Total questions: 176
Worksheet time: 1hrs 29mins
A project manager is facilitating a sprint retrospective meeting where the team members discuss customer dissatisfaction from the product increment they delivered during the sprint. The discussion reveals some issues with the remote team members who were primarily using email to communicate with the rest of the team.
What was the most likely cause the product increment did not meet customer expectations?
Failure to respond to changes in scope
Non colocated team members
Delivering working software in each sprint
Demotivated team members
You are leading a project to replace an aging bridge spanning a river in a heavily populated area. The new bridge would include a pedestrian pathway, that is not a feature of the existing bridge. The bridge is well under construction when residents learn the pathway would allow strangers to enter their neighborhood at all times. The residents demand the elimination of the pathway.
What would have been the best course of action to avoid this situation?
Identify the pathway as a possible point of contention with stakeholders early in the project
Nothing could have been done differently because the project was authorized per project charter
Engage a public relations company to handle community outreach once local residents voiced their disapproval
Reroute the pathway entrance during construction to an old railway train instead of the local street
You are managing a project team that has recently been expanded by new team members working remotely from another country. their roles have been outlined to from a preliminary team charter. Nevertheless, you have noticed a considerable lack of acceptance of cultural differences in the team, resulting in frequent conflicts.
Which of the following techniques could help you in this situation? (Choose three answers)
Focus groups
Role definition
Ground rules
Ability tests
Meetings
Customer requirements for the new application to be developed by an agile team limit the technology choices to only two approaches. The team members are not familiar with any of them and ask the scrum master for advice.
Which of the following should the scrum master recommend to select the best approach?
A risk-based spike
Exploratory testing
An architectural spike
Prototyping
You are leading a project with a critical time constraint and cannot afford any project delays. An argument between two project team members over a report format to document their testing result turns into a shouting match. The team members draw you into their argument. You realize that resolving the conflict would delay the project timeline.
What is your best course of action?
Tell the team members to figure it out for themselves
Look for an approach that would completely satisfy both team members
Request the team members to go back to work to avoid any further delays
Select the report format that you think is best and make decision
You have been assigned to lead an initiative for which the business case has not been sufficiently made to get approval to initiate a hybrid project. In some of the past project, teams realized too late into project execution that no one in the company had the skills needed to build some of the features, so it was developed by a contractor, resulting in cost overruns.
What would yo do differently in your assignment to avoid cost overruns?
Start with a proof of concept
Use burndown charts for reporting
Developed a project charter
Encourage team knowledge sharing
You are leading a software development project for a client. Due to unstable requirements, you have elected to use a
change-driven life cycle. You are currently facilitating an iteration planning meeting with the product owner and the development team.
What should you do as part of the meeting?
Control the scope to prevent scope creep
Review the product increment and get feedback
Make sure the scope of the iteration is fixed
Recommend improvements for the next iteration
You have been assigned to manage an agile project to develop various analytical tools for your company's executive
team. Everyone involved in the project is new to agile methodologies. After the first few tools are released, the executives
are frustrated that the tools they needed the most are still in the pipeline for future development.
What might you have done differently to avoid this issue?
Provided the product owner with the training on how to prioritize the product backlog
Trained the development team on pair-programming and code refactoring
Explained that agile focuses on developing the highest-risk features last to avoid early failure
Colocated the development team to take advantage of osmotic communication
A project manager is assigned to an agile software development project for a large banking corporation. With the project
just getting underway, the project manager has learned about new hacking tactics that present a potential threat to
regulatory compliance for the project.
What should the project manager do next?
Review the risks during the project retrospective
Analyze the consequences of non-compliance
Submit a change request to update the risk management plan
Develop a cumulative flow diagram
An organization has established a controlling project management office (PMO). The first task of the PMO is to update
the guidelines for project compliance in the organization.
Which of the following could the PMO enforce? (Choose three.)
Use of particular project management methodologies
Adoption of specific templates, forms, and tools
Adherence to local health regulations
Conformance to governance frameworks
Assignment of project managers by the PMO
As a project manager, you recently completed a project team performance appraisal, and a previously unknown
competency gap in technical skills was uncovered, which needs to be addressed.
What should you do next?
Implement the response planned for this risk
Conduct unplanned training to address the competency gap
Consult the training management plan
Let go of the staff who have technical skill gaps
Due to an uncertain market environment and complexity of upcoming projects, your company is considering a transition
from a traditional to hybrid project management approach. The company tasks you with researching various options for
incorporating new project management practices that would help the company move closer to its goal.
Which of the following would you least likely recommend?
Involving business analysts in requirements management
Increasing the level of detail during initial project planning
Implementing tools to identify complex project elements
Incorporating agile, incremental, and iterative practices
While monitoring project work, the project manager notices an increase in actual costs that have not been accounted for
in the original budget. To understand whether a change request to update the cost baseline should be submitted, the
project manager gathers raw observations and measurements of all of the costs that have been authorized, incurred,
invoiced, and paid.
What has the project manager gathered?
Planned value
Earned value
Work performance information
Work performance data
A project manager is estimating the length of time the project will take. The project manager worked on a comparable
project two years ago that installed 10 miles of guardrails at a rate of one mile a day in similar weather conditions, using
the same size crew on the same type of highway.
What estimating technique would be the appropriate option for the project manager to use for his duration estimate?
Parametric estimating
Analogous estimating
Bottom-up estimating
Three-point estimating
A project team that is experienced in the waterfall project management approach has been assigned to their first agile
project. To make the transition easier, it has been decided to keep some elements of the waterfall approach in place.
During the iteration review, it was realized that a misunderstanding among the development team has led to a duplication
of efforts.
How might the project manager address this issue?
Bring up the topic during the upcoming iteration retrospective
Do nothing since the team members are transitioning from waterfall to agile
Fallback to a waterfall project management framework going forward
Submit a change request to update the communications management plan
The plan for the first iteration was to complete 80 story points. However, the team was only able to complete 60. Each
story point earns $1,000 for the project. The actual cost of the iteration was $70,000. As the iteration retrospective
approaches, the scrum master requests that the team prepares all the data required to calculate the various earned value
metrics.
At the retrospective, the team determines that the schedule performance index (SPI) of the iteration was ________.
(On the real PMP exam you may be asked to provide your answer by filling in the blank with the letter representing the
correct answer. But here in the simulator, we are asking you to select the answer below.)
1.333
0.750
1.143
0.857
You are new to the organization and have been given a few weeks to get yourself settled before starting your project in a
role of a project manager. During this period, you realize that you have no authority over resources, the stafare grouped by specialty, the budget is under the full control of those group's managers, and you as a project manager
are only required to dedicate part of your time to perform the project work.
What type of an organization are you working in?
Weak matrix
Functional
Balanced matrix
Projectized
You are leading a project to be developed incrementally in small releases. Requirements have been established for the
initial release. Feedback from a focus group will determine the scope of each subsequent release. The client has
established a strict budget for the entire project.
In this adaptive environment, which is the best way to proceed?
Use a traditional waterfall approach for the project
Add prioritized features to the project scope with each release until the budget is exhausted
During initial project planning, develop a detailed budget for each release
Use a change control board (CCB) to prevent scope creep
In their first iteration, an agile team completed only half of the planned work. It turns out that before the current project
began, the team members were requested to provide ongoing support for the prior release. Angry project stakeholders
meet with the scrum master and complain that supporting prior releases should have never been included in the project
plans.
How should the scrum master respond?
Agree with the stakeholders and remove all further support work from the next iterations
Ignore the stakeholders' complain and instruct the team to continue supporting the prior releasesI
Explain that routine work of supporting prior releases may be included in project plans
Request that from now on the team work overtime to complete both the planned work and support
You are preparing for an upcoming software development project. The project will be initiated and planned using a
predictive approach, while the development team will use Kanban. A budget has been established for training, and you
need to determine how to allocate those funds.
What is your best course of action?
Send the development team to a seminar on maximizing WIP
Provide training to transform T-shaped people into I-shaped people
Deliver training to convert I-shaped people into T-shaped people
Train the team on how to best prioritize the features to be developed
A project manager invited several vendors to a pre-bid conference. After a private conversation with one of the vendors
who had an inquiry about a new mandatory government requirement, the project manager sent an email to the vendor to
address the question. The project manager realizes that the requirement should have been included in the project scope
baseline and the statement of work (SOW).
What should the project manager do in this situation?
No further action is needed as the vendor's question have been addressed
Update the statement of work and the scope baseline, and communicate the changes to all vendors
Update the statement of work and the scope baseline, and hold another pre-bid conference
Update the SOW, submit a change request to update the scope baseline, and communicate the changes to
all vendors
As project execution begins, the project manager acquires the project team and, based on project needs, decides that the
team will use Scrum to develop the product of the project. After conducting an assessment of the project team's Scrum
skillset, the project manager realizes that according to the Shu-Ha-Ri model, the team is at the Shu level.
What should the project manager recommend to the team?
Request project termination
Modify Scrum to fit the project needs
Develop a new agile method
Closely follow Scrum ceremonies
A project manager is explaining the roles and responsibilities for the quality assurance process with the project team.
Who will play a role in this process?
The project manager, project team, and management of the performing organization
The project sponsor along with the project manager and project team
The project manager along with the project team
The project manager, project team, project sponsor, management of the performing organization, and the
customer
In order to take advantage of the best talent available, a project manager recruits developers internationally rather than
just locally. She is delighted to have acquired such highly skilled individuals but now needs to develop them into a
cohesive team. Ideally, the project manager would like to bring everyone together at the home ofbudget does not allow for travel expenses.
What is the best tool or technique for the project manager to use in this situation?
Sensitivity analysis
Recognition and rewards
Virtual teams
Colocation
You are acquiring the necessary resources for your project. The organization where you are employed is an international
company with locations in several countries. With personnel located around the globe, you will be forming your project
team as a virtual team, and the team members will be allowed to work from their home offices.
What special considerations do you need to take into account while working with your team?
Project expenses
Communication planning
Pre-assigned team members
Team members with disabilities or mobility issues
You have just been assigned to an upcoming agile project. As part of pre-project work, you review all of the organization's
policies and procedures regarding compliance. You realize that only some of them may be applicable to your project.
What should you do first?
Switch the project management approach from agile to traditional
Incorporate all compliance policies and procedures in the implementation strategy
Ensure compliance activities are included in the project schedule baseline
Classify the compliance categories to determine the expenditure of project resources
During the development of the stakeholder engagement plan, the project manager realizes that a key stakeholder is
resistant to the project. Without the support of this stakeholder, the project may fail.
What is the best course of action for the project manager to identify the reason for the stakeholder being resistant?
Escalate to the project sponsor
Update the stakeholder register
Use the mind mapping technique
Utilize an Ishikawa diagram
An agile software development project consists of four releases, with features incrementally added with each release.
Due to an excessive number of defects found by users after the first release, the risk response plan was implemented,
which involved more rigorous testing by the project team. After the second release, the client has reported two bugs.
What must first be done to determine the effectiveness of the implemented risk response?
Schedule a release retrospective
Complete a sensitivity analysis
Conduct technical performance analysis
Perform a reserve analysis
You are leading a project to develop a product that will be sold through an existing nationwide dealer network. The
product will be built incrementally by a virtual team, while the dealer training and product rollout processes will be welldefined upfront.
You want the dealers to provide the team with regular feedback throughout product
development.
What is the best strategy to achieve your goal?
Suggest that the dealers attend the biweekly iteration retrospective meetings
Collect requirements upfront and develop a detailed WBS for product development
Invite the dealers to attend product demonstrations via video conference
Colocate the dealers with some of the developers for the duration of the project
wo project team members are having a disagreement over how to approach a minor technical detail. The project
manager has little experience working with them, and her technical knowledge is limited.
What is the best action for the project manager to take?
Abide by the decision of the most senior team member
Avoid being involved in the discussion and decision making
Stop the discussion and direct the team members to get back to work
Request the human resource department's representative to step in
After reviewing proposals for a large-scale product development project, vendors X and Y are equally qualified to deliver
both the hardware and software. The project manager believes the hardware should be developed with a traditional
project management approach, but the software might be better suited to an agile framework.
What is the best course of action?
Contract with vendor X for hardware, with vendor Y for software and use the appropriate methodology for
each
Contract with vendor X for both hardware and software and require an agile framework for the entire project
Contract with vendor Y for both hardware and software and require a waterfall approach for the entire project
Contract with either vendor X or vendor Y for both hardware and software and utilize a master services
agreement
You review the WBS of your project and realize that due to the lack of in-house expertise, some of the deliverables will
need to be outsourced to a vendor. However, the requirements for these deliverables are not well-understood at the
moment. Therefore, you decide that the outsourced portion of work will need to be managed using an agile framework.
What is your best approach in negotiating an agreement with the vendor?
Seek an informal agreement rather than a formal contract
Secure a fixed-price contract for the outsourced scope
Negotiate aggressively for the most advantageous terms
Pursue a shared-risk-reward contract relationships
A project manager is in the process of creating the stakeholder register. He has just completed the stakeholder
classifications and needs to update the project roles.
According to the partial stakeholder register below, which individual is most likely to be the project sponsor?
John Snow
Todd Young
Marie Smith
Tonya Stewart
A project manager is executing the quality management plan of a project to develop a prototype medical device. Given
the nature of the project, the quality standards are very stringent. With no known cause, it becomes apparent that the
product quality does not meet project requirements.
What is the best course of action for the project manager to take in this situation?
Direct the project team to improve the quality of their work
Ask the project sponsor what to do
Create an affinity diagram
Develop an Ishikawa diagram
Your project team functions as a well-organized unit. The team members are interdependent and work through issues
smoothly and effectively.
What is your best course of action?
Provide clear direction on the project objectives and the behavior expected from the team members
Help the team to get through their struggle by ensuring they listen to each other and understand their
differences
Ensure the team resolves conflicts quickly and continues to work collaboratively and step in only when needed
Serve as a gateway between the project team and the stakeholders and delegate decision making to the
team members
For the third consecutive time, at the end of each iteration, a software application developed by the team fails during the
Control Quality process conducted by the quality assurance (QA) department. This situation causes rework for the
product and a delay in the project schedule. The project manager wants to reduce the feedback loop to the shortest
possible interval.
What is the best course of action for the project manager?
Shorten the iteration length
Reduce the size of the user stories
Revise the schedule baseline
Suggest pair programming to the team
To comply with the customer's contract, the project must use a certified agile practitioner to lead and coach the project
team. However, the only certified agile practitioner employed by the company was just assigned to another project. The
project manager must now hire an independent contractor to serve as the agile coach, which delays the start of project
execution.
Which of the following may have helped to avoid the delay in executing the project?
Documenting the potential unavailability of the agile coach in the project assumption log
Using different verbiage in the resource management plan to remove the requirement for an agile coach
Assigning a different team member from the company to serve as the agile coach
Securing the internal agile certified practitioner with a pre-assignment when this requirement was first
identified
A new smartphone will be developed by two teams: a hardware team that will use a predictive project management
approach and a software team that will use an agile framework. Each team is colocated but resides in two different parts
of the country. The teams will need to coordinate their activities very closely, but bringing them together in one location is
not an option.
What should the project manager do to create the most collaborative environment?
Use a blended agile approach
Create a fishbowl window
Transition the hardware team to agile
Implement caves and common
A client completed a walkthrough of the deliverables and formally accepted the work. The next day, the project manager
returns to the project site to pick up company equipment and make arrangements for final payment.
What should the project manager do when meeting the client as part of project closure?
Confirm the final acceptance of the deliverable
Settle procurement claims
Validate the scope objectives have been met
Ensure quality assurance was performed
After an agile team completes three iterations, the project manager determines that the average velocity of the team for
these three iterations was 30 story points. There are 292 more story points to complete the remaining portion of the
project.
How many additional iterations will it take for the team to complete the project?
7 iterations
8 iterations
9 iterations
10 iterations
You are leading a software development project, which requires knowledge of several programming languages. During
project execution, one of the developers has been pulled out of the project by her functional manager. The manager
provided you with another developer instead.
What should you do first?
Provide the new developer with an ability test
Introduce the new developer to the project sponsor
Schedule training for the new developer
Assign the developer the next user story in the backlog
A project has to procure goods and services from a seller. Some aspects of the procurement are well-defined up-front
while others will be known only after initial deliverables are validated and accepted.
What contracting technique would work best for this procurement?
Multi-tiered structure
Cost plus award fee
Procurement audit
Request for quotation
You are the project manager for a project that is in its early stages. During a meeting, your boss informs you that senior
management would like you to include a particular staff member on your project team because of their necessary
expertise. You have not recruited any other team members, and the project has not even been formally authorized yet.
How should you handle senior management's request?
Deny the request because the project manager should be the one to acquire project resources.
Accept the request, since identifying specific resources for the project can occur as part of the early planning
process.
Accept the request only after you have finished creating the project management plan.
Deny the request since you have not had an opportunity to verify that the individual has the proper skills.
You are drafting a stakeholder engagement plan for a software development project. The product will be built using a
scrum framework. You want to ensure that the stakeholders' level of influence on product development is analyzed and
categorized.
What is your best course of action?
Submit a change request to update the stakeholder register
Wait until the stakeholders attend the first sprint review
Suggest that the product owner use a power/influence grid
Conduct the analysis yourself using hierarchical charts
A project manager is determining the budget for a software development project where the product will be built
incrementally. Since the project is subject to a strict budget, the project manager has to ensure that scope and schedule
baselines stay within cost constraints. The project manager includes budgetary requirements in the release plan.
How can the information in the release plan help the project manager with determining the project budget?
The release plan can become a part of the cost management plan.
The velocity can be increased for the project to stay within budget constraints.
Release burndown charts can be updated with cost trend lines.
Review meetings with stakeholders can be used to discuss the scope and schedule.
Development team members argue with the product owner who rejected a deliverable the team developed during the
recent iteration. The project manager schedules a meeting with the team, product owner, and other relevant stakeholders
to break down the situation and identify the root cause of a misunderstanding.
Which of the following will be considered an antipattern if used during the meeting?
Drawing a fishbone diagram
Using the five whys method
Maximizing the number of action items
Defining the problem statement
A member of an agile project team gathered data about the project and discovered an opportunity for improvement. The
team member thinks that a change to the process used by the team to develop the product of the project would improve
team performance. The team member approaches the scrum master for advice on the best way to implement the change.
What advice can the scrum master give to the team member?
Make the change, see what happens, then report the results during the upcoming retrospective meeting
Submit a change request, wait for the approval of the change control board, and implement the change
Send an email to the functional manager to report the findings and ask for permission to make the change
Inform the team of the opportunity for improvement and, if the team supports it, implement the change
Gold plating had been an issue with your current software development project. However, you found that ever since
instituting daily stand-up meetings, no more features or functionalities that the customer did not request have been
introduced into the project.
What is your best course of action to prevent gold plating for the remainder of the current project and on future projects?
Bring up the topic during the project retrospective
Capture the best practice in the lessons learned register
Gold plating adds customer value and should not be prevented
Ensure that the scope management plan includes daily stand-up meetings
At the daily scrum meeting, a team member brings up a problem accessing a database that impedes his progress.
Another team member offers a possible solution, which triggers a conversation between the two. After a few minutes, the
scrum master cuts off their conversation, reminding them that the daily scrum is not the appropriate venue for their
discussion.
What should the scrum master do next?
Submit a change request to the database team so that the problem gets resolved and impediment removed
Request that the team members swarm on the database problem and resolve it as soon as possible
Suggest the two team members place the issue in the parking lot and discuss it once the meeting is over
Allow the conversation between the two team members to continue until the issue is resolved
A project team is using the Stacey Complexity Model to evaluate the degree of uncertainty in the project and select the
appropriate project life cycle. The team maps the technical degree of uncertainty on the horizontal axis and requirements'
uncertainty on the vertical axis. The resulting mapping suggests that a predictive life cycle would work best for this
project.
Where on the Stacey Complexity Model did the team most likely map the project?
(On the real PMP exam you may be asked to provide your answer by clicking the correct area in the image. But here in
the simulator, we are asking you to select the answer below.)
A
B
C
D
As you execute the quality management plan for a project to develop a new autopilot feature for a vehicle, you have
created the diagram below, which compares the vehicle speed with uncommanded lane departures.
What can be said about this diagram?
Affinity diagram, which shows a weak correlation between the speed and lane departures
Scatter diagram, which shows a strong correlation between the speed and lane departures
Affinity diagram, which shows a strong correlation between the speed and lane departures
Scatter diagram, which shows a weak correlation between the speed and lane departures
Near the end of an iteration, the project team is ready to lead a product review with the product manager.
What is the objective of the review?
Validate the product scope
Manage product quality
Control the product scope
Close the project or phase
You are leading an agile project to develop a computer game, which will be broken down into four releases. After the first
release, the initial online reviews are poor, and the early adopters have provided detailed feedback about what they don't
like about the game. You are concerned about the impact of the poor reviews on future releases.
What is the best course of action?
Hold a release retrospective
Terminate the project
Discuss the issue with the project sponsor
Expedite the delivery of the second release
You are attempting to coordinate activities between your project, another related project, and operations, all of which are
being managed as a group. A conflict has arisen over control of a key resource that is vital to both projects as well as
operations. The conflict has reached an impasse and needs to be resolved by a higher authority.
What is your best course of action?
Discuss the problem with the portfolio manager
Escalate the issue to the operations manager
Raise the issue with the other project manager
Request help from the project management office
You are leading a software development project, which is utilizing an agile framework. While monitoring the progress of
the project, it is apparent that velocity is trending down, and you are aware of some setbacks that have been encountered
by the development team. You want to capture and analyze lessons learned so far during the project to improve the
process going forward.
What is the best way to achieve this goal?
Perform a sprint review
Schedule a sprint planning meeting
Conduct an iteration retrospective
Lessons learned are not utilized on agile projects
You are in the initiation stage of a project that aims to deploy and then maintain the robotics for an automated production
line for a returning client. In the project charter, you need to include the agreed mean time to recover (MTTR) in the event
of a breakdown.
What should you do to find this information?
Do nothing since agreements are not yet available during project initiation
Refer to the procurement management plan
Review any emails or other correspondence with the client
Check the service level agreement with the client
A project manager has compiled a list of key deliverables, which include the working software, employee training
materials, user manuals, etc.
When is the first time that these key deliverables would have been identified?
During the Define Scope process
When processes of the Executing Process Group are performed
During the Develop Project Charter process
When processes of the Planning Process Group are performed
Midway into an iteration, an agile team faces a minor technical issue. One of the team members recalls that the agile
coach is an expert in the field from her past experience as a senior developer. The team requests that the coach help
resolve the issue.
What should the agile coach do first?
Let the team resolve the issue
Help the team resolve the issue
Resolve the issue for the team
Consult with the product owner
To engage the newly identified stakeholders in the project at the earliest opportunity, the scrum master suggests inviting
them to the upcoming sprint review meeting to demonstrate to the stakeholders that the team is moving in the right
direction and get feedback from the stakeholders about what the team has accomplished.
Which of the following is another reason for inviting the stakeholders to this meeting?
To reflect on the team performance
To prioritize high-risk user stories for the next sprint
To reprioritize the release backlog
To discuss the high-level plans for the next sprint
To better use existing knowledge and to create new knowledge for a project, the project manager is looking for ways to
identify any knowledge gaps.
Which of the following would help the project manager the most to complete this process?
Bid documents
Resource breakdown structure
Quality metrics
o-complete performance index
A project manager is considering to change the Control Costs process currently used on her project. Instead of submitting
budget change requests to the CCB, she wants to invite stakeholders to the parking lot portion of the daily standups and
discuss requested changes there. The project manager meets with the stakeholders to propose the process change.
Which of the following arguments would least likely to convince the stakeholders of the benefits of the new process?
The cost management and change management plans will be updated to reflect the new process.
Earned value analysis data from a previous project will be compared to iterative data accumulation.
Only those budget change requests that do not affect the project cost baseline will be discussed.
Other project managers in the organization going through similar process changes will be consulted.
You have joined a project in which requirements are elaborated at several intervals during delivery, and the delivery is
divided into subsets of the overall product. Change is incorporated at periodic intervals, and risk and cost are controlled
by progressively elaborating the plans with new information. Key stakeholders are regularly involved.
What development approach is used on your project?
Agile
Predictive
Hybrid
Periodic
A scrum master is conducting a daily standup. Each member of the development team states that their work has been
stalled due to various blockers. As a result, the entire development team has been idled, and the schedule baseline is in
jeopardy.
What should the scrum master do first?
Attempt to resolve the problems during the meeting
Analyze and prioritize the blockers
Assign the team to work on another project in the meanwhile
Escalate the issue to the project sponsor
A project manager and team are in the process of finalizing all project activities. They have obtained final acceptance and
transferred ownership of deliverables, obtained administrative closure, collated lessons learned, archived all project
documents, and obtained feedback from relevant stakeholders. Finally, the project manager and team have been
released and reassigned to other assignments.
Based on the information provided, what might have been forgotten?
Reviewing project requirements
Verifying project deliverables
Sharing the final project report
Conducting benefit analysis
You have been assigned to lead an agile project. You want to ensure that project information is shared within and across
the organization, so that any misalignments, dependencies, or other issues related to the frequently changing
requirements are surfaced as quickly as possible.
How could this goal be best achieved?
By distributing the project report weekly
By inviting stakeholders to daily standups
By promoting aggressive transparency
By sharing comprehensive documentation
A project manager has been asked to create a document that formally authorizes a project to use ground-penetrating
radar to map geological conditions along a proposed crude oil pipeline route. The performing organization has a written
formal agreement in place to share the data with a local university. The project manager has reviewed the business
documents and considered any relevant external environmental factors to create the requested document.
What might the project manager do next?
Research the stakeholder engagement plan for any information to be included in the document
Ensure any relevant information from the memorandum of understanding (MOU) is included in the document
Review the business case for any pertinent information
Look to see if a benefits management plan was previously created
While performing monitoring and controlling activities, the project manager discovers inconsistencies between the project
management plan and the project's actual performance. She now needs to determine corrective actions to minimize the
impact of the inconsistencies on the project.
In what project document would she have documented the inconsistencies and would look at to review them?
Quality report
Change log
Assumption log
Issue log
Your company has been contracted by a client for a software development project. The project will use agile methods to
deliver product increments. For the client, however, this project will be their first experience with agile. You want to make
sure that the client gains the full benefit of early and continuous delivery of software.
What is your best course of action?
Develop a change management plan to address the inevitable changes
Request the client to take part in product testing to speed up delivery
Gain alignment with the client on the timing of project deliverables
Instruct the project team to develop all features in a single release
You are managing a project that is nearing its end. You have been reviewing the project management plan to ensure that
all the project work is completed and that the project has met its objectives. The next thing you need to do before moving
on to the next project is to complete the administrative closure of the project.
Which of the following activities will not be performed as part of this process?
Closing seller contracts
Handing over the project deliverables to operations
Transferring the knowledge gained to the lessons learned repository
Measuring stakeholder satisfaction
A scrum master is leading an agile project in which the development team has failed to achieve the sprint goal for the
past three iterations. During the sprint retrospective, the team decides to implement several changes to improve velocity.
How might the scrum master verify any performance improvement?
Calculate the project's CPI
Create a burndown chart
Review the burnup chart
Study the Gantt chart
A project manager creates a procurement statement of work (SOW) from the project scope baseline. The scope of the
SOW, however, is not yet well defined, therefore the project manager decides to contract with a vendor to provide an
agile team of programmers. The contract is structured with fixed-price increments based on user stories.
How might the project manager verify that the vendor has met the contractual obligations?
Wait until the team completes the development of all user stories specified in the SOW
Request the product owner to approve or reject user stories during a sprint review
Validate the user stories as soon as they are completed at any point during a sprint
Conduct a procurement audit with the vendor each time a sprint retrospective is held
A project manager is reviewing a document where information about problems impacting project performance is recorded
and monitored. According to the document, a new problem that was logged yesterday by a project team member
indicates that delays have just exceeded the established schedule variance threshold and corrective action is required.
No additional details about the new problem are provided in the document.
What should the project manager do immediately?
Assign a responsible party to follow up on the problem
Record the disposition of the change request
Send the project progress report to the stakeholders
Update the lessons learned register
You are leading a software development project using agile methodologies. If the project is successful, it will open up vast
opportunities for future revenue and growth. The project has a high risk of failure, but the potential benefits outweigh the
risks. These risks and rewards must be considered when selecting the content of each iteration.
Which features should be prioritized and developed first in this scenario?
High-value and low-risk features
Low-value and low-risk features
High-value and high-risk features
Low-value and high-risk features
You are leading a meeting with the project sponsor and key stakeholders to review the recently completed project
management plan. The goal of the meeting is to establish a common understanding of the plan, answer any questions or
concerns, and gain formal approval of the project management plan.
Which of the following interpersonal and team skills is the least beneficial to the project manager to use to achieve the
meeting’s goal?
Conflict management
Facilitation
Meeting management
Team building
An organization is transitioning from predictive project management to agile. As a project manager, your upcoming project
will require compliance reporting that will need to be submitted to internal auditors due to regulatory oversight.
How might you address the need for compliance reporting in this hybrid environment?
Work with the auditors to streamline the process
Task one of the team members to complete the compliance reporting
Transfer the responsibility of compliance reporting to the legal department
Avoid agile as it not suitable for projects that operate in a regulatory environment
The project you are leading is supposed to upgrade the application developed by your company on desktop computers
and mobile devices. Last week, a major supplier of electronics unexpectedly released a new mobile device. You realize
that your application, with a little bit of modification, can run much faster and more securely on the new device.
What should you do next in regards to this opportunity?
Create a cost forecast and communicate it to stakeholders
Submit a change request to modify the application
Update project funding requirements in consideration for the unexpected work
Conduct variance analysis for an appropriate reserve amount
The project manager is 6 months into a multi-million-dollar project. The latest analysis shows a CPI of 1.5 and an SPI of
0.6.
What should she do?
Nothing. The analysis shows the project is on budget and on schedule.
Consider crashing the project schedule
Replace one of the higher paid team members with a lower-salaried employee
Inform the customer that you are extending the delivery date for the project
Up until now, your project team has allowed the use of flextime where project team members may take time off during
regular business hours and make up the time during the evening hours or weekends. Recently, excessive use of flextime
has become a roadblock as some team members are not available when needed. The team feels they should set a
standard that flextime is only to be used for personal emergencies.
How should you handle this situation?
Contact the human resources department to update the corporate policies to prohibit flextime
Submit a change request to update the team charter based on the team's inputs
Discuss the issue with the team and update the team charter accordingly
Do nothing as the team has already agreed to use flextime for personal emergencies only
An agile coach has been nurturing and growing team members through and beyond their current roles. This helped
several team members to develop their personal and professional skills to the level where they felt that they outgrew their
roles. Eventually, some of them left the team to pursue new opportunities within the organization and outside of it.
Was the agile coach right in her approach?
No, agile leaders must ensure the team members never leave their teams
Yes, agile leaders should develop team members even if that means losing them
No, agile leaders may develop team members but not beyond their current roles
Yes, agile leaders have to make sure team members eventually leave the team
You are a project manager conducting a meeting with your project team. The goal of the meeting is to improve the overall
team environment to enhance project performance. The meeting becomes contentious with team members interrupting
each other and being disrespectful to each other's suggestions. You attempt to return civility to the meeting by
establishing ground rules for acceptable behavior, but working relationships may already be damaged.
What might you have missed that could have prevented this situation?
Sharing the team management plan with the project team
Involving the project team in the creation of a team charter and gaining agreement with the content
Allowing the team members to work independently and avoid interaction
Making sure each team member has a copy of the project charter
A project manager is developing a quality management plan for a project to design a medical device. Given the nature of
the product, quality will play a vital role. Additionally, the acceptance criteria for the project deliverables will have a direct
impact on quality standards. The project manager wants to gain an understanding of the acceptance criteria.
What document should the project manager review for this purpose?
The project charter
The requirements management plan
The scope statement
The acceptance criteria register
During an initial project planning meeting, the project team decides to save a portion of cost estimates in the work
package to offset the potential risk of advances in technology, which would make their current equipment obsolete.
What is the best course of action for the project manager?
Create a management reserve
Submit a change request
Create a contingency reserve
Do nothing as the risk has not yet realized
An agile coach joined a team that has been working on a project for the last few months. The coach noticed that the team
members were struggling to remove impediments, did not have a discipline around time-boxed events, and were not
using information radiators to display the project status.
What is the best course of action for the agile coach to take?
Help the team deal with impediments, remind of the importance of time-boxing, and force the team to use
information radiators
Tell the team to deal with impediments, remind of the importance of time-boxing, and suggest the team to use
information radiators
Help the team to deal with impediments, remind of the importance of time-boxing, and suggest the team to
use information radiators
Do nothing, since the issues are minor and can be handled by the team because agile teams are selfmanaging and
self-organizing
You are leading a project with two dispersed development teams. One team is using traditional waterfall methods, and the
other is using XP for product development. Budgetary constraints prevent any of the team members from being
colocated.
What should you prioritize for team collaboration?
Documenting collaboration requirements of the XP team in the communications management plan
Setting up remote pairing for the XP team and providing video conferencing capabilities for both teams
Allocating dedicated portions of the offices to support the caves and common practice for both teams
No specific considerations are required as both teams can learn to collaborate as they do their job
Following is an illustration of a project network activity node that includes some information about activity B.
Assuming that work starts on day one (not day zero) and given the information provided, what is the late start of activity
B?
35
36
37
39
A project manager is currently in the process of determining, documenting, and managing stakeholder needs and
requirements. Due to the sensitive nature of the project, there is a concern that some stakeholders will not provide candid
feedback unless confidentiality is maintained.
What is the project manager's best course of action?
Conduct interviews to elicit information from stakeholders by talking to them directly
Use brainstorming to generate and collect multiple ideas related to project requirements
Hold a focus group to learn about stakeholder expectations and attitudes about the project
Use multicriteria decision analysis to provide a systematic analytical approach for establishing criteria
A project manager is analyzing the communication needs of stakeholders in order to develop the communications
management plan for a project that will use a hybrid project management framework. The project manager understands
that the plan should accommodate the needs of both predictive and agile aspects of the project.
How should the plan accommodate the agile aspects of this project?
Account for an increased exchange of documentation
Specify the exact number of communication channels
Secure facilities to support face-to-face interactions
Deploy the project management information systems (PMIS)
A new developer joins the project. However, her productivity is limited since she lacks the competency in one of the
programming languages. This language is not only used on this project but will also be required on future projects.
Training costs were not included in the project budget, and the project CPI is 0.75.
What is the best course of action for the project manager?
Submit a change request to update the development approach
Seek approval for the performing organization to absorb the training costs
Stop using this programming language on this project
Terminate the employment of the new developer and find a replacement
An agile project to develop a new application has just finished its first iteration. To better assess marketing and support
needs, the company's management has requested that the scrum master provide a date for when the application can be
launched.
What is the best course of action for the scrum master?
Provide an accurate estimate based on the velocity of the first iteration
Request time to develop the project schedule baseline
If possible, defer estimating until after a few iterations are completed
Provide a random date just to calm the management down
A senior executive suggests initiating a project to replace a significant portion of the company's labor force with an
automated production line. Other company executives are skeptical that this approach is the best way to increase profit
margins and wonder if they are ready to sponsor such an effort.
What is the first thing that should be done in this scenario?
Performing a needs assessment
Consulting with the project management office
Appointing a project sponsor to create a project charter
Providing a project manager with the authority to apply organizational resources
You meet with your team and key stakeholders to decide on what approach, waterfall or agile, should be used for your
project. You explain to the meeting participants that continuous improvement is of utmost priority for the project. Someone
asks you how waterfall methodologies compare with agile as it relates to continuous improvement.
How should you respond to this question?
Waterfall takes a more proactive approach to continuous improvement, comparing to agile which is more
reactive.
Agile projects conduct retrospectives during project execution but not at the end of the project as in waterfall.
Agile teams tend to be more focused on continuous improvement and will review performance more regularly.
Continuous improvement is handled essentially the same in agile and waterfall project management
frameworks.
You are leading an off-grid housing construction project. Each of the ten homes in the development will have solar
shingles to generate energy and a novel energy storage system. The performing organization is highly experienced with
traditional construction methods, but this is their first project to incorporate energy generation and storage.
How might you best support continuous improvement efforts throughout the project?
Construct the homes sequentially using a predictive model and hold a retrospective after the completion of
each home
Review the lessons learned repository during project planning and apply the knowledge gained during project
execution
Build all of the homes concurrently using a predictive approach and update the lessons learned register
continuously
Utilize an incremental project management approach for the development of the homes and hold a project
retrospective
As the project manager, you are in the process of developing a draft of a document that authorizes a new software
development project. You have reviewed the agreements and both business documents.
What else should be done as part of this process?
Identify stakeholders and prepare the stakeholder register
Study the governance functions and processes to provide guidance and decision making
Update the business documents to correct any errors
Review the benefits management plan
As a scrum master, you are facilitating a retrospective for a sprint that failed to meet all of its objectives. Members of the
development team and the product owner are arguing over who is responsible for the failure. After performing a root
cause analysis, you uncover the source of the conflict.
Of the following, what did you most likely discover?
The product owner determined how many user stories were to be completed during the sprint
The development team decided how many user stories were to be completed during the sprint
You, as the scrum master, failed to assign user stories to the development team
The Gantt chart did not include enough story points
ou are planning a kick-off meeting for your new project. The meeting will communicate the start of the project, key
milestones, and other relevant information.
Which of the following best describes the objective of this meeting?
Inform and engage stakeholders and gain commitment
Manage threats and opportunities throughout the project
Ensure that the project is completed on schedule and budget
Secure resources required to complete project deliverables
An agile team is tasked with the development of a robot. The project manager wants to ensure that before the actual
robot is built, the team receives early feedback on requirements and adapts the design accordingly.
Which of the following should the project manager use to achieve that goal?
Prototyping
Design review
Checklists
Business case
You are managing a project with stakeholders from many different departments including marketing, engineering, and
information technology. As you are monitoring stakeholder engagement, it becomes clear to you that stakeholders from
the marketing department who used to be supportive appear to be neutral. After researching the reasons for the gap, you
discover the marketing department views the project communications to be too technical, leading them to lose interest in
the project.
What might be your next step?
Perform a communication styles assessment
Provide technical training for the marketing department
Update the communications management plan
Review the stakeholder engagement assessment matrix
A project manager is leading an agile research and development project. The project team is using a diagram, which
breaks down the causes of an identified problem into discrete branches to determine the main cause of the problem.
Which diagram might the project team be using in this situation?
Pareto diagram
Matrix diagram
Tornado diagram
Why-why diagram
The quality management has been perfect for the project up to this point. Suddenly, the quality assurance (QA) lead who
developed and performed most of the quality activities for the project has been temporarily reassigned to help another
project.
What should the project manager do?
Submit a change request to adjust the cost baseline and the schedule baseline
Request the team to develop replacement quality activities
Assign another team member to carry out the originally planned quality activities
Pause quality activities until the QA lead returns to the project
After the project team has completed their first iteration, you are requested to provide the project's status report to the
sponsor. You collect the following data:
- The cost baseline for the entire project is $528,000
- The schedule baseline provides for six two-week iterations
- The actual costs associated with the first iteration were $80,000
- The team completed 45 of 50 story points planned for the first iteration
What should you report to the sponsor?
The team's velocity in the first iteration is zero
The team's velocity in the first iteration is 50
The SPI for the first iteration is 0.9
The CPI for the first iteration is 1.1
A project manager is implementing the quality management plan for a project to construct a natural gas pipeline. During
this process, an internal audit discovers that while the project meets all applicable government regulations, there is a
discrepancy with ISO 9000 criteria.
Which tailoring consideration did the project manager most likely neglect earlier in the project?
Continuous improvement
Standards and regulatory compliance
Project life cycle
Since the project meets all applicable government regulations, nothing was missed earlier in the project
The agile project team members are all working in an open office space arrangement. There are many conversations
happening concurrently throughout the day.
Which of the following is the best option for the project manager?
Schedule frequent team checkpoints and post project artifacts in a transparent fashion
Request team members to hold off their conversations until formal meeting times
Record the conversations and post them in a shared repository
Designate afternoons as quiet work times
Unlike traditional managers, agile leaders:
Enable team members to act
Solve problems for the team
Create working agreements
Handles uncertainties, risks, and changes
A scrum master is working with stakeholders to develop the project vision for inclusion in the project charter and wants to
ensure that regulatory compliance measures are incorporated into the project requirements.
How might the scrum master analyze the consequences of non-compliance?
Facilitate a project post-mortem
Play a session of "remember the future"
Lead a round of planning poker
Conduct a t-shirt sizing exercise
The project team reports that they have finished creating the requirements management plan, the requirements
documentation, and the requirements traceability matrix. The team informs that they are going to start working on the
project work breakdown structure (WBS) next.
What has the project team forgotten to do?
Create the project scope statement
Complete the project management plan
Update the lessons learned register
Perform the Validate Scope process
You are leading two independent teams working on the same project. The nature of the deliverables requires that one
team takes a predictive approach, while the other uses Scrum. Due to dependencies between the teams and the variable
nature of the outputs from the Scrum team, the predictive team needs to confirm their understanding of the Scrum team's
activities with the shortest feedback loop possible.
What is your best course of action?
Include a project retrospective into the project schedule
Request that the Scrum team use information radiators
Incorporate the use of periodic customer feedback loops
Have the predictive team attend the daily scrum meetings
Your project is running behind schedule. To bring the timeline back into alignment with the project management plan, you
need some of your project team members to work extra hours. In order to motivate your team, you offer each team
member two tickets to a popular sporting event if they work a weekend shift.
What type of power are you using in this situation?
Managerial
Charismatic
Persuasive
Reward-oriented
As a project manager, you are leading a colocated project team that will create deliverables in an agile fashion, followed
by a rollout phase that will use a predictive approach. You are concerned that the transition from agile to waterfall may
cause friction within the project team.
With the development phase complete, how might the team's working agreements need to change in this situation?
The team charter will need to be updated to reflect collective responsibility for the completion of project tasks.
The project manager should institute a set of working agreements that worked well on previous waterfall
projects.
Each project team member will need to develop their own social contract to support the new framework.
The social contract should reflect a transition from collective to individual responsibility for the project tasks.
A project manager has just received a signed formalized document as an output from one of the initiation processes in
her project. This document was prepared by someone external to the project and will be utilized as a catalyst for the
project to move forward.
Which of the following describes this document?
The business case
The scope statement
The project charter
The approved project plan
You and the project management team have been vigilant about observing different aspects of the project to ensure the
project is progressing as planned. Currently, you are using performance data generated during project execution to
determine if the status of overall project risk has changed, if the project assumptions are still valid, if contingency reserves
for cost or schedule require modification, and if project strategy remains valid.
What process are you performing?
Plan Risk Responses
Monitor Risks
Plan Risk Management
Identify Risks
A project manager has been communicating with 10 stakeholders regularly. Last week 2 more stakeholders were
identified and added to the communications management plan.
What is the number of potential communication channels?
66
78
55
12
During a meeting, the product owner restated the product vision, described the target user groups, the business goals,
and main features to be delivered by the agile project in its upcoming releases. Then, to visually depict these features,
the product owner created the product roadmap.
Which of the following best describes the purpose of the meeting?
Establish a shared project vision among the project stakeholders
Create the product backlog for each one of the upcoming releases
Establish a shared release vision among the project stakeholders
Determine the project scope, schedule, cost, quality, and resources
First, a project manager assisted with the development of the project charter which has been approved. Second, he
completed the development of the stakeholder register.
What should the project manager do next?
Submit a change request to update any project documents with information gathered during the Identify
Stakeholders process
Update the communications management plan to include the communication requirements of stakeholders
identified in the newly developed stakeholder register
Update the stakeholder engagement plan with any pertinent information uncovered during the Identify
Stakeholders process
Establish the scope of the project, refine the objectives, and define the course of action required to attain the
objectives that the project was undertaken to achieve
During project execution, the new state-of-the-art technology that is used on the project to produce the deliverables is
unstable, which puts the whole project at risk of failure. Your sponsor is on vacation and cannot be reached. To get
immediate attention to the issue, you want to know what is the escalation procedure.
What should you do next?
Consult the communications management plan
Consult the risk register
Consult the stakeholder engagement plan
Submit a change request to replace the technology
You are managing a virtual project team across multiple time zones. As the project progresses, the team members learn
to trust one another and adjust their work routines to accommodate the different time zones, work habits, and culture.
What stage of team development is being demonstrated in this situation?
Forming
Storming
Performing
Norming
The project management plan and the performance measurement baseline have been approved. As you monitor the
project's progress, you realize the approved budget is limiting the project and will affect the targeted completion date.
This constraint could affect the company's success in the new venture.
What is your best course of action?
Use the contingency reserves
Use the management reserves
Cut costs to stay within the budget
Ask for a change in the budget
The project manager and a stakeholder get into a heated debate about the stakeholder's idea requiring a scope change
to the project. The project manager says the change will not be implemented and that the stakeholder must drop the idea.
The project manager emphasizes that she is the project manager and the decision is final.
Should the project manager have responded differently to resolve the conflict?
No; The project manager has the formal authority to make the final decision.
Yes; The project manager should have discussed the idea with other stakeholders.
No; The project manager was demonstrating the culture in which the company works
Yes; The project manager should have compromised with the stakeholder.
You are a senior project manager who is mentoring a newly promoted project manager. Your mentee states that she has
recurring arguments with her project team and is having difficulty controlling her own temper. This situation has created a
toxic environment for the project team and threatens the successful completion of the project.
What is the best advice for your mentee?
Improve leadership skills
Develop emotional intelligence
Study conflict management
Introduce recognition and rewards
You are leading a software development project for a client. The change control board (CCB) has been inundated with
change requests from the client throughout the project as the product has evolved. This situation drives the team crazy
and makes controlling the project scope extremely challenging and time-consuming.
Which of the following tailoring considerations might you have missed earlier in the project?
Diversity
Stability of requirements
Physical location
Validation and control
The latest software released to the customer in the first project phase is full of defects. The customer is angry and
demands that the development of the new release, which is planned to be delivered in the second phase, is much more
transparent. The customer wants to see the team’s results more regularly and without very long development intervals inbetween.
Which of the following could the project team introduce in the second phase to better comply with the customer's
demand? (Choose four.)
A cadence with regular timeboxes
Regular and frequent retrospectives
Optimization at the level of each individual team member
est-driven development practices
Incremental delivery using a backlog
The deliverables of a two-year-long project have just been accepted. It is four months late, but the customer is pleased to
have it. The project manager is glad to be done with the deliverables but is concerned about the cost and schedule
overruns. He decides to re-run the initial cost-benefit analysis using the actual project costs.
Where should the project manager obtain the initial cost-benefit analysis?
From the customer
The project charter
The business case
The benefits management plan
You are the project manager for the initial design phase of a new ergonomic pen. You have conducted multiple interviews
with pen users and have tested various design concepts. Your most recent design has been verified and accepted by key
stakeholders. The pen design is ready to transition to the team managing the next phase.
Which of the following should you consult to find out who will take ownership of the pen design?
The project management plan
The final report
The scope statement
The communications management plan
You are leading an agile software development project. During a sprint review, the customer rejects the deliverables
stating that the grade is acceptable but not the quality.
Of the following, which might be the best course of action?
Add another developer to increase velocity
Remove some of the features and focus on quality for the next iteration
Increase the number of features for the next sprint
Introduce more rigorous testing during the next sprint to reduce bugs
A project team will work in a noisy environment requiring hearing protection. To communicate in this type of environment,
your employer has a mandatory proprietary instant messaging mobile phone application that will be installed on the
phone of every project team member for the duration of the project.
The requirement to install this messaging application is an example of which of the following?
Pull communication
Push communication
Enterprise environmental factors
Communication model
Late in a project, a key team member leaves the company. The project manager realizes that he does not have enough
team members to meet the hard deadline. At a weekly status meeting, the project manager discusses several options
with his project team, including authorizing additional overtime, hiring subcontractors, or bringing in additional resources
from another project team within the company.
Which resource management technique does the project manager use?
Cost-benefit analysis
Alternatives analysis
Problem solving
Interpersonal skills
Two project team members have had frequent clashes, which have at times resulted in shouting matches during team
meetings. The project manager has intervened, asked them to resolve their differences, and even facilitated a meeting
between them, but things have gotten worse. The project manager is concerned that the situation is negatively affecting
team cohesion and is placing the successful completion of the project at risk.
What should the project manager do next?
Use formal procedures including disciplinary actions
Allow the team members to resolve their differences on their own
Facilitate another meeting between the two team members
Request that the other project team members intercede as a form of peer pressure
You have been requested to fill in for a project manager who has called in sick. As you get yourself familiar with the
project team, you notice that the team members do not collaborate well, and there are a lot of disagreements and
conflicts going on. You feel that the overall environment is counterproductive.
Based on your observations, where is the team on the Tuckman ladder?
(On the real PMP exam you may be asked to provide your answer by clicking the correct area in the image. But here in
the simulator, we are asking you to select the answer below.)
A
B
C
D
E
You are leading a complex project with a schedule baseline that cannot be modified due to external constraints. The
scope, however, is flexible. The project deliverables are produced by three development teams that work independently
from one another. The teams manage their workflow using Kanban.
Which of the following is the most effective tool for you to use to measure the project's progress?
Feature chart
Burndown chart
Burnup chart
Cumulative flow diagram
A project manager has taken over a project that has been in execution for a few months. He ran into problems right away.
He has had difficulty getting sign off on decisions; he doesn't have the authority to acquire the equipment necessary for
the project; the stakeholders and the project team have differing opinions about the objectives and the outcome of the
project.
What is the most likely source of these problems?
Weak leadership skills
Lack of a project charter
Lack of a project management plan
Lack of a procurement management plan
An agile team is trying to determine the ideal iteration length. The team members are having a long and intense argument
about it, but no one is willing to compromise. The scrum master is called in to help resolve the conflict.
What is the best course of action for a scrum master?
Avoid being involved in the process and let the team work out toward a consensus
Recommend evaluating the pros and cons of each one of the suggested iteration lengths
Threaten the team with disciplinary actions if they are unable to come to an agreement
Break the impasse by making the decision for the team before relationships are damaged
You are managing a project, and members of your project team are at odds about the tasks they are assigned.
Disagreements between the team members have escalated and have created a reduction in performance across the
project.
What tool or technique will you use to address the team's issues and get the project back on track?
Networking
Recognition and rewards
Training
Conflict management
During a sprint retrospective, the team members complain that the business analyst has been unresponsive to clarify the
work package to be developed in the sprint. As a result, the work package has not been accepted by the customer. The
scrum master reaches out to the business analyst and requests them to collaborate with the team during the upcoming
sprints.
What else should the scrum master do?
No further action needed as the problem is resolved
Report a work ethics violation to the human resources department
Continue monitoring the business analyst's involvement
Instruct the team to fix the work package to meet customer needs
The PMBOK Guide defines project charter as a document that "formally authorizes the existence of a project and
provides the project manager with the authority to apply organizational resources to project activities."
Developing project charters on agile projects:
Must follow the PMBOK® Guide processes
Must not follow the PMBOK® Guide processes
Is not required because Agile is paperless
Does not necessarily require a formal document
A project manager has developed the following earned value analysis chart for a software development project. Based on
the current trend, what action should the project manager take immediately?
Submit a change request to increase funding for the project
Look for options to reduce costs and improve schedule performance to meet project objectives
No immediate action is required in this case
Crash the schedule to bring it back into alignment with project objectives
A project manager is drafting a charter for a software development project. In support of this process, the project
manager has scheduled a brainstorming meeting to gather relevant information.
Which of the following activities is the project manager least likely to conduct?
Inviting relevant stakeholders to attend the meeting
Ensuring that a software engineer joins the meeting
Arranging for a facilitator to lead the meeting
Following the communications management plan to determine meeting attendees
You are leading a project that was supposed to be managed using agile methods. Every week, however, the product
owner holds a five-hour backlog refinement meeting with the project team where she presents the project scope broken
down to the work package level. After three iterations, the project team's velocity is slower than expected.
What is your best course of action?
Ask the product owner to decompose the scope down to the task level and assign the tasks to the team
members
Advise the product owner to hold two five-hour backlog refinement meetings per week to gain further clarity on
the scope
Coach the product owner on presenting the overall story concept with one-hour weekly backlog refinement
meetings
Hold a team-building exercise with the team members and product owner to improve the communication
between them
It has been decided that the project will be managed using waterfall. However, due to ambiguous requirements, the
software will be developed in short iterations using Scrum. After acquiring a team from within the organization, the project
manager realizes that the organization lacks technical expertise in several key areas and will require external resources
from a vendor. The organization, however, wants to preserve its strategic discretion on the work performed.
What is the best contracting technique for the project manager to use to maximize collaboration with the vendor?
Team augmentation
Early cancellation option
Fixed-price increments
Not-to-exceed time and materials
A conflict between the project manager and the team has been going for a while. The conflict negatively impacts the
team's morale and jeopardizes the project's goals. To address the conflict, the project manager maps the desire to satisfy
the parties' concerns on the chart below. Based on the map, the project manager decides to find a collaborative solution.
Where did the project manager most likely map the desire to satisfy the team members' concerns vs. the desire to satisfy
his/her own concerns?
(On the real PMP exam you may be asked to provide your answer by clicking the correct area in the image. But here in
the simulator, we are asking you to select the answer below.)
A
B
C
D
E
During the current sprint, the product owner's availability has been limited due to other commitments. At the daily
standup, the team members complain that they cannot get answers from the product owner, and, as a result, the
development of the product increment is delayed.
What is the best course of action for the scrum master?
Let the senior developers make the product decisions
Contact the product owner on behalf of the team members
Mention the availability issue during the sprint review
Discuss the availability issue at the sprint retrospective
Two days before the end of the last iteration of the project, an agile coach has noticed that the performance of one of the
developers significantly degraded, risking the iteration goal. The coach and the developer have a one-on-one coaching
meeting scheduled a day after the iteration’s end date.
What is the best course of action for the agile coach to take in this situation?
Conduct the individual performance appraisal of the developer
Ask the team to swarm on the tasks assigned to the developer
Employ real-time feedback to address the issue with the developer
Wait for the one-on-one meeting scheduled with the developer
A PMO steeped in traditional waterfall project management has hired you, as an agile practitioner, to guide the
organization's transformation to agile. After completing an initial assessment of the organizational culture, you have
realized that many of the stakeholders are resistant to the change.
What is your best course of action?
Provide training to ensure the employees are more highly specialized
Transition all projects to agile at the same time
Seek a high-level executive willing to champion the cause
Ensure the work is decomposed into silos
The project team has just completed its fourth sprint. As part of the Control Costs process, you determine that the team's
average velocity is 25 points per sprint, and the team has earned 1/3 of the total number of story points required to
complete the entire project. The average cost per story point is $575.
What is the estimate to complete the remaining work?
$57,500
$115,000
$14,375
$172,500
You have been assigned to lead an agile project. The project team is comprised of experienced agile practitioners who
have been working together for a long time.
In this agile environment, what is the best approach for you to take to manage project integration?
Develop the project management plan that integrates all project activities
Let the team determine how plans and components should be integrated
Seek approval to hire an external project integration management expert
In agile environments, project integration management is not applicable
Monthly audits were performed to determine if project activities comply with corporate policies, procedures, and best
practices. Throughout the project, the results of the monthly audits indicated that the team was in compliance. However,
at the end of the project, it was determined that some of the project activities did not comply with organizational policies.
What most likely caused these compliance gaps to be missed during the audits?
The audits were conducted by the company's internal audit department
The audits were conducted by one of the project team members
The audits were conducted by the project management office (PMO)
The audits were conducted by an auditor external to the organization
A scheduling error occurred on a construction project that you are managing. The painting contractors arrived as
scheduled, but the drywall was not yet finished. As the project manager, you want to know who was responsible for
scheduling the contractors and who should be held accountable.
What tool or technique is most helpful in this situation?
Project organization charts
Resource management plan
Hierarchical charts
Responsibility assignment matrix
You are leading a hybrid project with an agile team developing the web application and a traditional engineering team to
design the servers that will host the application. You want to determine what does your company say about the use of
social media tools to communicate and work with the stakeholders to meet their needs and expectations.
What is your best course of action?
Review the stakeholder register
Check the organizational process assets
Consult with the project sponsor
Check the lessons learned repository
Midway into project execution, a key stakeholder leaves the company. A new stakeholder fills in the vacant role. The
project manager understands that the stakeholder engagement plan should be updated to reflect the strategies and
actions required to involve the new stakeholder in the project. The project manager meets with the new stakeholder for an
interview.
Which of the following questions would be the most helpful for the project manager in updating the plan? (Choose three.)
Have you ever managed a project before?
How much risk are you willing to take for an anticipated benefit?
What position did you hold in your previous company?
What are your communication preferences?
Do you think it was the right thing to undertake the project?
You and your project team have just completed the development of the project management plan for your agile project.
You have requested one of the team members to schedule a meeting to present the finalized project management plan.
The team member has asked who should be invited to the meeting.
How should you respond?
Invite the customer only because it is an agile project
Find the answer in the organization process assets
Invite only the project sponsor and the project team
Invite only the project sponsor and the project team
D
Planning is underway for a project to develop a new online collaboration tool. The team will use eXtreme Programming
(XP) method to develop the tool, while the deployment to the customers will be managed using a waterfall approach. The
agile coach would like to gather early customer feedback to ensure the new tool is aligned with the product vision.
What is the best course of action?
Develop the complete set of features and showcase it at a developer's conference
Create a wireframe for the public to use and provide feedback
Plan for the development of an MVP for a release to a subset of customers
Perform decomposition to create the work breakdown structure
As your project progresses, a team member suggests a minor modification to one of the project deliverables, saying that
the modification will improve the overall performance of the final product. You believe that the modification constitutes a
minor change to the project scope, schedule, and budget, and should be approved without going to the change control
board.
What should you do next?
Approve the change request. As the project manager, you should use expert judgment to decide what is best
for the project.
Meet with the change control board members individually and try to persuade them to approve the change
request.
Submit the change request to the change control board and abide by their decision.
Review the change management plan and follow the established process for processing change requests.
The project requires ongoing stakeholder engagement and needs to respond to high levels of change. The project
manager has chosen an adaptive life cycle for the project. The backlog contains an ordered list of requirements and work.
At the beginning of each iteration, the team determines how many backlog items can be delivered within the next
iteration.
Which process(es) will the project team need to repeat with each iteration?
Define Scope
Collect Requirements and Create WBS
Collect Requirements and Define Scope
Collect Requirements, Define Scope, and Create WBS
While the first phase of a construction project was a success, one of the two lead architects suddenly had to resign from
her position due to a conflict of interest within the company.
What should the project manager do immediately to manage the team composition?
Write a work performance report to generate awareness of the lead architect's departure
Update the project organizational chart to reflect the team change
Review the change management plan and submit a change request
Use float on the critical path to prevent schedule slippage due to this new risk
A company is experiencing exponential growth and will soon run out of space in their current production facility. A needs
assessment has been completed to evaluate alternatives. One of the options to support future growth is to build an
expansion on to their existing production facility.
What should the company do next?
Collect requirements and develop the project management plan
Understand the business goals and objectives to recommend proposals
Prepare the business case and benefits management plan
Perform the processes within the Initiating Process Group
You have been provided a list of concerns some stakeholders have with your project. You meet with them to address the
concerns in hopes of gaining their support and cooperation. You pay close attention by actively and effectively listening.
You focus on each person's input to ensure you are aware of and are taking all perspectives into consideration. You then
clearly articulate your point and your position and ask for their support.
Which tool or technique best describes the skills you are using?
Influencing
Team performance assessments
Conflict management
Emotional intelligence
A project manager is developing the communications management plan. She has determined which stakeholders need
what information and how often she will distribute the various reports.
What else should the project manager do as part of this process?
Determine the information needs of the stakeholders
Determine how the information will be transmitted
Measure the effectiveness of the communications
Submit a change request to update the communications management plan
A vendor has been contracted by a buyer to develop a new device. The vendor insisted that the contract thoroughly
capture the device specifications. The buyer does not have clear requirements upfront and, therefore, requested that the
vendor develop the device using agile. The vendor delivers as per the contract, but the buyer is not satisfied with the
outcome.
Which Agile Manifesto's value was most likely not appropriately applied?
Business people and developers must work together
Individuals and interactions over processes and tools
Pair programming over continuous integration
Customer collaboration over contract negotiations
You meet with your team to determine the life cycle for your project. After analyzing the best way to define and manage
requirements, develop deliverables, handle changes, control risk and cost, and engage key stakeholders, the decision is
made to select a hybrid life cycle.
With the project life cycle selected, how will the requirements be managed on your project?
Defined during the transition to the customer
Elaborated at periodic intervals during delivery
Defined up-front before development begins
Elaborated as often as needed during delivery
As part of the Develop Schedule process, the project manager creates the project schedule using a Gantt chart. Three
Scrum teams will develop the project deliverables. Due to dependencies, the teams will be required to coordinate their
work twice a week using extended standup meetings.
What should the project manager do next?
Submit a change request to switch the Gantt chart to burndown chart
Include Scrum of Scrums (SoS) meetings in the project schedule
Crash the schedule to eliminate the dependencies between the teams
Reflect the actual velocity of the teams in the project schedule
You and your team are currently developing the stakeholder engagement plan. A project team member has already
created the stakeholder engagement assessment matrix below.
Which answer choice represents the most important element to be included in the stakeholder engagement plan?
A plan to improve Marie Smith's engagement level
An engagement level improvement plan for Todd Young
A strategy to address the engagement level of John Snow
A strategy to improve the engagement level of Tonya Stewart
You have been assigned to lead a drug development project for a small pharmaceutical company. The drug development
aspect of the project is characterized by a high degree of uncertainty, complexity, and risk. The governmental approval
process, on the other hand, is highly structured and well defined.
What project management approach would you recommend for this project?
Agile for the drug development phase, and predictive for the governmental approval process
Predictive for the drug development phase, and agile for the governmental approval process
Kanban to maximize WIP for compliance activities related to the governmental approval process
Crystal clear for both the drug development phase and the governmental approval process
A project manager has just calculated the project performance measurements, and the project's current cost performance
index (CPI) is 0.9 while the schedule performance index (SPI) is 1.1.
Which of the following is correct regarding the project's performance status?
Over budget and ahead of schedule
Under budget and behind schedule
Over budget and behind schedule
Under budget and ahead of schedule
An agile coach is leading an iteration planning meeting, which is being dominated by a highly respected senior developer.
The agile coach is concerned that the senior developer might be exerting too much influence and overcommitting the
team.
What is the best course of action for the agile coach?
Address the situation during the next project retrospective
Suggest that the team holds a round of fist-of-five voting
Reduce the story points to avoid over-commitment
Do not interfere as the iteration plan is determined by the team
Four vendors have responded to a bid request on your project.
Which of the following vendors should you select based on the expected monetary value (EMV)?
Vendor 1 with an 80% probability of success and profit of $20,000
Vendor 2 with a 90% probability of success and profit of $19,000
Vendor 3 with a 75% probability of success and profit of $18,000
Vendor 4 with an 85% probability of success and profit of $20,000
A project has short iterative planning and executing cycles where the requirements are progressively elaborated. The key
stakeholders are continuously involved and provide frequent feedback allowing the team to respond to changes more
quickly.
What is the best way for the project manager to manage quality in this type of project environment?
By conducting periodic quality audits
By using the Validate Scope process
By scheduling regular retrospectives
By using the quality control matrix
You are leading a construction project that involves a vendor. A team member tells you that based on the rough
assessment of the vendor's current work in progress, she suspects that the vendor will be unable to complete their work
on time. You share your concerns with the vendor, but they claim that they are progressing as planned.
What is your best course of action to ensure a mutual understanding of the work in progress?
Conduct a walkthrough
Perform an earned value analysis (EVA)
Conduct an audit
Resort to alternative dispute resolution (ADR)
You are halfway through a project, which has experienced several setbacks due to unanticipated problems. Based on
recent feedback, you are concerned that critical support for the project among key stakeholders is eroding. You want to
bring the stakeholders together for a meeting to address any concerns and rebuild support for the project.
Which of the following meetings would be the most beneficial for the key stakeholders to attend?
Customer wrap-up meeting
Change control meeting
Celebration meeting
Iteration retrospective
An agile team member encounters a technical issue while developing one of the user stories she selected for the current
sprint. After multiple unsuccessful attempts to resolve the issue, the team member approaches the scrum master for
advice.
What is the best course of action for the scrum master?
Request that the rest of the team members swarm on the user story
Replace the team member with another more experienced one
Ask the product owner who wrote the user story to resolve the issue
Recommend that the team member try other alternative solutions
The first phase of a software development project that was conducted using a predictive project management approach is
over. The project enters its second phase which will require the project team to utilize an eXtreme Programming (XP)
method to develop the rest of the product.
How might the team ground rules need to be updated?
Acceptance of collective responsibility for the project's deliverables
Addition of agreements for working in a virtual environment
The ground rules will no longer be needed as the team will use XP
Accountability for the creation of highly detailed documentation
A project manager is leading a product development project, which will use an agile framework. The project team and
other stakeholders are co-located at the company's corporate office.
What is the best way for the project manager to communicate the project status and promote transparency?
Reserve a conference room and invite all relevant stakeholders to monthly project status meetings
Post burndown charts and other project status documents to the company's intranet site
Share the appropriate information whenever requested by stakeholders
Display burndown charts and other relevant project artifacts in a highly visible location
A change request has been approved and is currently being implemented by the project team.
According to the project life cycle shown on the chart below, which of the following is true about project costs and risks
associated with the process group described in this scenario?
Both the cost of changes and the project risk are zero.
The cost of changes is lowest while the project risk is highest.
The cost of changes is nearly equal to project risk.
The cost of changes is highest while project risk is lowest.
You are managing a project to build 100 site towers, and you have just completed building the 50th tower. To mark the
successful completion of this first significant milestone, you hold a celebration where you share the developments,
challenges, and lessons learned so far on the project.
In what process will you use this information and knowledge gained so far to improve the future performance of the
project?
Control Quality
Perform Continuous Improvement
Manage Quality
Direct and Manage Project Work
During project execution of a high priority project, a previously identified risk is realized. The project manager sends an
email to the risk owner and receives an automated response indicating that this individual will be out of the country on
vacation for the next two weeks. The risk owner did not disclose a backup contact to use during the interim.
What should the project manager do first?
Capture the problem in the issue resolution register
Update the communications management plan
Submit a change request
Record the information in the issue log
To ensure that lessons learned are captured and documented throughout the project life cycle, the project manager
creates the lessons learned register.
What project management process is being performed?
Direct and Manage Project Work
Monitor and Control Project Work
Manage Project Knowledge
Create Lessons Learned
You are a scrum master leading an agile project team that has been consistently meeting the goals set for each iteration.
The product owner is pleased with the team's progress, and the performance measurement baseline shows no
deviations. However, you feel that one team member is less productive than the others.
What is the most appropriate feedback approach for you to take in this situation?
Allow the project team members to address the issue if they deem necessary
Direct the underperforming team member to work extra hours to bridge the gap
Call out the team member's low productivity at the upcoming iteration retrospective
From the next iteration onward, assign the team member the easiest user stories
You are creating the schedule to deploy a new ERP software in your company. The company is currently undergoing an
agile transformation, so it was decided to develop the new ERP iteratively. The first release of the ERP should be rolled
out in four months, and you know that another project, a company-wide operating system upgrade, is scheduled in three
months.
With the upgrade project affecting your schedule, an impact on which of the following should you assess to determine the
number of iterations until rollout?
Release planning
Product roadmap
Iteration backlogs
Project charter
You are leading a project in a small startup company with decentralized purchasing. A supplier informs you that they have
excess inventory that can be purchased at a reduced price. You review the project's inventory needs and find that most of
the excess inventory offered by the supplier can be used for the project.
What is your best course of action?
Refer the supplier to the project sponsor for procurement
Negotiate and sign a procurement contract with the supplier
Refer the supplier to the procurement department
Refer the supplier to the project management office (PMO)