PM1 Unit 4 Estimations

Total questions: 5

Worksheet time: 3mins

Name
Class
Date
1.

A project manager estmates that most likely a rodeo will take 3 months to produce, an optomistic timeline would be 1 month will be, and if lots goes wrong it will take up to 7 months. What estimate should they give using the 3-point method? TE=(O+4L+P)/6

a)

4 months

b)

3 months 10 days

c)

3.5 months

d)

20 months 2 days

2.

A project manager estmates that most likely a rodeo will cost $14,000 to produce, an optomistic cost would be $10,000, and if lots goes wrong it will take up to $27,000. What cost estimate should they give using the 3-point method?

TE=(O+4L+P)/6

a)

$15,600

b)

$13,500

c)

$30,000

d)

$15,500

3.

A project manager estmates that most likely a rodeo will cost $14,000 to produce, an optomistic cost would be $10,000, and if lots goes wrong it will take up to $27,000. What cost estimate should they give using a 20% extra reserve analysis with the 3 point method?

TE=(O+4L+P)/6

a)

$18,600

b)

$30,000

c)

$14,850

d)

$16,800

4.

A team is using vendor analysis with quotes to determine what to charge for hosting a competitive event at their local community center. Vendor A quoted $8,000, Vendor B quoted $10,500, and Vendor C quoted $5,500. What would be a safe quote to give based on vendor analysis?

a)

$9,000

b)

$8,000

c)

$10,500

d)

$5,500

5.

An the expert wedding planner tells you that the wedding described should cost $15,000 with 300 memebers. What will you quote if the customer decides on 500 guests using the parametric method?

a)

$25,000

b)

$15,000

c)

$20,000

d)

$30,000