1.

A 2 ̋ x 4 ̋ measuring 8 ́-0 ̋ or 96 ̋ is to be cut into 22 ̋ pieces for blocking. If 200 pieces of blocking are needed, how many 2 ̋ x 4 ̋ x 8 ́-0 ̋ lengths are needed?

a)

47A

b)

46B

c)

45C

d)

44D

2.

Siding can be installed at a rate of 175 square feet per carpenter per day. A crew of 4 carpenters is working on a house containing 5600 square feet of siding. The carpenters work 8 hour days. How many man-days will it take?

a)

10A

b)

9B

c)

8C

d)

7D

3.

Siding can be installed at a rate of 175 square feet per carpenter per day. A crew of 4 carpenters is working on a house containing 5600 square feet of siding. The carpenters work 8 hour days. How many man hours will it take the carpenters to finish siding the house?

a)

312A

b)

413B

c)

250C

d)

256D

4.

Rafters are to be installed on a structure that measures 128 ́-0 ̋ long. Required spacing is 16 ̋ on center. How many sets of rafters are required? Note: Add 1 rafter for a starter.

a)

97A

b)

96B

c)

100C

d)

101D

5.

The following material list was compiled for a framing project. Out of all of the pieces needed for the project, how many total 2x4 are needed?

a)

65A

b)

431B

c)

108C

d)

352D

6.

An apprentice program has the following number of apprentices enrolled in each section. What is the total number of Carpenters, Millwright and Pre-Apprentice apprentices enrolled in the program?

a)

1743A

b)

1024B

c)

1226C

d)

1300D

7.

A crew of carpenters frames a roof using various trusses and braces. The package includes 96 king post trusses, 75 scissor trusses, 31 2 x 4 x 16 ́ -0 ̋ braces, and 2 gable end trusses. Each truss requires 8 2 x 4 x 16'-0" to build. How many total 2 x 4's are needed, including bracing, are required for completion?

a)

1405A

b)

1632B

c)

1234C

d)

1350D

8.

A building was being built. The respective dimensions are 6 ́ -0 ̋, 20 ́ -0 ̋, 8 ́ -0 ̋, 37 ́ -0 ̋, 27 ́ -0 ̋ and 35 ́ -0 ̋. What is the sum of all of the dimensions?

a)

125' - 0"A

b)

138' - 0"B

c)

133' - 0"C

d)

145' - 0"D

9.

You need to drywall a room that is 20' x 24' with 8' high walls. How many 4x8 sheets of drywall will you need to drywall all 4 walls and ceiling?

a)

22A

b)

37B

c)

30C

d)

19D

10.

You are adding baseboard to a room that measures 20' x 24'. How many linear feet of baseboard are you going to need to complete the job?

a)

78A

b)

88B

c)

98C

d)

108D

11.

What are the dimensions of the front porch

a)

10'5" x 9'2"

b)

10'5" x 7'x1"

c)

72 S/F

d)

15'1" x 9'9"

12.

How many doors are there in this blueprint?

a)

10

b)

12

c)

11

d)

9

13.

What are the dimensions of bedroom 4 knowing it has 78 S/F?

a)

14'10" x 9'4"

b)

8'0" x 11'3"

c)

9'5" x 11'1"

d)

11'1" x 8'0"

14.

The walk-in closet has 8ft ceilings. Knowing this, how many 4'x8' sheets of drywall will it take to drywall all four walls, standing the sheet of drywall upright? Do not worry about scrap pieces.

a)

10 sheets

b)

9 sheets

c)

11 sheets

d)

12 sheets

15.

A room measures 12' x 15'. How many square feet of carpeting will you need to cover the entire floor?

a)

120 sq ft

b)

180 sq ft

c)

200 sq ft

d)

150 sq ft

16.

A crew of 3 carpenters is working on a house containing 4500 square feet of siding. The carpenters work 8 hour days and can install 150 square feet per carpenter per day. How many man-days will it take?

a)

12A

b)

10B

c)

15C

d)

9D

17.

You are installing a fence around a rectangular yard that measures 30' x 40'. How many linear feet of fencing will you need?

a)

120A

b)

140B

c)

160C

d)

100D

18.

Your company insures a snow removal company. The snow removal premiums for each of the past 3 years are $1075, $1790, and $4236.  What was the total premium for the past 3 years. 

a)

$7201

b)

$6873

c)

$6998

d)

$7101

19.

A point established by a surveyor on or close to the building site.  It is used for a reference point for determining the elevation during the construction of a building.

a)

Property Line

b)

Bench Mark

c)

Easement

d)

Plan View

20.

A procedure that involves surveying, measuring, and counting all materials indicated on a set of drawing.

a)

Title Sheet

b)

Quantity Takeoff

c)

Elevation View

d)

Construction Drawing

21.

Tells design professionals and other tradespeople how to build a specific building or structure.

a)

Construction Drawing

b)

Property Line

c)

Specification

d)

Easement

22.

A contractual document used with the construction drawings.  It contains detailed written instructions that supplement the set of drawings.

a)

Plan View

b)

Bench Mark

c)

Front Setback

d)

Specifications

23.

At the beginning of a set of drawings or at the beginning of a major section of drawings.

a)

Drawing Set

b)

Title Sheet

c)

Construction Drawing

d)

Quantity Takeoff

24.

Used in architectural plans and drawings to pictorially show different kinds of materials, fixtures, and structural members.

a)

Building Codes

b)

Symbols

c)

Title Block

d)

As-Built Drawing

25.

Specialized drawings that show how to fabricate and install components of a construction project.

a)

Section View Drawings

b)

As-Built Drawings

c)

Shop Drawings

d)

Plan View Drawings

26.

 Enlargements of special features of a building or of equipment installed in a building. They are drawn to a larger scale in order to make the details clearer.

a)

Symbols

b)

Schedules

c)

Details

d)

Plan View Drawings

27.

A two word phrase that means safety in the work place

a)

First Aid

b)

Safety Second

c)

Safety Meeting

d)

Safety First

28.

Give information about the location and dimensions of footings, grade beams, foundation walls, stem walls, piers, equipment footings, and windows and doors

a)

Civil Plans

b)

Electrical Plans

c)

Plumbing Plans

d)

Foundation Plans

29.

A drawing of the view of the roof from above the building

a)

Floor Plans

b)

Roof Plans

c)

Plumbing Plans

d)

Mechanical Plans

30.

Drawings that are formally incorporated into the drawing set to record changes marked up by the various trades to show any differences between what was originally shown on a pan by the architect or engineer and what was actually built.

a)

As-Built Drawings

b)

Elevation Drawings

c)

Section View Drawings

d)

Symbols