)
Sprint backlog planning
c)
Daily stand-up meetings.
d)
Team blocker brainstorming.
e)
End-user feedback sessions
33.
A cultural event project has distinct work packages of varying durations comprised of tasks which cannot be predictably scheduled.
What agile approach would be appropriate in this case?
a)
Flow-based
b)
Incremental
c)
Predictive
d)
Extreme
34.
The project manager is using the INVEST method to check the quality of three stories in the product backlog:
Story 1: As a user, I want to be able to bend the flex conduit up to 90° in any direction to orient lighting from a fixed position.
Story 2: As a user, I want to exert no more than 4 MPa to bend the flex conduit from an unsupported standing postion.
Story 3: As an assembler, I want to spray a conduit coating that will inhibit all oxidation when exposed to 50 years of tropical rain conditions.
What is the evaluation result for these stories?
a)
Stories 1 and 2 fail on the V criterion and Story 3 fails on the N criterion
b)
All stories fail on the I criterion and Story 3 also fails on the V criterion
c)
Stories 1 and 2 pass all criteria and Story 3 fails on the T criterion
d)
All stories fail on all except the S and T criteria
35.
A project has the following characteristics:
- To determine what product should be created, a feasibility study was conducted.
- A change request was approved to develop another product that contradicts the original requirements.
- Data analysis was conducted before the change request was approved.
Which action should the project manager take?
a)
Execute the change request.
b)
Decline the change request.
c)
Ask for a detailed report of the data analysis.
d)
Ask for a feasibility study of the new product.
36.
The quarterly results show that competitors are driving prices down. The company is losing market share and midway into a product development project, it appears the sponsoring unit is not likely to get return on their investment.
Which two actions should the project manager take to adapt the project to these new conditions? (Choose TWO).
a)
Incrementally replace local staff by outside expert staff who can work at half the hourly rate or less
b)
Re-scope the project to deliver the same features as the competitors to match their pricing
c)
Make a cost/benefit analysis of deliverables to optimize delivery cost and speed
d)
Fast-track the remainder of the project to deliver the intended scope with less overhead costs.
e)
Create an agile track to incrementally maximize value within a fixed budget.
37.
A project manager is leading a meeting with key stakeholders to update them on the progress of the project as well as address any questions or concerns of the stakeholders. In order to capture relevant information from the meeting, the project manager assigns a project team member to be the meeting scribe. The meeting is a success with enthusiastic participation among the stakeholders.
With the meeting concluded, what should be done with the meeting minutes?
a)
Added to the meeting minutes register
b)
Addended to the communications management plan
c)
Recorded in the lessons learned register
d)
Documented in the organizational process assets
38.
A project manager is leading a large project to develop a new model of smartphone. Early in project execution, to foster the stakeholder involvement, the project manager holds a meeting as specified in the stakeholder engagement plan.
What type of meeting does the project manager likely hold?
a)
A project retrospective to finalize lessons learned register
b)
A workshop to develop the team charter
c)
A project kick-off meeting to explain the roles and responsibilities of stakeholders
d)
A meeting to create a comprehensive list of stakeholders
39.
The project must take on new requests to enhance or repair the product while working on a long term plan to deliver a new version of the product. Both needs have different owners or sponsors and require purchasing new materials.
How should the project manager handle the ownership of priority and purchasing of new materials?
a)
Determine purchasing priority and ownership based on the cost of the new materials
b)
Assign ownership to the requestor with the highest priority and nearest term need
c)
Facilitate an agreement between stakeholders on priority, ownership, and purchasing
d)
Procure new materials in the order of how the purchasing requests come in
40.
A project manager is leading a project with a predictive life cycle. Detailed plans were provided by the requesting organization before the start of the project.
What will be the focus of the project manager?
a)
Controlling the schedule by successively adding functionality until the deadline is reacheD
b)
Controlling scope to meet schedule and budget
c)
Determining the scope before the start of each iteration
d)
Revising cost and time estimates as the project team's understanding of the product increases
41.
An agile team is developing custom manufacturing equipment for a client. After three iterations, a functional prototype is ready, but it lacks critical safety features as well as several enhancements that can be installed on-site in future releases. To get early feedback from the client, the product owner requests that the team deliver an MVP as soon as possible.
What should the project manager do to address the product owner's request?
a)
Install safety features and enhancements on the prototype and deliver it to the client
b)
Install only the safety features on the prototype and deliver it to the client
c)
Deliver the prototype to the client in its current condition as it is already functional
d)
Install only the enhancements on the prototype and deliver it to the client
42.
You are working as a part-time manager at a weak matrix organization. Your functional manager adds to your workload by declaring you the project manager for a new business idea. After reviewing the business case, you understand new personnel will need to be hired to execute the project.
What constraint, if any, will you be operating under in terms of hiring additional staff?
a)
The functional manager would be responsible for hiring staff.
b)
The human resources manager would be responsible for hiring staff.
c)
You, as project manager, would be responsible for hiring staff.
d)
Senior management would be responsible for hiring staff.
43.
A project manager has been chosen to lead the project to find a location for a second headquarters. The project manager wants to formalize the authority that has been assigned to her and to gain commitment and acceptance for the project.
What is the best thing for the project manager to do?
a)
Inform stakeholders of the approved project charter
b)
Propose an implementation approach
c)
Obtain project charter approval from the sponsor
d)
Determine the feasibility of the project
44.
During a procurement audit, it is discovered that a vendor's project team is spending an inordinate amount of time using a group review technique which was not stipulated in the contract, thus causing a delay to the project. A corrective action has been taken to address the issue.
What should the project manager document in the lessons learned register regarding the vendor?
a)
A record indicating that the vendor should not be considered for future projects
b)
Recommendation to include the vendor for future projects
c)
Effectiveness of corrective actions used to improve vendor's performance
d)
Procurement information is not captured in lessons learned register
45.
A project manager has just returned from vacation and wants to get a project update. The project team outlines several issues and describe how each issue was addressed. The project manager is impressed with how smoothly and effectively the team has addressed the issues even in the absence of leadership.
What stage of team development is being demonstrated in this scenario?
a)
Norming
b)
Performing
c)
Excelling
d)
Forming
46.
User test results for a prototype release are ready. The test users describe the kind of smoother experience they want, the many missing features they desire, and the ways the product could be more visually appealing.
What conclusions can be drawn from the user's input?
a)
The tests are irrelevant: the prototype design is NOT complete.
b)
The tests were a failure: most of the features will need to be re-designed.
c)
The tests were a success: the input will ensure a more targeted backlog.
d)
The test results are unusable: the users did NOT understand the goals.
47.
A project manager is introducing agile values to a newly formed team. The team is assigned to develop a new software application using the eXtreme Programming (XP) method. The project manager explains that agile approaches are value-driven in two ways: one way is focusing on features that provide the highest value to the customer.
Which of the following did the project manager most likely mention as another way of agile approaches, unique to XP, to be value-driven?
a)
Promote the company's success and prosperity
b)
Endorse courage, respect, and communication
c)
Respect practitioners from different cultures
d)
Encourage use of the best technology
48.
You meet with your team to determine the life cycle for your project. After analyzing the best way to define and manage requirements, develop deliverables, handle changes, control risk and cost, and engage key stakeholders, the decision is made to select a hybrid life cycle.
With the project life cycle selected, how will risk and cost be controlled?
a)
By adhering to the cost baseline and implementing risk responses
b)
By grooming the backlog as requirements and constraints emerge
c)
By increasing the cost baseline for each newly identified risk
d)
By progressively elaborating the initial plans with new information
49.
A historic building restoration project requires consultation with a historian. The project also requires specialized equipment along with period correct materials and construction techniques to faithfully reproduce the original construction.
Where should the project manager look to find information on the equipment, tools, materials, and supplies that need to be acquired for the project?
a)
Requirements traceability matrix
b)
Resource calendar
c)
Resource histogram
d)
Resource requirements
50.
Your project team is located in a building that undergoes renovation. During project execution, the power goes out. You know that response plans were made in the event of a power outage which includes the use of a generator, fuel, and an uninterruptible power supply, but you cannot recall where all these items are located.
What should you do next?
a)
Review the risk register
b)
Read the risk management plan
c)
Implement the agreed-upon risk response
d)
Search any storage areas of the building for the supplies
51.
A project is looking to procure a series of products to be developed in tandem with the project. A single supplier must be able to build out the products and provide services to the project team as the team works on the multitude of other components.
To best manage the quality of the long-term procurement need, what is the best practice?
a)
Require the seller to deliver earlier than needed to accommodate repairs of poor quality deliverables
b)
Reduce the number of metrics to optimize the cost of quality and associated assets
c)
Tighten the quality standards at various points in the project to ensure the seller is staying aware of changing conditions
d)
Form a relationship with the seller to build cooperation and mutually lasting solutions
52.
You need to hire one contractor. You are leaning toward one who has an 80% chance of delivering in one month with a cost of $5,000, and a 20% chance of delivering in two months with a cost of $10,000. Another contractor has a 90% chance of delivering in one month with a cost of $6,000, and a 10% chance of delivering in two months with a cost of $12,000.
What technique would you use to select the contractor?
a)
Monte Carlo analysis
b)
Sensitivity analysis
c)
Decision tree analysis
d)
Influence analysis
53.
An agile coach reflects on his past agile projects and realizes that his ability to understand human motivation, expression and dynamics played a large part in his success.
Which of the following interpersonal skills does the agile coach refer to in his personal retrospective?
a)
Servant leadership
b)
Conflict resolution
c)
Emotional intelligence
d)
Adaptive leadership
54.
During estimating, the team is discussing an item in the backlog. It becomes clear that the item can be done in different ways, but the best way is NOT obvious.
What should the team do to progress on this item?
a)
Add ranked alternatives to the backlog.
b)
Select the cheapest alternative to build.
c)
Add a new spike item to the backlog.
d)
Select the fastest alternative to build
55.
You are conducting the source selection analysis for a project that will procure services from a vendor. Since the value of the procurement is relatively small, you have decided that a full selection process does not make sense.
With three prospective vendors under consideration, what is the best course of action?
a)
Utilize a sole source for the procurement
b)
Use a firm fixed price contract
c)
Establish a qualifications only selection method
d)
Conduct a bidder conference
56.
You are in the process of finalizing all activities for your project. As part of this process, you are preparing the final project report which includes a summary of the project performance.
Once the final report is complete, what should you do next?
a)
Release the project team to start the next project
b)
Share the report according to the communications management plan
c)
Analyze how the final product of the project achieved the business needs identified in the business plan
d)
Capture any risks or issues encountered during the project and how they were addressed
57.
A company has been contracted to develop software for a hydroelectric plant. The project management plan specifies Scrum as the development approach. Few sprints into the project, regulators notify the performing organization that due to new environmental laws, safety features originally not included in the scope baseline will need to be built into the software.
What is the project manager's best course of action?
a)
Issue a change request to update the project management plan and, once approved, ensure that the scope baseline is updated
b)
Conduct a root cause analysts with the product owner to determine why the safety features were not included in the scope in the first place
c)
Use the MoSCoW model of prioritization to groom the scope baseline and categorize the new safety features as "should have"
d)
Discuss the new features with the team during sprint planning and if the team agrees, ask them to implement the features in the next sprint
58.
Your project is midway into execution when a new executive joins the company. The sponsor tells you the executive will play a significant role in your project.
What should you do first?
a)
Perform the Develop Project Management Plan process
b)
Record the new executive as an issue in the issue log
c)
Meet with the executive to review the project charter
d)
Update the resource breakdown structure
59.
A project to roll out a new payroll system for the organization has been completed. Training the employees on the new system was a key deliverable in the scope baseline. The training was provided to all employees in a single class but proved inefficient as the payroll department was overwhelmed with incorrectly filled out timesheet forms, which delayed paychecks.
What might the project manager have done differently to prevent the incorrectly submitted timesheets?
a)
Conducted a project retrospective to gain insights into the problems that occurred
b)
Included the approval of overtime and bonuses for the payroll department as a risk response
c)
Captured the problem in the issue log and assigned an owner for monitoring
d)
Incorporated incremental delivery along with retrospectives in the project management plan
60.
A project manager is estimating the number of work periods needed to complete individual project activities with estimated staff.
To complete this process, the project manager should consider all of the following factors except for:
a)
Staff motivation
b)
Number of resources
c)
Law of diminishing returns
d)
Political awareness
61.
A project manager has just been hired to lead a project, which is already in the execution stage. Even though the project team members demonstrate strong social relations and collaborative working environment, the project manager wants to improve the performance of the team and provide the training necessary to achieve the project's objectives.
Among the following, what should the project manager do first?
a)
Evaluate the team members' current skills and competencies
b)
Provide one of the courses offered by the company
c)
Schedule a project retrospective
d)
Conduct a team building activity
62.
The large multi-year manufacturing project relies on traditional and agile methods to manage the vast project complexities and external dependencies. Due to those external dependencies, there are many challenges that cannot be addressed or budgeted for in the two-week iteration cycle.
How should the team address the longer-term budget challenges?
a)
Facilitate a quarterly review of the budget and explore potential future budget challenges
b)
Slowly inject more budgetary constraints and track the budget challenges that these constraints cause
c)
Steadily burn down the budget with every iteration and mitigate budget challenges
d)
Re-evaluate the budget after every iteration and add identified budget challenges to the risk register
63.
As part of monitoring and controlling costs for your project, you need to calculate a cost variance (CV). You have already determined that $22,000 has been spent thus far on the project. In order to calculate the CV, what should you do next?
a)
Check the project cost management plan
b)
Examine the quality control measurements
c)
Look up the budget at completion for the project
d)
Review the cost baseline and project schedule
64.
A project manager is monitoring the status of the project schedule for a product development project. The project deliverables are being produced in an iterative fashion, and the project has just completed seven of twelve planned sprints. The project manager has gathered the following information:
- 17 story points were completed and accepted in the seventh sprint; - 20 story points were planned for sprint #7;
- One feature worth 3 story points was completed but rejected and placed back in the product backlog;
- The value of the features developed to date is $172,000; Actual costs to date are $167,000;
- The BAC for the project is $300,000;
- The project backlog contains 250 story points;
- The project team has successfully completed 137 story points to date
Which of the following accurately describes the schedule performance of the project for the seventh iteration?
a)
The schedule variance (SV) is 0 story points, and the schedule performance index (SPI) is 1.0
b)
The cost variance (CV) is $5,000, and the cost performance index (CPI) is 1.03
c)
The schedule variance (SV) is -3 story points, and the schedule performance index (SPI) is 0.85
d)
There is not enough information in the scenario to determine the schedule performance
65.
The agile team is building a version of a smartphone shopping application suitable for older people. Marketing has not been able to find any volunteer test users fitting the profile.
Which option would be most effective to ensure the best product value is delivered?
a)
Examine evaluations of similar competitor products.
b)
Ask older relatives about the price point they want.
c)
Remove eyeglasses when testing the user interface.
d)
Ask the product owner to run friendly tests with older relatives.
66.
A construction project experienced delays from lower than anticipated worker productivity, errors in construction, as well as worse than expected weather. Although these individual risks were previously identified, the combined effects of these realized risks were greater than the individual risk response plans were able to address, and a critical project deadline was missed.
What might have been done differently to plan better for the risks?
a)
Conducted a sensitivity analysis
b)
Performed a Monte Carlo simulation
c)
Developed a prototype
d)
Applied a decision tree analysis
67.
A project will use an adaptive approach to prepare plans, develop the product, and monitor progress. Initiating and closing processes, however, will have to be managed traditionally due to the constraints imposed by the organization. In this hybrid environment, the project manager decides to use information radiators.
What is the most likely reason behind the project manager's decision?
a)
A To inform project stakeholders about the progress the team made during the latest iteration retrospective meeting
b)
To communicate progress, share issues, drive continuous improvement activities, and manage stakeholder expectations
c)
C To share information with prospective sellers and explain the roles and responsibilities of the team and project stakeholders
d)
D To document lessons learned throughout the project while preparing plans, developing the product, and monitoring progress
68.
A project has just been initiated to transform an organization from a functional organizational structure to project-oriented.
If the project is successful in meeting its objectives, what will be the most likely outcome? (Choose three)
a)
The organization will shift from the current state to the desired future state.
b)
The project manager(s) will have control over the project budget.
c)
Employees will be grouped by the work being done (engineering, manufacturing, etc.)
d)
The project manager(s) will have significantly more authority over projects.
e)
The role of the project manager(s) will be defined as a project coordinator.
69.
To develop the communications management plan, the project manager needs to determine the number of potential communication channels (or paths) of sprint planning meetings. The project manager realizes that the following individuals will have to be invited to the meetings: the product owner, four programmers, two testers, and a UX/UI designer.
What should the project manager do next with this information?
a)
Use the sample interactive communication model to assess the number of communication paths, which is nine in this case.
b)
Conduct a communication styles assessment to determine the number of communications channels, which is 28.
c)
Determine the communication model to be used for the sprint planning meetings before calculating the number of communication paths.
d)
As part of a communications analysis, calculate the number of communication channels, which is 36 in this case.
70.
You are developing baselines for a multi-phase project to install smart wireless meters for a local electric utility company. The first phase will prepare infrastructure, second will install the meters, and third will upload the software. However, due to the opposition of anti-wireless-technology groups, it's unclear if the project will be completed all across the planned region.
What is your best course of action to increase the chances of delivering value in case the project closes prematurely?
a)
Request that the local government provide the necessary security measures for the project team members to protect them from the potential confrontation with the anti-wireless-technology groups
b)
Get approval from the sponsor to offer bonuses to those who agree to work extra time to complete the work as fast as possible even if this involves working in shifts during nights and weekends
c)
Suggest switching the project from a multi-phase to one-phase approach and complete infrastructure preparation, meters' installation, and software upload in short iterations one neighborhood at a time
d)
Recommend project termination since under the circumstances described in the scenario there is no way to complete the project on time, scope and budget, and deliver any value to the customer
71.
A project manager is leading a project kick-off meeting with the project team and other stakeholders. The goal of the meeting is to gain the commitment of the team for the project and inform the stakeholders of the project's objectives as well as define the stakeholders' roles and responsibilities.
Which of the following interpersonal and team skills is least likely to be utilized during a kick-off meeting?
a)
Meeting management
b)
Facilitation
c)
Conflict management
d)
Nominal group technique
72.
A project is carried out using traditional methods. To produce project deliverables more frequently, the project manager wants to incorporate some agile practices into the team's work. An agile coach is brought in to conduct a workshop with the project team.
What should the project manager do next to verify that the team has acquired the agile skill set needed to meet the project objectives?
a)
Facilitate a focus group to evaluate the effectiveness of the workshop and then prepare a team performance assessment
b)
Schedule a team-building event to enhance team cohesiveness, improve collaboration, and strengthen interpersonal skills
c)
Hold a retrospective and then submit a change request to update the lessons learned register with the knowledge gaineD
d)
Update the RACI chart with the agile knowledge and skills acquired by the project team members during the workshop
73.
A project manager has been reassigned from a traditional project to a hybrid project, in which the progress is measured against the baselines, while the product is developed incrementally over the course of several iterations. In this hybrid environment, the project manager is struggling to find a way to carry out the Monitor Risks process.
What tools and techniques would be best for the project manager to use in this situation?
a)
Sensitivity analysis, and risk probability and impact assessment
b)
Risk-based spikes, architectural spikes, and iteration ‘Zero'
c)
Risk burndown charts, daily stand-up meetings, and risk reviews
d)
Pair programming, continuous integration, and automated testing
74.
A small company is occupying one floor in an office building. A new senior manager has been assigned to oversee several projects. The manager contacts an agile project leader and asks for a monthly report that summarizes the project status and the projected finish date.
How should the project leader respond to this request?
a)
Provide the senior manager with a detailed monthly project status report
b)
Suggest that the senior manager periodically attend the daily standups
c)
Monthly, demonstrate the product increment to the senior manager
d)
Invite the senior manager once a month to review the information radiators
75.
During a meeting, the agile coach proposes that the team implement a defined process for reporting defects on their online tracking tool. Since the team members are well familiar with the tool from their past projects, they, by consensus, agree that they do not need to waste their time discussing this matter. The agile coach is unhappy.
What is the best nest step for the agile coach?
a)
Wait and see if the team experiences fast failure
b)
Document defects tracking process
c)
Praise the team for their choice
d)
Force the team to use the tool
76.
A customer contemplates adding new features to a project deliverable.
Which mandatory step must a project manager take before a project team member can start working on these new features?
a)
Verify requirements.
b)
Ensure approval from the responsible individual identified in the project management plan.
c)
Gain approval from the project sponsor.
d)
Ensure key subject matter experts (SMEs) approve.
77.
You are managing a new needs assessment project. While you are analyzing the monthly progress data your team has submitted, you notice that one of your project team members has spent half as much time working on a project activity than you had planned.
What should you do?
a)
Reward the team member for finishing the activity ahead of schedule
b)
Investigate further to determine if there is a problem
c)
Issue a corrective action as you obviously overestimated the activity duration
d)
Do nothing now and wait for the next month's progress data.
78.
A project manager is having difficulty getting project team members to meet their weekly performance targets. The project manager has provided team training and team-building activities, but so far these and other efforts have been unsuccessful. The project manager would like to use a reward system to incentivize team members to meet their performance goals.
What should the project manager do first?
a)
Give rewards to team members who meet their performance goals at the end of the project
b)
Give all team members a salary raise to help motivate them
c)
Hold a contest where team members can compete for prizes
d)
Consult the resource management plan
79.
At an iteration retrospective meeting, two senior developers express frustration that junior team members call them with questions late at night, waking them up and disrupting their family time. As a result, the developers are less productive during the work hours, which negatively affects product quality and creates variance with the performance measurement baseline.
What could the project manager have done earlier in the project to avoid the situation altogether or at least reduce its severity?
a)
Facilitated a meeting to develop a team charter as part of the Plan Resource Management process
b)
Established team working agreements during the daily standups and iteration planning meetings
c)
Selected a team of only senior developers using the pre-assignment tool during project initiation
d)
Nothing could have been done differently since agile teams should accept working at all hours.
80.
A project has to procure goods and services from a seller. Most of the procurement items are well-defined up-front. However, the scope is subject to change and will be elaborated as the project progresses.
Which of the following is best for the project manager to use to address the scope part of the procurement while contracting with the seller?
a)
Master services agreement
b)
Lightweight statement of work
c)
Source selection analysis
d)
Procurement management plan
81.
You work as a project manager for an organization that has a directive type of project management office (PMO). The PMO requires you to document relevant information in the lessons learned register.
What is the main purpose of preparing this documentation?
a)
To enable the ongoing improvement of products, services, and processes
b)
To capture issues and risks and document how they were handleD
c)
To ensure quality policies and procedures are implemented on the project
d)
To satisfy the requirements of the project management office (PMO)
82.
An agile project team begins the development of the project deliverables. The sponsor stresses the importance of having the stakeholders apprised of value gain progress as often as possible.
What is the best way for the project manager to address the sponsor's request?
a)
Provide the stakeholders with value stream mapping
b)
Demonstrate the product at the end of each iteration
c)
Perform the earned value analysis on a daily basis
d)
Colocate the stakeholders with the team members
83.
You are leading a project to design a car with new self-driving technology. During project planning, existing government regulations regarding the new technology were virtually non-existent. You identified this ambiguity risk during project planning and developed a risk response. Now, with the car ready for production, new regulations have been enacted. The new regulations are so complicated that you have trouble understanding them and their implications for the project.
What should you do next?
a)
Seek the opinion of a recognized expert to validate or modify the risk response
b)
Terminate the project since the new technology does not meet the new regulations
c)
Submit a change request to alter the scope baseline to accommodate the new regulations
d)
Proceed with the project and implemented the risk response as originally planned
84.
Midway into project execution, a developer leaves your scrum team. You follow the risk management plan, review the risk register, and implement the planned response by acquiring a new developer. The new developer is highly qualified but is new to the organization and not familiar with the Scrum framework. You introduce the developer to the other team members.
What is your next best step?
a)
Request the team members to rotate with pair programming so that each team member has an opportunity to mentor the new developer
b)
Ask the new developer to review the organizational breakdown structure and the Scrum Guide and assess the knowledge gained
c)
Have the new developer review the product backlog and ask him to select the user story with which he would prefer to begin his work
d)
Hold an outdoor team-building exercise and invite the sponsor, key project stakeholders, and customer representative
85.
During project execution, a vendor is not able to deliver on their contract. Before executing on the previously planned risk response of contacting a secondary vendor, the risk owner goes on vacation and delegates the finalization of the procurement to a project team member. Unfortunately, the project team member forgets to complete the procurement process.
Who is ultimately accountable for ensuring the implementation of the risk response plan in this situation?
a)
Risk owner
b)
Project manager
c)
Project sponsor
d)
Team member
86.
A client's employee asks the project manager for an additional, new product feature during a status meeting.
To which document should the project manager first refer to determine who has the authority to approve this request?
a)
Change log
b)
Change management plan
c)
Responsible, accountable, consult, and inform (RACI) matrix
d)
Change request document
87.
A project manager has diligently captured the knowledge gained from each iteration retrospective and recorded the information in the lessons learned register. After the project retrospective, the project manager finalizes the lessons learned register and transfers the information to the lessons learned repository as specified in the project management plan. However, when other project teams review the lessons learned as part of planning their projects, some of the information is misinterpreted, and knowledge is lost.
How might the project manager have avoided this situation?
a)
Ensured that the tacit knowledge gained during the project is recorded and codified in the lessons learned repository
b)
Updated the organizational process assets with the knowledge gained from the project as part of project closure
c)
Invited the other project managers to attend the project retrospective so the tacit knowledge can also be transferred
d)
Developed a more robust knowledge management plan as part of the Plan Knowledge Management process
88.
A project is 50% completed. An essential project team member requests two (2) months leave for personal matters.
What should the project manager do first?
a)
Check with this team member to see if the leave can be postponed.
b)
Discuss the issue with the functional manager and request a replacement.
c)
Assess how the leave will impact the project.
d)
Refer to the resource management plan.
89.
A start-up company needs to quickly expand its product portfolio to meet market demand. Recently, staff members are working on two or three agile teams, each dedicated to a different product line. Output is dropping and defect rates are rising in all teams.
In which two ways can the project manager help the agile teams improve their work? (Choose THREE).
a)
Perform root-cause analysis in the next retrospectives.
b)
Influence the product owners to right-size their portfolios.
c)
Organize dedicated teams to reduce context-switching.
d)
Appoint dedicated test teams to offload the agile teams.
e)
Train the agile teams to improve time and focus management.
90.
A project sponsor asks the project manager to change production materials because these materials could cause health problems to consumers.
Which step should the project manager take?
a)
Follow the Perform Integrated Change Control process and thoroughly investigate the matter.
b)
Immediately implement the change and submit a change request for formal documentation.
c)
End the current work and enact the change control process.
d)
Reject the change because the request is outside of scope.
91.
A team was in the execution stage of the project management plan when three (3) necessary changes were brought to their attention. The team members all have differing opinions regarding how to implement the changes.
What should the project manager do?
a)
Hold a meeting with the board and project sponsor to address the issue.
b)
Confirm that all team members and stakeholders understand and follow the change management plan.
c)
Organize a meeting with team members to review the issues and request changes where needed.
d)
Ensure all requested changes are applied to the project and communicate directly with all team members.
92.
A project manager recently joined a new project with the following characteristics:
- Tight deadlines
- Global virtual team
- Fixed budget.
During the planning stage, the project manager wants to avoid scope creep and keep the team focused on delivering a product that meets requirements.
The project manager should ensure __________. (Fill in the blank with the correct response.)
a)
that any changes to scope go through the formal approval process
b)
that daily standups occur, with all development teams
c)
that the development team leads generate detailed requirements
d)
that stakeholders do NOT directly interact with the development team leads
93.
The project sponsor requests that an element of a product will be swapped for the equivalent supplied by a local manufacturer in order to have a more sustainable supply chain.
Which action should the project manager take?
a)
Promptly implement the change and submit a change request for formal documentation.
b)
Refer to the Perform Integrated Change Control process to examine the issue further.
c)
Halt current production and initiate the Perform Integrated Change Control process.
d)
Refuse to fulfil the request because it will lead to scope creep.
94.
A worldwide product launch will likely be delayed by the lengthy analysis needed to assess the impact of new European Union (EU) regulations. Perishable ingredients and factory bookings are at risk of being lost. The executive committee decides to postpone the launch in the EU but maintain launch dates in all non-EU countries.
How should the project manager re-plan the project to support both launches?
a)
Use the contingency budget to cover sunken costs for the EU launch and adjust plans for the non-EU launch.
b)
Replan the project as a fully agile set of iterations and ensure that fixed milestones are documented on the burn-down chart.
c)
Plan analysis activities and tollgates for the EU launch and crash the schedule for the non-EU launch.
d)
Embed a set of iterations to analyze and develop the EU product, while adjusting plans for the non-EU launch.
95.
A multi-year, hybrid pharmaceutical project adds new fixed-date activities for the team to run Machine Learning (ML) processing of medical scans. The output from the ML analysis is used by an agile team of doctors to determine next steps in a patient case. The project manager has updated the scope statement and schedule.
In which three other documents should the project manager record this new process? (Choose THREE).
a)
Stakeholder Register
b)
Sprint Backlog
c)
Definition of Ready
d)
Risk Register
e)
Resource Management Plan
96.
A project’s workload is increasing significantly, and the resource level is NOT sufficient. In response, management outsources some major tasks to keep the project on schedule.
What should the project manager do in this scenario?
a)
Review the communications management plan.
b)
Revise the procurement management plan.
c)
Escalate to the project sponsor.
d)
Revise the organizational chart.
97.
A textile development project needs a specialized resource to work for 900 hours. The company has decided to outsource these hours. Because of internal policies, all potential service providers must be given the same information about the requirements.
Which action should the project manager take to ensure this?
a)
Hold direct negotiations with each service provider.
b)
Conduct a bidder conference with the service providers.
c)
Ensure the procurement management plan is sent to each service provider.
d)
Add each of the service providers to the stakeholder register.
98.
Because a deliverable does NOT meet the agreed-upon quality specifications, it is rejected by the customer. Team members find that the deliverable fails to meet expectations because of a problem with vendor-provided parts. The vendor says that they will NOT correct the problem.
Before deciding on next steps, what should the project manager do?
a)
Check the service level agreement (SLA) established with the vendor.
b)
Review the procurement management plan and contract agreements.
c)
Check the internal quality assurance reports.
d)
Review the resource management plan and document lessons learned.
99.
Near the end of a manufacturing project, several team members are transferred to another project. To complete the work, the project manager needs to acquire additional resource support from a new supplier but is concerned about the cost risk of using a new supplier at this advanced stage of the project.
Now, the project manager needs to work with the procurement team to establish specifications and type of contract to be used.
What should be done?
a)
Recommend a time and material (TM) contract.
b)
Recommend a fixed price incentive fee (FPIF) contract.
c)
Recommend a cost plus incentive fee (CPIF) contract.
d)
Recommend a firm fixed price (FFP) contract.
100.
The agile team surpassed the planned number of stories in the last three agile iterations.
How can the project manager be sure all the work performed is truly complete?
a)
Ask the product owner if results are satisfactory.
b)
Check results against the Definition of Done.
c)
Ask the team to cross-check other members' work.
d)
Check the results of all the tests performed.
101.
Because a deliverable does NOT meet the agreed-upon quality specifications, it is rejected by the customer. Team members find that the deliverable fails to meet expectations because of a problem with vendor-provided parts.
Before deciding on next steps, what should the project manager do?
a)
Check the service level agreement (SLA) established with the vendor.
b)
Review the procurement management plan and contract agreements.
c)
Check the internal quality assurance reports.
d)
Review the resource management plan and document lessons learned.
102.
A hybrid project combines IT integration and software development tasks. The predictive and agile teams seem to be working in silos, resulting in misaligned deliverable scheduling.
Which two measures would most effectively enable the teams to better synchronize their deliveries? (Choose TWO).
a)
Alter the story size to ensure more complete integration to the IT build requirements.
b)
Use the IT predictive schedule to limit the features the software team starts to develop.
c)
Create a common Kanban board to queue and track progress of both teams' deliverables.
d)
Break down IT work packages into more granular tasks to align to the software releases.
e)
Define common milestones and an overall dependency network to be used by both teams.
103.
Company G has a goal of increasing customer satisfaction within four (4) months and initiates a project to meet this goal. The project manager needs to identify best practices.
Which method should the project manager use to accomplish this?
a)
Benchmarking
b)
Emotional intelligence
c)
Facilitation
d)
Affinity diagram
104.
A project manager begins to prepare the project management plan after receiving the project charter. There is currently NO historical information in the project management office (PMO).
What next step should the project manager take in this scenario?
a)
Utilize analogous estimating.
b)
Seek advice from experts in the field.
c)
Organize an initial kick-off call.
d)
Request that the project sponsor provides input.
105.
Company P’s IT transformation project has three (3) deliverables, and they have the following characteristics, according to the project team:
- Deliverable 2 has strictly scheduled milestones, with no expected variation in the timeline.
- Requirements for deliverables 1 and 3 will change quickly during development.
Which project life cycle should the project manager use for this project?
a)
Select a fully agile project model, with a common user story and three-week sprints.
b)
Select a waterfall project model for deliverables, with firm milestones and change control procedures.
c)
Select a hybrid project model; position deliverable 2 as a single agile sprint embedded in an overall waterfall project.
d)
Select a hybrid project model; position deliverable 2 as a single waterfall phase embedded in an overall agile project.
106.
A consultant has advised an IT director to use a development and operations (DevOps) approach to a migration project. The IT director wants to understand how the necessary speed can be achieved in a safe way.
Which two examples could demonstrate how DevOps can reduce incidents and speed up deployment at the same time? (Choose TWO.)
a)
Virtualization of all systems and software containers
b)
Early collaboration between operations and development
c)
Machine Learning-based development and deployment
d)
Development testing at deployment sites before operations.
e)
Automation of operations and development
107.
An innovative product fails to satisfy targeted consumers despite significant investments in quality control and marketing campaigns.
Which agile practice would best prevent future failures of this nature?
a)
Run continuous consumer usability testing on product releases.
b)
Align objectives between the product owner and marketing.
c)
Broaden the persona type definition of the target consumer.
d)
Add more features and tests to the minimum viable product (MVP).
108.
An emergency vaccine roll-out project should be deployed to vaccination centers as soon as confirmed locations are booked. Factors such as delayed batch shipments, safety protocols, and target age groups may block the deployment at the last minute. However, the deployment process does NOT vary after passing the tollgate to begin setup at a new location.
Which project approach would best support the goal to maximize the number of centers deployed?
a)
A fully predictive life cycle where each center deployment is a phase subject to dependencies.
b)
A set of agile deployment iterations embedded in a predictive set of processes.
c)
A set of predictive deployment sequences embedded in a set of agile processes.
d)
A fully agile life cycle where dependencies and deployments are combined in each iteration.
109.
A project to start building an ecology-focused resort complex is planned, and the contract is ready for signature. The client now asks the prime contractor to suspend planned development work on a parcel of land while the team runs a consumer study—the team needs to know what kind of structures to build on the parcel.
What should the prime contractor do to quickly close the deal, given the new client requirements?
a)
Subtract the parcel development work from the quoted price and plan the parcel development as agile iterations paid based on time and materials.
b)
Add a risk premium to the agreed price of the full works and add a clause to renegotiate the new scope when it is fully defined.
c)
Raise a change request to examine the impact on scope and price and close the deal when all information is available.
d)
Exclude all work on the parcel from the project plan and pricing and propose a separate contract when the scope becomes clear.
110.
A new wildlife reserve project will have a staff of approximately 80 experts, builders, and logistics workers with exposure to various safety risks. The project manager wants a scalable approach combining flexibility and team dynamics with traditional safeguards.
Which option could be used to tailor a hybrid project of this nature?
a)
Crystal Methods
b)
eXtreme Programming (XP)
c)
Behavior-Driven Development
d)
Monte Carlo Simulation
111.
A medium-sized company is expanding into a new market. However, the company does NOT have previous experience in that market. A project manager needs to collect requirements.
Which two tools or techniques should the project manager use? (Choose TWO).
a)
Prototypes
b)
Expert judgment
c)
Product analysis
d)
Create requirements traceability matrix
112.
In a hybrid product design project, the team encounters a 3D printer malfunction resulting in costly losses of titanium supplies. When the production team tells the agile programming team about the problem, it becomes clear that mistranslated data sheets created problems for both teams. However, the agile team resolved their problems a month before the malfunction.
What could the agile team have done to prevent the current malfunction?
a)
Deprioritized the stories impacted by information in the data sheets
b)
Asked the project sponsor to halt the project pending translation corrections
c)
Summarized their retrospective conclusions on information radiators
d)
Formally requested a change of equipment supplier for the project
113.
A medical equipment vendor is running a hybrid project which includes some custom software development by an agile team. The team progress is good, but slow customer approval causes unnecessary delays. The customer insists that approval can only be given after repeating all the test cases in the target environment.
How can the project manager accelerate the approvals and build customer trust at the same time?
a)
Invite the customer to send representatives to witness the team's testing to pre-approve the tests.
b)
Work out an arrangement with the customer to defer as many tests as possible to the final release.
c)
Propose new terms for team members to work aside the customer testers to run tests in their environment.
d)
Allow the team to progress at their pace while the customer continues to test and approve earlier builds.
114.
An organizational change program has met with internal resistance, a risk which was previously identified. A logistics manager is particularly affected, due to reduction of the team size and the rate of change driven by an agile planning of the predictive implementation. The manager's supervisor formally requests the change program to delay implementation for the logistics team.
What should the project manager do next in response to this request?
a)
Work with the program sponsor to re-prioritize the program backlog sequence.
b)
Request that the sponsor escalate the strategic issue to the executive committee.
c)
Perform root-cause analysis on the key factors causing the manager's resistance.
d)
Review the risk register and implement the relevant risk response for the case.
115.
A project team collected sensitive client data during the early stages of a project to help develop the project management plan. The team is now working on deliverables for the project when the compliance manager discovers a data breach and alerts the team to a compliance issue.
Which document should the project manager review first?
a)
Statement of work (SOW)
b)
Issue log
c)
Business case
d)
Risk register
116.
The team working on Project A has resolved a technical issue, and the project is moving forward. The project manager has been warned that the same issue will probably arise on similar projects in the future.
What should the project manager do first when responding to this warning?
a)
Ensure that the issue log is updated and update the lessons learned register.
b)
Create a risk report and keep the report current.
c)
Notify the project sponsor about the warning.
d)
Ensure that the lessons learned register is updated.
117.
While reviewing the issue log, the project manager notices that tasks assigned to two (2) team members are quite a bit behind schedule.
What should the project manager do?
a)
Notify the responsible team members of the need to complete the overdue tasks quickly in order to avoid introducing extra project risks.
b)
Document the issue, escalate to the project sponsor, and ask how they would like it resolved.
c)
Tell the team members who are behind schedule that they should explain why tasks were delayed and how they will get back on schedule.
d)
Work with the relevant team members to review the delayed tasks and decide on strategies for resolution.
118.
Project team members are busier than usual. They indicate that they do NOT have the time to update the lessons learned repository because of other project responsibilities.
How should the project manager respond?
a)
Require submission of lessons learned documentation after each project deliverable is accepted by the customer.
b)
Ensure there is an agenda item for discussion of lessons learned from project activities as part of all project meetings.
c)
File a change request to the project management office (PMO) to change how often lessons learned is collected.
d)
Bring in a consultant to assist with collecting lessons learned to help reduce the burden on project team.
119.
A large project includes functional groups in four (4) countries, a steering committee, and a project sponsor. As the project approaches completion, the project manager must prepare the closeout documents.
How should the project manager obtain appropriate sign-off on the acceptance of project deliverables?
a)
The project sponsor should be asked to sign off.
b)
The steering committee should be asked to sign off.
c)
The four managers from the four countries should be asked to sign off.
d)
All of the parties involved should be asked to sign off.
120.
After six (6) iterations, significant variations have occurred to project scope and schedule. These are due to the customer's technology regulations and security policies, which are regularly reviewed. The project manager suggests taking a new approach to the next iteration to avoid possible delays.
What should the project manager do first?
a)
Rank the importance of each improvement item, then implement actions identified during the last retrospective.
b)
Engage in a cost-benefit analysis that can help predict the profits that could be realized through the use of new technology for the next phase.
c)
Research new technology trends and management tools that have been successful on similar projects.
d)
Use a backlog refinement meeting and include the customer's change requests in the discussion.
121.
A project manager has completed the following steps:
- Finished a major IT deployment project
- Confirmed with the release manager that all systems are working
- Confirmed that functionality has been verified by the quality assurance team
- Informed the customer.
Which next step should the project manager take?
a)
Add the lessons learned to the organization knowledge base.
b)
Update the risk register, stakeholders, and team members.
c)
Ensure that the procurement plan is closed out.
d)
Review, verify, and complete the release documentation.
122.
A client brings a project manager into a project during the project's execution stage.
The project manager reviews the project scope for cost estimating purposes and notices that some deliverables were missed in the work breakdown structure (WBS).
Which step should the manager take next?
a)
Verify with the stakeholders to see if these missed deliverables should be added.
b)
Ask that the project management office (PMO) approve additional funds for this work.
c)
Include the work in the WBS, per the 100% rule, and recalculate the total project cost.
d)
Determine whether these deliverables are necessary by verifying with experts in the field.
123.
Review the following steps.
1. A project has been successfully delivered.
2. The project manager is executing formal closure.
3. ______________________________________.
What is step 3?
a)
The project manager should update the bid documents.
b)
The project manager should obtain stakeholder acceptance.
c)
The project manager should reassign the project team.
d)
The project manager should reallocate the unused funds.
124.
Review the following project characteristics:
- The project is in the initiation phase.
- Due to lack of funding, the project is terminated.
- The project manager must close the project.
What is the first action the project manager should take?
a)
Rely on the communications management plan to properly inform all stakeholders.
b)
Examine the organization's project closure guidelines.
c)
Determine the potential impact of terminating the project by performing a risk analysis.
d)
Close all project procurement processes.
125.
After a project ends, the project manager and project team members are still being asked to do the following:
- Evaluate new requirements
- Make minor modifications
- Solve technical issues.
The project manager wants to ensure the product or service developed by the project now has operational support.
What should the project manager do?
a)
Complete the hand-off of the project.
b)
Review the acceptance criteria and get acceptance.
c)
Formally disband the project team and find a new project.
d)
Continue to fulfil the requests as the product is still being developed.
126.
Project team members are spending a lot of time helping maintenance and operations staff with a recently commissioned project component. The project manager needs to validate that the component was signed off and ownership transferred.
Which three (3) documents should the project manager use for this decision?
a)
Final report, organizational process assets updates, and procurement agreements
b)
Procurement agreements, project document updates, and organizational process assets updates
c)
Procurement agreements, stakeholder engagement plan, and organizational process assets updates
d)
Final report, project document updates, and organizational process assets updates
127.
A project is completed, but the project manager and project team members are being asked to do the following:
- Troubleshoot and resolve technical issues
- Evaluate new requirements
- Make minor adjustments.
The project manager needs to ensure that the product developed by the project now has operational support.
What should the project manager do?
a)
Since the product is still under development, continue to fulfil the requests.
b)
Procure project acceptance.
c)
Contact the project team, dismiss them from the project, and find a new project.
d)
Execute the project hand-off.
128.
At the end of an agile project, all stories are completed on schedule and all tests passed, but the customer does NOT consider the product a success.
Which is the most effective way to prevent this outcome in future projects?
a)
Ensure that the product vision is approved by the customer before developing the backlog.
b)
Agree with the customer on success criteria to be included in the Definition of Done.
c)
Collect customer feedback on incremental release demos and user tests.
d)
Ensure that the test plan includes non-functional requirements in the backlog.
129.
An energy infrastructure vendor is delivering a complex solution proof of concept to a new strategic customer. The predictive project should be completed in 10 weeks, but there will be a long list of outstanding items, and some are dependent on external events with uncertain scheduling.
How should the project manager handle the outstanding items?
a)
Transfer the outstanding items to the next project with the customer.
b)
Plan five agile iterations to complete the tasks as soon as conditions allow.
c)
Descope the outstanding tasks and remove them from the invoice.
d)
Add resources and crash the schedule to complete outstanding tasks.
130.
A project has the following characteristics:
- It is in the execution stage.
- A new law requires immediate compliance.
- This law will impact the project's scope, schedule, and cost.
What are three possible actions to ensure compliance? (Choose THREE).
a)
Initiate avoidance of the risk.
b)
Ensure the project management plan is updated.
c)
Escalate the issue to senior management.
d)
Update the issue log.
e)
Begin the change request process.
131.
A new law is expected within the next six (6) months that will affect a business’ product line. The next product is launching and should be completed within three (3) months. Unfortunately, the new product will NOT meet the requirements of the proposed law.
How should the project manager respond to this potential problem?
a)
Schedule a meeting with the sponsor and key stakeholders to discuss risks. Then, using the results of the meeting, revise the assumption log and project charter.
b)
Revise the risk management plan. Then, move ahead with planning the project.
c)
Move ahead with the project, following the plan. Then ensure on-time completion, so that the product will NOT be affected by any possible rule change.
d)
Schedule a meeting with the sponsor and key stakeholders to warn them about the law. Then advise them to cancel the project until the legislation is finalized.
132.
Project N is a business merger in a highly regulated industry. The project sponsor and a high-level executive have asked for changes that appear to disregard legal requirements.
What should be the first step in the project manager's response?
a)
Immediately schedule a meeting with the stakeholders to review the situation.
b)
Send the change control board (CCB) a change request.
c)
Check with the organization's relevant legal practitioner for guidance
d)
Review the organization's lessons learned database for precedents and direction.
133.
Review the following project characteristics:
- A sponsor approves a project.
- The project manager invites selected team members, key stakeholders, and the sponsor to a meeting.
- The primary purpose of the meeting is to create a document that will guide the team in defining the main project deliverables.
What will be the final output of this meeting?
a)
Milestone list
b)
Work breakdown structure (WBS) dictionary
c)
Scope management plan
d)
Requirements management plan
134.
A project manager needs to ensure that all data security requirements are covered during a data warehouse development project’s execution phase. Each of the databases created during different project phases will have a specific data security policy to comply with governmental data security laws.
How should the project manager plan to meet these requirements?
a)
Plan a database development specification, then regularly check to ensure the work aligns with the specification.
b)
Arrange for review of the data security status on a quarterly basis, and recommend remedial steps if noncompliance is found.
c)
Tell the database developer to submit documentation of data security items and the steps they need to take to correct items that do NOT meet specifications.
d)
Add a quality assurance specialist resource to the project team, who will be responsible for monitoring the data security quality of the project.
135.
A project team learns about a new compliance requirement from an international entity that may impact the baseline business case for the project. They learn this right after the project charter is completed and the project sponsor has signed.
How should the project manager proceed?
a)
Research the requirement and possible consequences, then give the sponsor a recommendation.
b)
Address the requirement through the creation of a quality management plan.
c)
Ignore the issue, as the new requirement is NOT part of the project's documented scope.
d)
Ensure that the requirement is documented in the risk register, then ask for further guidance from all stakeholders.
136.
A Canadian start-up company announces to the press its imminent launch in the European Union (EU) and Latin America. Soon afterward, the compliance team recommends delaying the launch by six (6) months to avoid substantial penalties related to a new set of EU regulations.
Which approach could the project manager take to advance the launch project while preparing the compliance measures?
a)
Run a SWOT analysis to weigh priorities between compliance and consumer needs, and resume project if the result favors consumers.
b)
Estimate impact of penalties on the project, increase the contingency reserve accordingly and resume project as planned.
c)
Replan the predictive project as a Large-Scale Scrum life cycle, and use story points to estimate approval milestones.
d)
Split work affected by the regulations into an agile track and replan unaffected work in the predictive schedule.
137.
Two (2) months into a three (3)-year mobile telecom roll-out, the project manager discovers that approximately fifteen percent (15%) of the equipment is prohibited for delivery because of an embargo. The procurement contract does NOT cover the embargo case, but the company could incur severe penalties for incomplete delivery.
What is the appropriate solution for the situation?
a)
Add an agile track to explore and plan delivery of alternative equipment.
b)
Explore insurance and contingency options to cover the cost of the risk.
c)
Compare the penalty costs of delivering or not delivering and choose the lower one.
d)
Accept the client’s penalties, close the project, and cease business in the country.
138.
The legal team informs the product owner that another company owns a patent for an innovation used in the agile team's product, which is now 75% complete.
What should the product owner do to determine the appropriate way forward?
a)
Work with the legal department to find markets where the patent is NOT registered.
b)
Perform marginal economics analysis and identify minimum releasable features.
c)
Terminate the project immediately to prevent any further sunken costs.
d)
Continue work on the product after removing the patented component.
139.
A new regulation requires consumer warnings on labels, but a company's product package is too small to fit the additional information. The regulatory specification does NOT provide a solution, so the agile team decides to solve the problem by displaying the information on a fold-out flap. The start of mass production of the new labels, the project's next milestone, is scheduled to begin in five days.
What should the agile team do next?
a)
Update the sprint backlog to reflect the additional product label requirement.
b)
Contact the compliance team to determine validity of the selected format.
c)
Develop a prototype and submit it to the label manufacturer for approval.
d)
Develop a prototype and submit it to the label manufacturer for approval.
140.
A project manager leaves the company and is replaced. The new project manager is excited to start guiding the team toward project success.
What should the new project manager do first?
a)
Review the project charter to identify goals and deliverables.
b)
Review the project diary and look for notes made by the former project manager.
c)
Modify the project schedule, adding a new activity related to the knowledge transfer process.
d)
Revisit the project budget and schedule to determine if extra time is required.
141.
A project manager receives the following for a new project:
- Assumptions
- Restrictions
- Preliminary scope.
After receiving this information, what should the project manager do first?
a)
Review and understand the business case and project goals.
b)
Put together the project team and assign project tasks.
c)
Build the project schedule and determine the critical path.
d)
Ensure project charter approval is obtained from the sponsor.
142.
A week prior to the project kick-off call, a project manager meets with a key project resource to gain a deeper understanding of the complexity of the project deliverables. The resource expresses concern and worry regarding the deliverables.
How can the project manager ensure that the deliverables are realistic?
a)
Perform a feasibility study, and then assess the results.
b)
Discuss the resource's concerns with the sponsor, and modify the project charter.
c)
Note the concerns in the issue log to review at a later date.
d)
Identify threats and preventive actions by conducting a risk assessment.
143.
A key project resource is discussing the complexity of project deliverables with the project manager two (2) weeks before the kick-off call. The resource expresses nervousness and concern regarding the deliverables. The project manager wants to ensure that the deliverables are realistic.
What is the appropriate action to take?
a)
Implement a feasibility study, and then assess and review the results.
b)
Hold a meeting with the project sponsor to discuss the resource's concerns and revise the project charter.
c)
Ensure that the concerns are documented in the issue log for later review.
d)
Start to identify threats and preventive actions by performing a risk assessment.
144.
A project manager is working with a customer who repeatedly submits requests for new requirements for an existing software product. The project manager has already provided the completed scope definition for the product's next version release to stakeholders.
Which step is appropriate for the project manager to take next?
a)
Hold a meeting with the product manager to request that the number of new requests be reduced.
b)
Define project boundaries immediately with the sponsor.
c)
Organize a meeting with the stakeholders to set expectations.
d)
Analyze the scope management plan to see how changes in scope are handled.
145.
During user testing, a client agrees to the final product. One day later, the client indicates that the final product MAY NOT be acceptable.
What should be the project manager’s first step for resolving this issue?
a)
Discuss concerns with the client and consult the project’s acceptance criteria.
b)
Review the project's quality management plan.
c)
Review the project’s requirements documentation.
d)
Refer to the project charter and lessons learned register.
146.
A new product development project is to be initiated in a difficult business context. Competition is driving prices down, and supply costs are rising.
Why would an agile incremental project approach be the safest choice in this context?
a)
It ensures that the project can be cancelled at any time without loss.
b)
It accelerates delivery of business value and minimizes risk of irrelevancy.
c)
It reduces the team size and eliminates communication bottlenecks.
d)
It provides stringent methods to reduce cost of quality and conformity.
147.
The marketing director is displeased that the agile innovation team is producing too many novelty products with too little business value.
Which two approaches should the project manager take to correct the team's approach? (Choose TWO).
a)
Work with the product owners to tighten value criteria in the Definition of Ready.
b)
Ask the team to take a training course on direct response marketing.
c)
Increase the story sizes to integrate more valuable features.
d)
Survey end users and integrate resulting value rank into the product backlog.
e)
Add a process so the marketing director can approve each story.
148.
An agile innovation team is highly productive. However, the Head of Operations informs the product owner that the company is NOT getting sustainable return on investment from the team's work.
How should the product owner address the problem?
a)
Define a minimum viable product (MVP) with the team and prioritize relevant backlog items.
b)
Reduce the number of team members as necessary to guarantee a positive return on investment.
c)
Identify minimum marketable features (MMF) and prioritize relevant backlog items.
d)
Work with the project manager to run a retrospective and perform project cancellation.
149.
A company is losing market share to disruptive competitors with new business models. A cross-functional agile team has been formed to recommend ways to recover market share.
How can the team increase their chance of producing successful recommendations?
a)
Gain a deep understanding of why customers are disappointed by the company's products.
b)
Focus on enabling profitable delivery of unique, high-quality, and innovative products.
c)
Understand how the competitors' business models can reach more consumers at a lower cost.
d)
Focus on understanding the value consumers seek and the value competitors offer.
150.
Over the past six months, the development cost per story has risen by more than 250% due to a faulty platform which is NO longer supported. The product vision highlights unique features of the platform as a pre-requisite for the product.
What should the project manager do to determine next steps?
a)
Cancel the project due to exceeding the budget constraint.
b)
Ask the product owner to select an alternative platform.
c)
Cancel the project as the product vision CANNOT be fulfilled.
d)
Run what-if cost impact scenarios with the product owner.
151.
The agile team will take over from another supplier to maintain a client's website. The team notices that recent browser changes imply that most of the website's existing content would now require users to install a plug-in.
How should the agile team move forward?
a)
Inform the client and propose an impact analysis.
b)
Update all pre-existing code to remove plug-in dependencies.
c)
Inform the client about the previous supplier's negligence.
d)
Deliver the code updates as defined in the contract
152.
The quarterly results show that competitors are driving prices down. The company is losing market share and midway into a product development project, it appears the sponsoring unit is not likely to get return on their investment.
Which two actions should the project manager take to adapt the project to these new conditions? (Choose TWO).
a)
Incrementally replace local staff with outside expert staff who can work at half the hourly rate or less.
b)
Re-scope the project to deliver the same features as the competitors to match their pricing.
c)
Make a cost/benefit analysis of deliverables to optimize delivery cost and speed.
d)
Fast-track the remainder of the project to deliver the intended scope with lower overhead costs.
e)
Create an agile track to incrementally maximize value within a fixed budget.
153.
A pharmaceutical project includes an agile team of doctors who analyze human tissue scans from drug trial patients. The CEO wants to leverage Machine Learning (ML) technology, because it is proven to be faster and more accurate than doctors in scan analysis.
How should the product owner proceed in response to the CEO's wish?
a)
Record the risk in the register and plan for discussing a response in the retrospective.
b)
Work with the team to plan how to use the ML resources and produce a business case.
c)
Anticipate a negative response from the team and be ready to persuade them that their time and skill will be better spent elsewhere.
d)
Ask the team to produce a SWOT analysis supporting human-based validation.
154.
A project manager is working on a software development project. Two customers are repeatedly submitting new feature requests. The completed scope definition for the product's next version release has already been provided to stakeholders.
What should the project manager do next?
a)
Ask to meet with the product manager, and discuss reducing the number of new requests.
b)
Meet with the sponsor immediately to discuss project boundaries.
c)
Meet face-to-face with stakeholders to set expectations.
d)
Assess the scope management plan to see how changes in scope are managed.
155.
As part of an organizational change program, an experienced project manager with agile experience and certification is hired by a company with a strong predictive culture.
Which two actions can the project manager take to start helping the company adopt agile methodologies? (Choose TWO.)
a)
Ensure that the MoSCoW method is used to write all project requirements.
b)
Analyze all planned projects to pick the appropriate agile model.
c)
Show stakeholders how agile can increase quality and decrease risk.
d)
Train project teams to be more self-reliant and cross-functional.
e)
Identify opportunities for incremental business value delivery.
156.
An agile team needs to decide who should represent them in the Scrum of Scrums.
Which option should be used to select the best-suited team member?
a)
Scrum
b)
DevOps
c)
eXtreme Programming
d)
CI/CD
157.
A Project Manager joins a project as a replacement on a project team. During initial meetings, the Project Manager realizes there are many differing opinions about how to address technical decisions. Team members do not respect each other's ideas, and the environment is becoming counterproductive. However, the team developed processes and procedures and is now working smoothly and productively on the project, without conflict or interruption.
In what phase of development is the team?
a)
Forming
b)
Storming
c)
Norming
d)
Performing
158.
A Project Manager needs to successfully lead a project that has diverse, globally-dispersed team members.
What should the Project Manager do to develop cultural sensitivity?
a)
Explore each team member's culture in-depth for several weeks to be sensitive to their needs.
b)
Seek help from the human resource department to obtain formal training in this area.
c)
Travel to each team member's geographic location to gain awareness of their culture and meet face-to-face.
d)
Be aware of local customs, remain flexible when working with team members, and recognize that culture is learned.
159.
As part of effective leadership, Project Managers help team members grow and keep them motivated throughout each project.
What is one trait that supports this effective leadership?
a)
Stand up for the team’s beliefs and be assertive.
b)
Challenge the team by delegating project tasks.
c)
Use daily discussion sessions to solicit and respond to the team’s concerns.
d)
Provide a team reward for each successfully completed task
160.
A new Project Manager joins the project’s daily standups, only to find that the project team spends too much time discussing ways to deal with obstructions in the project. Because of these discussions, standups often last well over two hours.
What process should be used to deal with this issue?
a)
Ask team members to invite their managers to standup sessions, in order to find solutions more quickly.
b)
Explain to team members that long discussions take time away from actual work on the project.
c)
Insert a new team member who will manage obstacles and schedule additional meetings to discuss possible solutions.
d)
Tell the team members that they are required to shorten the standup meetings and improve on finding solutions.
161.
A project needs a specialized resource. A resource that fits the needs of the project is identified, and can work onsite, but lives in another country. The visa process was expected to take weeks but is now taking months.
What should the Project Manager do?
a)
Ask the existing team to work overtime.
b)
Place a limit on the project's scope.
c)
Put the project on hold by an equivalent duration.
d)
Request that the resource work virtually.
162.
A Project Manager joins a project that has the following features:
-Globally distributed team
-Budget that is fixed
-Very tight deadlines.
During planning, what should the Project Manager do to avoid any scope creep and keep the team focused on delivering a product that meets requirements?
a)
Ask that all development team leads prepare detailed requirements.
b)
Hold daily stand-ups with all development teams.
c)
Put any changes to scope through the formal approval process.
d)
Disallow stakeholders from directly interacting with the development team leads.
163.
There are necessary changes being requested to a project; however, team members are not in agreement regarding how to implement the changes. The Project Manager needs to address this issue.
Which action should the Project Manager take?
a)
Use the change management plan and ensure all team members and stakeholders understand and follow it.
b)
Schedule an in-person meeting with the project sponsor and the board to address the issue.
c)
Hold a meeting with team members to assess the issues and request changes where needed.
d)
Ensure all requested changes are applied to the project and communicate face-to-face with all team members.
164.
There are concerns about the cost risk of adding an external supplier at the mid-point of a project. Still, several team members have been transferred to another project, and the Project Manager requires resource support from an external supplier. The Project Manager needs to work with the procurement team to establish specifications and type of contract to be used.
What should be done?
a)
Suggest a fixed price incentive fee (FPIF) contract.
b)
Recommend a time and material (TM) contract.
c)
Suggest a cost plus incentive fee (CPIF) contract.
d)
Recommend a firm fixed price (FFP) contract.
165.
An empowered agile team showed impressive progress in the first four iterations, but now the product owner has noticed low output in the latest five iterations without any apparent reason.
What could be the cause of this situation?
a)
The team worked on low-complexity stories from the backlog in the first four iterations.
b)
Technical debt has set in and the team's output will keep dropping until the cause is eliminated.
c)
The team was in the storming stage of the development and now have moved to norming.
d)
There is most likely a specific under-performing team member slowing the team down.
166.
A project that is nearing completion has the following characteristics:
-It is very large.
-It contains functional groups in five different countries.
-Closeout documents are being prepared.
The Project Manager needs to gain acceptance of the project deliverables. What should the Project Manager do?
a)
Seek the project sponsor's sign off.
b)
Contact the steering committee for sign off.
c)
Seek sign off from the director of the Project Manager's business unit.
d)
Contact managers from the five countries involved in the project for sign off.
167.
The Project Manager has a large project with functional groups in four countries. Now that the project is close to completion, the Project Manager needs to obtain the correct signoff on the acceptance of project deliverables.
What should be done to obtain the appropriate signoff on this project?
a)
Ask the project sponsor to sign off.
b)
Ask the steering committee to sign off.
c)
Ask the director of the Project Manager's business unit to sign off.
d)
Ask for signoff from the managers of the four countries involved in the project.
168.
A project has the following characteristics:
-Is in the process of completing the planning stage.
-A key stakeholder will be unavailable for 2.5 weeks during the project.
The Project Manager must decide what to do first, after learning about the key stakeholder's unavailability.
What is the correct step to take?
a)
Ensure that the issue log is updated and inform the other stakeholders.
b)
Request that the finance department provide a replacement during the stakeholder's absence.
c)
Organize a meeting with the sponsor to evaluate the situation and identify alternatives.
d)
Continue with planning, and acknowledge the impact the change may have on the project schedule.
169.
The Project Manager reviews the issue log and sees that three tasks assigned to three team members are significantly behind schedule.
How should the Project Manager handle this issue?
a)
Meet with the relevant team members to review the tasks and determine a strategy for resolving the issue.
b)
Contact the project sponsor and escalate the issue in order to reduce delays.
c)
Ask those who are responsible for the reason for the delays and their plans for next steps.
d)
Instruct the team to quickly bring the tasks up to date, so that the project is not at risk.
170.
Although a previously-identified technical issue has been resolved, the Project Manager is warned that the same issue is likely to occur on similar projects in the future.
Which document should be part of the first step in responding to the warning?
a)
The issue log.
b)
A risk report.
c)
A communication for the project sponsor.
d)
The lessons learned register.
171.
A Project Manager has the following situation:
-A very long project management plan is drafted.
-Stakeholders on the project are spread across three continents.
-The Project Manager needs the stakeholders to approve the plan in as short of time as possible.
What is an appropriate course of action for the Project Manager to take?
a)
1. Divide the plan into sections.
2. Based on their areas of expertise, ask select stakeholders to review particular portions.
b)
1. Send the plan to each stakeholder individually.
2. Ask them to add their comments and return it for updating.
c)
1. Arrange a meeting with all stakeholders.
2. Have the stakeholders review the plan before the meeting.
d)
1. Schedule individual meetings.
2. Invite only the key stakeholders, and walk them through the plan.
172.
A project has increased in size. As a result, the project's single sponsor is replaced by a steering committee.
What should the Project Manager do to accommodate this new development?
a)
Ensure that the communications and stakeholder engagement plans are revised to include the new steering committee members.
b)
Ensure that the initial project plan is followed, since the new stakeholders will focus on the project’s progress to date.
c)
Introduce the steering committee to the team and continue to follow the initial project plan in order to meet project deadlines.
d)
Make sure that the new steering committee members are included when sending the current status report for the project.
173.
A project was not meeting scheduled dates for some tasks, so the Project Manager reprioritized a number of subsequent tasks to try to get the project back on track. The reprioritization did not fix the problem, and now the Project Manager needs to escalate the issue to project stakeholders.
To escalate the issue, to which plan should the Project Manager refer?
a)
Communications management plan.
b)
Stakeholder engagement plan.
c)
Change management plan.
d)
Baselines for scope plan.
174.
A Project Manager is doing the following:
-conducting a risk analysis based on a high-level scope, and
-using expert judgment to prepare a document.
What is the Project Manager doing, based on the description of the activity?
a)
Creating a project charter.
b)
Preparing a project scope statement.
c)
Creating the project management plan.
d)
Preparing a risk management plan.
175.
The project requires the development of a human resources information system (HRIS) to centrally manage human resources and payroll. The project sponsor is a multinational company. The Project Manager reviews historical data on the company’s human resources practices and considers the regulatory framework of the project. Still, there are concerns about project risks.
What should the Project Manager do in response to these concerns?
a)
Log high-level project risks.
b)
Calculate and quantify project risks.
c)
Formulate a risk mitigation plan.
d)
Engage in regular risk reviews.