WorksheetsLesson 2 | Start the Project
Total questions: 22
Worksheet time: 16mins
Which two of the following are reasons that PMI® publishes a ææCode of Ethics? (Choose two)
Set expectations for the project manager and the team.
Create a commitment to honesty, integrity, and commitment.
Ensure compliance with rules and laws.
Provide specific guidance on conflict resolution.
Which two of the following are components of a project agreement? (Choose two)
Pricing and payment terms
Incentives and penalties
Team members
Complete product backlog
Which is a good practice for the use of collaboration technology?
Select tools with the best features.
Select tools that the team lead has experience using.
Define team goals and practices before selecting tools.
Use the tools that the previous project used.
Which two are examples of virtual team collaboration tools? (Choose two)
Shared task boards
Your laptop hard drive
Social media
Team chat boards
Which of the following is not a stakeholder in a financial project?
Someone opposed to the project
Project manager
Someone who is not interested in the project
Project sponsor
Which of the following is an artifact that outlines how the team will operate and work together?
Team charter
Resource management plan
Project charter
Team acquisition plan
Which statement best describes project stakeholders?
Anyone affected by the project, its outputs, and its operation
Anyone making money from the project
A customer paying for the project’s output
The organization delivering the project’s products
Which of the following would be least likely to be included in a stakeholder engagement plan?
List of identified project stakeholders
Documentation of the relationships between project stakeholders
Amount of money invested by the project stakeholders
Actions to be used interacting with project stakeholders
Your company has entered into a contract to develop a new and improved website for another company. The contract specifies the major deliverables, with details about what the website will contain, the completion date, and budget. The appendix contains the change control procedures that will be used. What project life cycle should be used to deliver this project?
Predictive
Agile
Hybrid
Scrum
Is the following statement true or false? In a predictive project, phase-to-phase relations can be sequential, where a phase can start prior to the end of another phase, or overlapping, where consecutive phases start when the previous phase is finished.
True
False
An organization is exploring a new project with many unknowns, and most of the work to be done is designing software to build the best solution in collaboration with the customer. Which project management approach is best suited for this project?
Agile
Plan-driven
Phased
Predictive
Which two statements describe self-organization? (Choose two)
Asking teams to assess and agree to work goals as a group
Allocating all resources before they get assigned to a different project
Using a pull-based approach to ensure effective use of team resources
Having the project manager stipulate roles and responsibilities and assign all the work to individual team members
The business determines that the project you are managing must be based on a plan-driven project management approach. This is partially due to the SMART objectives the steering committee has set for the project. In the acronym SMART, what does the T stand for?
Technical
Tentative
Timely
Testable
A meeting that is held at frequent intervals in an agile project is referred to as which of the following?
Lessons learning meeting
End-of-phase meeting
Retrospective meeting
Status meeting
Every timeboxed iteration in the project has a demo scheduled at the end during the iteration review session. What is the goal of this demo?
To reprioritize the iteration backlog
To revise the product roadmap
To solicit feedback from the product owner and other stakeholders
To establish the features to be included in the product backlog
Which two of the following should be included in a project charter? (Choose two)
Measurable objectives
Detailed deliverables list
Key stakeholders list
Change request form
What is the typical length of a sprint/iteration?
1 week
2 weeks
1 - 4 weeks
Up to 12 weeks
In which of the following artifacts will a list of stakeholders who will receive communications about the project appear?
Communications requirements analysis
Communications management plan
Stakeholder register
Communications requirements analysis and communications management plan
Which of the following is not a component of the communications management plan?
Initiator and receiver of project information
Stakeholder register
Collection and transfer of institutional knowledge
Frequency of each communication
Which two of the following should be included in a communications management plan? (Choose two)
How and when team meetings are run
Equipment assigned to each team members
Project charter
Preferred communication approaches with external stakeholders
What are two techniques that a project manager can use to appraise the skills of a potential team member? (Choose two)
Ability tests
Focus groups
Kanban boards
RACI matrix
You are working on a project that is part of a program. All the projects within this program are being managed in an agile way. What is a good technique to get the project teams aligned?
Hold one daily standup meeting for all the projects.
Assign one customer point of contact for all projects.
Develop one project management plan.
dConduct a Scrum of Scrums meeting.