1.

Who is the client according to CDM 2015?

a)

The principal designer

b)

The project manager

c)

The principal contractor

d)

The person having construction work carried out for them

2.

What is the pre-construction phase also referred to as?

a)

The construction phase

b)

The design phase

c)

The planning phase

d)

The building phase

3.

What is the role of the principal designer in the pre-construction phase?

a)

Managing health and safety in the construction phase

b)

Liaising with the principal contractor

c)

Managing health and safety in the pre-construction phase

d)

Overseeing the completion and handover arrangements

4.

What should be included in the client brief?

a)

All of the above

b)

The design direction

c)

The main function and operating requirements of the finished building or structure

d)

The reason for the project

5.

When should the principal contractor be appointed?

a)

After the construction phase begins

b)

During the pre-construction phase

c)

At the end of the project

d)

Before the construction phase begins

6.

What is the purpose of the F10 notification form?

a)

To notify the HSE of project completion

b)

To notify the HSE of any notifiable projects

c)

To notify the HSE of any changes in project plans

d)

To notify the Health and Safety Executive (HSE) of any accidents on site

7.

Who is responsible for creating the construction phase plan?

a)

The project manager

b)

The client

c)

The principal contractor

d)

The principal designer

8.

What is the client's duty regarding welfare facilities on site?

a)

To maintain the welfare facilities

b)

To provide the welfare facilities

c)

To ensure that welfare facilities are being provided

d)

To inspect the welfare facilities

9.

What is the purpose of the health and safety file?

a)

To keep track of project expenses

b)

To provide information for future construction, demolition, cleaning or maintenance work

c)

To store project design documents

d)

To record project completion details

10.

Who is responsible for maintaining the health and safety file after project completion?

a)

The Health and Safety Executive (HSE)

b)

The principal contractor

c)

The client or owner of the building

d)

The principal designer