1.

A natural person under Philippine law with a valid certificate of registration and a valid professional identification card for the lawful practice of architecture.

a)

Architect

b)

Architectural firm

c)

Consulting Architect

2.

Directly and professionally responsible for the total design of the project for the client and who shall assume the civil liability for the plans, specifications and contract documents he/she signed and sealed.

a)

Architect-of-Record

b)

Architect-in-charge of Construction

c)

Consulting Architect

3.

Directly and professionally responsible and liable for the construction supervision of the project.

a)

Architect-of-Record

b)

Architect-in-charge of Construction

c)

Consulting Architect

4.

An architect professionally and academically qualified and with exceptional or recognized expertise or specialization in any branch of architecture.

a)

Architect-of-Record

b)

Architect-in-charge of Construction

c)

Consulting Architect

5.

For individual architectural practice, the architectural firm must be duly registered with the __ as a sole proprietorship

a)

DTI

b)

SEC

c)

PRC

6.

For group architectural practice, must be registered with the __ and with the __as a professional partnership or as an architectural corporation

a)

DTI

b)

SEC

c)

PRC

7.

Used when undertaking a relatively small project. The Client selects his Architect on the basis of: Reputation, Personal or business acquaintance or recommendation of a friend, Recommendation of the Architect’s former Client, Recommendation of another Architect

a)

Direct Selection

b)

Comparative Selection

c)

Design Competition

8.

May be conducted by committees representing institutions, corporations, or public agencies.

a)

Direct Selection

b)

Comparative Selection

c)

Design Competition

9.

Under Comparative Selection, The Client issues an ____ which includes the Terms of Reference (ToR) for the project which is based on the Design Brief prepared by another Architect. The selection committee established by the Client may consist of representatives from other State-regulated professions and/or the construction industry, as well as persons with related expertise

a)

Invitation

b)

Pre-qualification

c)

Interview

d)

Verification

10.

Under Comparative Selection, Architects and/or PRC-registered Architectural Firms (AFs) submit information regarding their qualifications and expertise.

a)

Invitation

b)

Pre-qualification

c)

Interview

d)

Evaluation and ranking

11.

Under Comparative Selection, The Architect explains his methodology in translating the plan/design requirements of the proposed project

a)

Pre-qualification

b)

Interview

c)

Verification

d)

Evaluation and ranking

12.

Under Comparative Selection, The selection committee may visit buildings designed by the Architects and check references such as former clients and financial institutions.

a)

Pre-qualification

b)

Interview

c)

Verification

d)

Negotiation

13.

Under Comparative Selection, The selection committee may adopt its own procedure in evaluating the entries and recommending the most capable firm.

a)

Pre-qualification

b)

Interview

c)

Verification

d)

Evaluation and ranking

14.

Under Comparative Selection, The Architect explains to the Client the Scope of Services and the Architect’s Fee as prescribed under the Architect’s Guidelines

a)

Interview

b)

Verification

c)

Evaluation and ranking

d)

Negotiation

15.

Used for civic or monumental projects. The competition may either be an idea competition, design, or design-build competition. Various Architects or architectural firms submit plans/design solutions to a particular design problem and are judged on the basis of comparative excellence.

a)

Direct Selection

b)

Comparative Selection

c)

Design Competition

16.

Advantage of Design Competition

a)

The Client/ Committee will have a wider range of options

b)

Expensive and time consuming

c)

Time and effort required may discourage qualified firms

d)

Some potentially unscrupulous prospective Clients will seek free services under the guise of design competition

17.

Applicable only to non-creative work such as accounting, secretarial, research, data gathering, preparation. Based on technical hours spent and does not account for creative work since the value of creative design cannot be measured by the length of time the designer has spent on his work. of reports and the like

a)

Multiple of Direct Personnel Expenses

b)

Professional Fee + Expenses

c)

Lump Sum (Fixed Fee)

18.

This method of compensation is frequently used where there is continuing relationship involving a series of Projects.

a)

Multiple of Direct Personnel Expenses

b)

Professional Fee + Expenses

c)

Lump Sum (Fixed Fee)

19.

This method may be applied to government projects since they entail more paper work and time-consuming efforts

a)

Lump Sum (Fixed Fee)

b)

Per Diem/Honorarium

c)

Multiple of Direct Personnel Expenses

d)

Mixed Compensation Methods

20.

The architect may be paid on which will require his personal time, such as: attending project-related meetings, conferences or trips, conducting ocular inspection of possible project sites, conferring with others regarding prospective investments or ventures and the like

a)

Per Diem/Honorarium

b)

Mixed Compensation Methods

c)

Professional Fee + Expense

d)

Lump Sum (Fixed Fee)

21.

The SPP provides for more than one method of compensation on a project. Each project should be examined to determine the most appropriate and equitable method of compensation.

a)

true

b)

false

22.

When a Client calls upon the Architect to give oral or written advice and direction, to attend conferences, and to make evaluations and appraisals regarding a contemplated project and similar activities, the Architect renders valuable inputs on whether or not the Client pursues the project.

a)

Consultation

b)

Pre-feasibility Studies

c)

Feasibility Studies

d)

Architectural Research

23.

Detailed analysis of the project based on prefeasibility studies that will determine the viability of a proposed development

a)

Feasibility Studies

b)

Pre-feasibility Studies

c)

Site Utilization and Land-use Studies

24.

These preliminary studies involve the procurement, analysis and use of secondary information gathered for the project to aid the Client in early decision-making.

a)

Pre-feasibility Studies

b)

Feasibility Studies

c)

Site Selection and Analysis

25.

The formulation of site criteria, assistance to the client in site evaluation, as well as analysis to determine the most appropriate site for a project

a)

Architectural Research

b)

Site Utilization and Land-use Studies

c)

Feasibility Studies

d)

Site Selection and Analysis

26.

Detailed analysis of the site involving the identification of a site’s potentials. The analysis covers the context of the site as well as that of its surrounding environment and the development controls that apply to the site

a)

Site Selection and Analysis

b)

Site Utilization and Land-use Studies

c)

Space Management Studies

27.

The conduct of primary and secondary research and assembled facts used as the basis for the conclusion.

a)

Architectural Research

b)

Architectural Programming

c)

Architectural Programming

d)

Promotional Services

28.

This analytical problem-seeking process will lead to the statement and identification of both horizontal and vertical requirements in offering a solution.

It incorporates a space program with characterizations of the envisioned spaces such as ambiance, cost range, etc

a)

Architectural Programming

b)

Architectural Research

c)

Space Planning

d)

Space Management Studies

29.

The Architect determines the adequate size and appropriate configuration for a proposed project in consideration of the use, allocation and interface of spaces for given activities.

It is done mainly through primary data gathering such as interviews, consultations, interfaces, focus group discussions (FGDs), space planning surveys, space audits, and analysis

a)

Architectural Programming

b)

Space Planning

c)

Space Management Studies

d)

Value Management

30.

An analysis of the space requirements of the project based on organizational structure and functional set-up. This analysis pinpoints linkages and interaction of spaces. The formulation of the space program will serve as the basis for the development of the architectural plan/design.

a)

Space Planning

b)

Space Management Studies

c)

Value Management

d)

Design Brief Preparation

31.

This technique is applied in the cost management process to minimize the negative effect of many cost-reduction programs.

The goal is to achieve an unimpaired program at a minimum cost. Thus, a plan, design, or system that has been successfully value-managed will still satisfy the same performance criteria as the costlier alternatives.

a)

Space Management Studies

b)

Value Management

c)

Cost

Management

d)

Development

Control

32.

the Architect states the project terms of reference (ToR) including the concept, objectives, and other necessary requirements to bid out architectural services (whether public or private)

a)

Design Brief

b)

Service Agreement

c)

Statement of the Problem

d)

Design Concept

33.

Projects may require this service in order to develop and generate financial support and acceptance from governing agencies or from the general public, In such cases, the Architect can act as the agent of the Owner by producing and coordinating the additional activities necessary to complete the services. In all such activities, the Architect must maintain his professional status as the representative of the Owner

a)

Promotional Services

b)

Administration Services

c)

Technical Services

d)

Marketing

Services

34.

Foreign architects who wish to render regular design services must first comply with the requirements of RA 9266:

a)

Temporary/Special Permit

b)

A work permit from DoLE

c)

Must work with a local counterpart who is an RLA

d)

DTI

35.

BPO and KPO firms can render architectural services for projects located on Philippine soil

a)

YES

b)

NO

36.

This phase involves the definition of the requirements of the project by the owner

The architect in turn informs the owner of the technical requirements of the project and the concomitant professional fees

a)

Project Definition Phase

b)

Schematic Design Phase

c)

Design Development Phase

37.

In Project Definition Phase, duties include except

a)

Preparation of an initial statement of probable construction cost

b)

Consultation with the owner to ascertain the conceptual framework and related requirements

c)

Gathering of relevant data leading to the definition of the requirements of the project, including the scope of the architect’s services

d)

Evaluates the owner’s program, schedule, budget, project site and proposes methods of project deliveries

e)

Review and refinement of the requirements and the translation of them into an architectural program

38.

This phase consists of the preparation of schematic design studies derived from the project definition phase, leading to conceptual plans

a)

Project Definition Phase

b)

Schematic Design Phase

c)

Design Development Phase

39.

In Schematic Design Phase, duties include except;

a)

Evaluates the owner’s program, schedule, budget, project site and proposes methods of project deliveries

b)

Prepares the initial line drawings representing design studies leading to a recommended solution

c)

Submits to the owner a Statement of the Probable Project Construction Cost (SPPCC)

d)

Diagrammatic layout of construction systems

40.

Based on approved schematics and conceptual plans, the architect prepares: consisting of plans, elevations, sections and other drawings, Outline specifications, Diagrammatic layout of construction system, And updated SPPCC

a)

Design Development Phase

b)

Contract Document Phase

c)

Construction Phase

41.

consisting of detailed designs and construction drawing, Prepares Technical Specifications

a)

Design Development Phase

b)

Contract Document Phase

c)

Bidding/Negotiation Phase

42.

Submits to the owner __ sets of all construction drawings and technical specifications for purposes of obtaining a building permit

a)

5

b)

6

c)

7

d)

3

43.

In this phase, the architect prepares bid documents, helps the owner establish a list of prospective contractors

a)

Contract Document Phase

b)

Design Development Phase

c)

Construction Phase

d)

Bidding/Negotiation Phase

44.

In Construction Phase, the architect;

a)

Makes decisions on all claims of the owner and contractors on all matters relating to the execution and progress of work or the interpretation of the contract documents

b)

Prepares change orders, gathers and turns over to the owner written guarantees required of the contractor and subcontractors

c)

Makes periodic visits to the project site

d)

The architect shall not be required to make exhaustive on site supervision to check on the quality of the work involved

e)

Assists owner in obtaining proposals from contractors, analyzes bid results and prepares abstract of bids, notice of award, notice to proceed and other construction contracts

45.

These certificates will constitute a certification to the client that the work has progressed to the state indicated and that to his best knowledge, the quality of work performed by the contractor is in accordance with the contract documents

a)

Certificates for Payment

b)

Certificates for Completion

c)

Certificates for Construction

46.

more extensive inspection or full-time (8-hour) construction supervision be required by the client, a separate full-time supervisor shall be hired and agreed upon by the owner and the architect subject to the conditions provided in the SPP document on full-time supervision

a)

true

b)

false

47.

Provide information on requirements, Designate a representative authorized to act on his behalf, if necessary, Promptly make decisions to avoid delay and issue such decisions only through the architect, Give the architect a certified survey of the site, Promptly pay for the architectural and engineering/allied services required for the project, Pay for the design and consulting services on specialty systems which may be required for the project

a)

owner's responsibility

b)

architect's responsibility

c)

contractor's responsibility

48.

If the owner observes or otherwise becomes aware of anything that may impair the successful implementation of the project, he shall give prompt written notice to the contractor

a)

false

b)

true

49.

When the suspension of construction exceeds a period of 3 months, the fee for the remaining works shall be doubled.

a)

true

b)

false

50.

Any SPPCC or any cost estimate submitted by the architect can attain only a certain degree of accuracy. As the architect has no control over the cost of labor and materials, or the many factors that go into competitive bidding, he does not assume any professional responsibility for such cost estimates, unless glaring errors or discrepancies are clearly evident

a)

true

b)

false

51.

The architect’s fee is a gross amount. Any tax (exclusive of income tax) that the national and/or local government/s may not be imposed on the architect as a consequence of the services performed for the project shall be paid by the owner

a)

true

b)

false

52.

During the progress of work, the owner shall furnish the architect a copy of the records of expenses being incurred on the construction. Upon completion of the project, the owner shall furnish the architect a copy of the summary of all cost of labor, services, materials, equipment, fixtures and all items used at and for the completion of the construction

a)

true

b)

false

53.

All signboards of the general contractor, sub-contractors, jobbers and dealers that shall be placed at the project site during the progress of construction shall be approved by the owner as to size, design and contents

a)

true

b)

false

54.

means the cost of the completed building to the owner, including the MEPF systems, elements attached to the building and all items indicated in the plans, designs, drawings and specifications prepared by the architect and his consultants

a)

Project Construction Cost

b)

Project Cost

c)

Cost of Work

55.

shall include cost of the construction as well as all professional fees, permits, clearances and utilities and cost of acquiring the project site/lot, cost of money, etc.

a)

Project Construction Cost

b)

Project Development Cost

56.

The PCC does not include any of the fees for the architect, the engineer, the specialist consultants or the salaries of the construction inspectors

a)

TRUE

b)

FALSE

57.

The cost of materials used and the labor for their installation are part of the PCC.

a)

YES

b)

NO

58.

Involves the detailed planning and design of the indoor areas of any proposed building, including retrofit, renovation, rehabilitation or expansion work, including the architectural laying out of all building engineering systems

a)

Architectural Interiors

b)

Site Development Planning

c)

Site and Physical Planning Services

59.

involves the detailed planning and design to control sound transmission for compatibility with the architectural design concept

a)

Acoustic Design Services

b)

Lighting Layout/Design

c)

Building Systems Design

d)

Security Evaluation and Planning

60.

Involves the detailed planning and design of light transmission, timing and control

a)

Acoustic Design Services

b)

Lighting Layout/Design

c)

Electrical Layout/Design

61.

The space planning, lay-outing and utilization of spaces within and surrounding a specific building have to be a well-coordinated effort so that both the building and the host environment shall act as one

a)

Site Development Planning

b)

Site and Physical Planning Services

c)

Comprehensive Development Planning Services

d)

Facilities Maintenance Support

62.

concerned with the general quality of the settings for people and their activities, buildinqs and other natural and man- made phenomenon. The architect undertakes the site planninq of a proiect that requires a composite arranqement of several buildinqs/ structures and their requisite amenities, facilities, services and utilities within a natural or built setting.

a)

Physical Planning

b)

Site Development Planning

c)

Comprehensive Development Planning Services

63.

based on the concept of expanded physical planning services to include other activities necessary for the proper handling of the numerous components considered in the formulation, implementation and realization of a Master Development Plan (MDP)

It covers the range of all services from primary data gathering through the formulation of the MDP and the parallel preparation of the environmental impact assessment (EIA).

a)

Comprehensive Development Planning Services

b)

Site and Physical Planning Services

c)

Site Development Planning

d)

Security Evaluation and Planning

64.

The suitably trained and experienced consulting architect in this area of architectural practice provides research, assessment, recording, management, interpretation and conservation of historical heritage.

a)

Historic/Heritage Conservation and Planning

b)

Forensic Architecture

c)

Post-design Services

d)

Architectural Research Methods

65.

The consulting architect arranges and formulates methods of rating and ascertaining the value of structures or facilities which must be fully secured, kept safe, protected, assured, guaranteed and provided sufficient safeguards for the conduct of any work or activity

a)

Security Evaluation and Planning

b)

Building Systems Design

c)

Facilities Maintenance Support

d)

Building Testing/Commissioning

66.

The architect in this area of practice engages in methods of producing building components in a highly engineered, efficient and cost-effective manner, particularly for residential and commercial applications.

a)

Building Systems Design

b)

Facilities Maintenance Support

c)

Building Testing/Commissioning

d)

Building Environment Certification

67.

The consulting architect in this area of practice provides the client with means and measures to ensure the proper function and maintenance of the building and site after the final inspection.

a)

Facilities Maintenance Support

b)

Building Testing/Commissioning

c)

Building Environment Certification

d)

Forensic Architecture

68.

The Architect recommends the systematic process of ensuring that a building's array of systems is planned, designed, installed and tested to perform according to the design intent and the building's operational needs.

a)

Building Testing/Commissioning

b)

Building Environment Certification

c)

Forensic Architecture

d)

Building Appraisal

69.

The consulting architect in this area of practice must have much more than the basic knowledge of green architecture and environmental/sustainable design

 He/she must possess sufficient knowledge of the governing environmental laws and environmental investigation procedures under international protocols such as the Philippine Solid Waste, Clean Air and Clean Water Acts, DENR administrative issuances, and the like.

a)

Building Testing/Commissioning

b)

Building Environment Certification

c)

Forensic Architecture

d)

Building Appraisal

70.

The architect in this area of practice undertakes a scientific study on the built environment's well being, focusing on the ways in which the building can best maintain itself and prolong its life in a cost-efficient manner, and finally provide recommendations to the client

a)

Building Testing/Commissioning

b)

Building Environment Certification

c)

Forensic Architecture

d)

Building Appraisal

71.

The consulting architect in this area of practice places value on the building condition and defects, and on its repair and maintenance, including the required improvements.

a)

Building Testing/Commissioning

b)

Facilities Maintenance Support

c)

Building Appraisal

d)

Structural Conceptualization

72.

The architect in this area of practice conceives, chooses and develops the type, disposition, arrangement, and proportioning of the structural elements of an architectural work, giving due consideration to safety, cost-effectiveness, functionality, and aesthetics.

a)

Building Testing/Commissioning

b)

Building Environment Certification

c)

Building Appraisal

d)

Structural Conceptualization

73.

The Consulting Architect in this area of practice must have much more than the basic knowledge of the following: Site analysis, Space planning and management, Architectural programming, Other services under SPP document 201

a)

Forensic Architecture

b)

Preliminary Services

c)

Contract Documentation and Review Services

d)

Dispute Avoidance and Resolution

74.

The Architect in this area of practice must have much more than the basic knowledge of: Specifications writing, Estimation and quantity survey, Architectural production, Architectural software, Architectural support services, Contract document review

a)

Post-design Services

b)

Contract Documentation and Review Services

c)

Special Building/Facility Planning and Design

d)

Management of Architectural Practices

75.

The consulting architect in this area of practice must have much more than the basic knowledge of preconstruction, construction, post- construction, and the other services under SPP Documents 204, 206 and 207.

Included under this specialized practice is the preparation of the Fire Safety and Life Assessment Report (FALAR) required by RA 9514

a)

Post-design Services

b)

Contract Documentation and Review Services

c)

Architectural Research Methods

d)

Special Building/Facility Planning and Design

76.

The Architect in this area of practice must have much more than the basic knowledge of the various modes of Alternative Dispute Resolution prescribed under RA 9285 (The ADR Act of 2004):

Construction Arbitration and Mediation, Negotiation and Contract Administration, Quality Surveys, Appraisals and Adjustments and Expert Testimony

An architect specializing in ADR must preferably be stateaccredited

a)

Dispute Avoidance and Resolution

b)

Special Building/Facility Planning and Design

c)

Building Components

d)

Management of Architectural Practices

77.

The consulting architect in this area of practice must have much more than the basic knowledge of the following; Research methods, Philippine architecture and its history, Architectural materials and finishes, Building types and standards, Architectural design trends, Architectural writing, Architectural photography

a)

Architectural Research Methods

b)

Dispute Avoidance and Resolution

c)

Management of Architectural Practices

d)

Building Components

78.

The consulting architect in this area of practice must have much more than the basic knowledge of the planning and design processes required for: Housing developments, Recreational and tourism estates, Healthcare and hospitality facilities, Transportation and telecommunications facilities, Production and extractive facilities, Utility-related developments, Secure facilities, business and industrial parks, Economic zones and community architecture

a)

Building Components

b)

Management of Architectural Practices

c)

Special Building/Facility Planning and Design

d)

Architectural Research Methods

79.

The consulting architect in this area of practice must have much more than the basic knowledge of: Building materials and finishes, Construction methodologies, Building envelopes including cladding and roofing systems, Architectural fenestrations, Architectural hardware, fixtures and fittings

a)

Architectural Research Methods

b)

Special Building/Facility Planning and Design

c)

Management of Architectural Practices

d)

Building Components

80.

The consulting architect in this area of practice must have much more than the basic knowledge of: The types of architectural office operations, Architectural office management, Accounting, finance, taxation and audit, The labor code, Architectural marketing and project development, Proposals, negotiations, contracts, File management and limitations of BPO/KPO operations

a)

Management of Architectural Practices

b)

Post-design Services

c)

Preliminary Services

d)

Comprehensive Development Planning Services

81.

The four principal members involved in the design and building construction process are:

a)

OWNER

b)

ARCHITECT AND HIS SPECIALIST CONSULTANTS

c)

CONTRACTOR

d)

The individual or group of individuals

82.

When projects were still manageable in size, the architect was then assisted by a construction inspector, traditionally called

(a)  

83.

As projects become more complex, it becomes necessary for a construction supervision group to do the full-time inspection at the project site

a)

TRUE

b)

FALSE

84.

SPP DOC 204 A FULL TIME SUPERVISION

SCOPE OF SERVICES

(CSG)

a)

Quality control

b)

Evaluation of Construction Work

c)

Preparation of Daily Inspection Reports

d)

Filing of Documents

e)

Coordination and supervision

85.

The construction supervision group (CSG) shall not assume the responsibility of the contractor’s project superintendent and shall not make decisions on matters that are the sole responsibility of the architect-of-record (AoR)

a)

true

b)

false

86.

The construction supervision group (CSG) is responsible to the owner only for

a)

administrative matters

b)

technical matters

87.

The construction supervision group (CSG) is responsible to the architecton-record (AoR) for

a)

administrative matters

b)

technical matters

88.

Under Article 1723 of the present Civil Code, the CSG may appear to have legal responsibility for the design and construction

a)

true

b)

false

89.

The architect as the ____ is directly responsible to the owner on all aspects of the construction work: programming, coordination, quality and cost control and time management

a)

project manager

b)

construction manager

c)

contractor

d)

AICC

90.

1. Sees to it that the building and all the parts thereof (structure, plumbing, electrical system, partitions, finishes, etc.) are all in good condition

2. Formulates and enforces rules for the proper use of the building and facility, particularly in the common areas and the exit areas

3. Monitors security services

4. Monitors maintenance and upkeep services (cleanliness of corridors, lobbies, stairs and other common areas, exits, parking areas, garbage collection

a)

Building Maintenance

b)

Grounds and Landscaping Supervision

c)

Business Development and Management

d)

Post Construction Evaluation

91.

1. Supervises landscape contractors and gardeners for the proper watering, pruning, trimming and maintenance of the landscape (both hardscapes and softscapes)

2. Maintains orderly entrances, exits and parking areas

3. Maintains streets, walkways and ramps

a)

Building Maintenance

b)

Grounds and Landscaping Supervision

c)

Building Equipment Maintenance

d)

Business Development and Management

92.

Assists the proper third parties in seeing to it that all equipment (air-conditioning, sprinkler system, generators, transformers, telecommunications equipment, etc.) are properly maintained and in good working condition

a)

Building Maintenance

b)

Grounds and Landscaping Supervision

c)

Building Equipment Maintenance

d)

Business Development and Management

93.

Innovates schemes to attain maximum building occupancy, Bills the tenants for rentals and utilities (electricity, water, telephone, cable, gas and other/related dues)

a)

Building Maintenance

b)

Building and Facilities Admin

c)

Business Development and Management

d)

Post Construction Evaluation

94.

Evaluates the initial design program vs. the actual use of the facility, Determine the effectiveness of the various building systems and the materials systems in use, Assist the proper third parties in evaluating the functional effectiveness of the design and construction process undertaken

a)

Post Construction Evaluation

b)

Business Development and Management

c)

Building Equipment Maintenance

d)

Grounds and Landscaping Supervision

95.

Comprehensive Architectural Services refers to the range of professional services that covers:

a)

Pre-design Services

b)

Regular Design Services

c)

Specialized Architectural Services

d)

Construction Services

e)

Design-Build

96.

involves management activities over and above the normal architectural and engineering services carried out during the pre-design, design and construction phase

The overall objective is to have control over time, cost and quality relative to the construction of a project

a)

Project Manager

b)

Construction Manager

c)

Architect

d)

AICC

97.

The role of the Project manager

a)

prime responsibility for the design of the project

b)

responsible for their respective engineering plans

c)

responsible for his men and equipment and the delivery of the project

d)

prime responsibility is the exercise of overall cost control. He will plan, program and monitor the various activities, and will act as an adviser on material costs and construction methods

e)

decisions on the project and assures that funds are available to complete the project

98.

the project manager should conduct regular consultations with the owner and with the architects and engineers on all aspects of planning for the project

a)

pre-construction phase

b)

construction phase

99.

If the project manager (PM) also serves as the construction manager (CM) to oversee time, cost and quality control during the construction of the project, he shall provide the services detailed under SPP Documents 204-A and/or 204-B

a)

pre-construction phase

b)

construction phase

100.

Design-build services by ____

The scope of design-build services by administration includes the architect’s regular design services (see SPP Doc. 202):

Project definition phase

Schematic design phase

Design development phase

Contract document phase

Construction phase

a)

administration

b)

technical

c)

with guaranteed maximum project construction cost

101.

In Design-build services with guaranteed maximum project construction cost, The client is given an estimate of the project, and upon completion, if there are realized savings from the estimated project construction cost. The client gets to keep the savings.

a)

yes

b)

no

102.

Under Design-build services with guaranteed maximum project construction cost,

when the actual cost exceed the estimated project construction cost plus 10%, the architect shall be liable for the excess amount but only up to the amount of his administration fee

a)

true

b)

false

103.

under ADC Classifications, it is for actual projects proposed for implementation.

a)

Project ADCs

b)

Ideas competitions

104.

Under ADC Classifications . it is set as a design and planning exercise to elucidate a problem

a)

Project ADCs

b)

Ideas competitions

105.

In ADC, It is essential that the anonymity of competitors be maintained until the final judgment of the competition.

a)

true

b)

false

106.

President Marcos, recognizing the role of the professionals in nation building, issued Letter of Instruction No. 1000 which directs all government agencies to give priority to Filipino professionals in the hiring of its employees and in the engagement of professional services.

a)

March 20, 1980

b)

March 20, 1981

c)

March 20, 1979

d)

March 20, 1975

107.

A coalition of purely Filipino professional consultants or consulting firms in collaboration with foreign professional consultants and/or foreign consulting firms authorized to render consultancy services in the Philippine setting

(a)