IT-PM 2

Total questions: 10

Worksheet time: 5mins

Name
Class
Date
1.
Which of the following is not part of the three-sphere model for systems management?
a)
Business
b)
Information
c)
Technology
d)
Organization
2.
Which of the four frames of organizations addresses how meetings are run, employee dress codes, and expected work hours?
a)
Structural
b)
Human resources
c)
Political
d)
Symbolic
3.
Personnel in a ____________ organizational structure often report to two or more bosses.
a)
functional
b)
project
c)
matrix
d)
hybrid
4.
roject work is most successful in an organizational culture where all of the following char_x0002_acteristics are important except ____________.
a)
member identity
b)
group emphasis
c)
risk tolerance
d)
control
5.
A ____________ is a product or service, such as a technical report, a training session, or hardware, produced or provided as part of a project.
a)
deliverable
b)
product
c)
work package
d)
tangible goal
6.
Which of the following statements is false?
a)
An analysis project life cycle is a collection of project phases.
b)
A product life cycle is the same as a project life cycle
c)
The waterfall approach is an example of a predictive life cycle model
d)
Agile is an example of an adaptive life cycle model.
7.
Which of the following terms describes a framework of the phases involved in developing information systems?
a)
Systems development life cycle
b)
Rapid application development
c)
Predictive life cycle
d)
Extreme programming
8.
The nature of IT projects is different from the nature of projects in many other industries because they are very ____________.
a)
expensive
b)
technical
c)
diverse
d)
challenging
9.
What term describes an organization’s acquisition of goods and services from an outside source in another country?
a)
Globalization
b)
Offshoring
c)
Exporting
d)
Global sourcing
10.
____________ is the leading agile development method.
a)
Extreme programming
b)
Sprint
c)
Kanban
d)
Scrum