WorksheetsCDM 2015 Client Duty Holder Quiz
Total questions: 10
Worksheet time: 5mins
Who is the client according to CDM 2015?
The principal designer
The project manager
The principal contractor
The person having construction work carried out for them
What is the pre-construction phase also referred to as?
The construction phase
The design phase
The planning phase
The building phase
What is the role of the principal designer in the pre-construction phase?
Managing health and safety in the construction phase
Liaising with the principal contractor
Managing health and safety in the pre-construction phase
Overseeing the completion and handover arrangements
What should be included in the client brief?
All of the above
The design direction
The main function and operating requirements of the finished building or structure
The reason for the project
When should the principal contractor be appointed?
After the construction phase begins
During the pre-construction phase
At the end of the project
Before the construction phase begins
What is the purpose of the F10 notification form?
To notify the HSE of project completion
To notify the HSE of any notifiable projects
To notify the HSE of any changes in project plans
To notify the Health and Safety Executive (HSE) of any accidents on site
Who is responsible for creating the construction phase plan?
The project manager
The client
The principal contractor
The principal designer
What is the client's duty regarding welfare facilities on site?
To maintain the welfare facilities
To provide the welfare facilities
To ensure that welfare facilities are being provided
To inspect the welfare facilities
What is the purpose of the health and safety file?
To keep track of project expenses
To provide information for future construction, demolition, cleaning or maintenance work
To store project design documents
To record project completion details
Who is responsible for maintaining the health and safety file after project completion?
The Health and Safety Executive (HSE)
The principal contractor
The client or owner of the building
The principal designer