WorksheetsLesson 2 - SAFe Quiz
Total questions: 14
Worksheet time: 5mins
Name
Class
Date
1.
What are the SAFe Core Values?
a)
Empowerment, Teams, Decentralization of Control, Value
b)
Built in Quality, Program Execution, Alignment, Transparency
c)
Incremental Delivery, Transparency, Trust, Built in Quality
d)
Lean-Agile Leadership, Build in Quality, Agile Architecture, Flow
2.
What is the foundation of the SAFe House of Lean?
a)
Value
b)
Leadership
c)
Innovation
d)
Culture
3.
What is one pillar of the SAFe House of Lean?
a)
Flow
b)
Deliver Fast
c)
Vision
d)
Transparency
4.
Which is one of the four pillars in the SAFe House of Lean advocates a "go see" mindset?
a)
Flow
b)
Innovation
c)
Respect for people and culture
d)
Relentless improvement
5.
Which statement is a principle of the Agile Manifesto?
a)
Customer collaboration over constant indefinite pace
b)
Customer collaboration over ongoing internal conversation
c)
Customer collaboration over feature negotiation
d)
Customer collaboration of contract negotiation
6.
Responding to change over…
a)
Processes and tools
b)
Comphrehensive documentation
c)
Contract negotiations
d)
Following plan
7.
"Take and economic view" principle includes the practice of …
a)
Devliery before requirement phase
b)
Parallel delivery
c)
Include an economonic feasability study before implementation phase
d)
Deliver value incrementally
8.
Which is an aspect of systems thinking?
a)
The length of the queue impacts the wait time
b)
Optimizing a component does not optimize the system
c)
Mastery drives intrinisic motivation
d)
Cadence makes routine everything that can be routine
9.
A program repeatedly show separate Feature branches rather than a true System Demo, which practice should be reviewed?
a)
Roadmap creation
b)
Continuous integration
c)
Scrum of scrums
d)
Test first
10.
What is an example of applying cadence-based synchronisation in SAFe?
a)
Teams meet twice every Program Increment (PI) to plan and schedule capacity
b)
Teams allow batch sizes across multiple intervals
c)
Teams align their iterations to the same schedule
d)
Team decide their own iteration length
11.
What is one benfit of unlocking the intrinsic motivation of knowledge workers?
a)
to lower work in process (WIP) limits
b)
To provide autonomy with purpose, mission, and minimum constraints
c)
To strive to achieve a state of continuous flow
d)
To centralize decision-making
12.
Infrequent and long-lasting decisions should be centralised
a)
True
b)
False
13.
What is the biggest benefit of decentralized decision-making?
a)
Delivering value in the shortest sustainable lead time
b)
Reducing the number of decision-makers
c)
Reducing the number of Projects
d)
Improving the controlling process
14.
What is the benefit of reduced batch size?
a)
Reduces the holding cost
b)
Enables more accurate long-term plans
c)
Accelerates feedback
d)
Eliminates the cost of quality inspections