NEW
Font size
WorksheetsALE_Review Standard Professional Practice 1
Total questions: 50
Worksheet time: 25mins
What is an additional information on contract documents issued to bidders before date of bidding?
Bid Forms
Invitation to Bid
Bid Bulletin
General Condition
The _________ printed documents stipulating the procedural and administrative aspects of the contract.
Memorandum of Agreement
General Conditions
Material Specifications
Bill of Materials
Under BP 344 , which of the following is NOT generally considered as basic physical planning requirement.
Orientation
Accessibility
Durability
Safety
How are projects classified in determining
the basis for the Architects "Basic Fees"
Structural Components
Total Flloor Area
Degree of project complexity
Material Specifications
A per diem not less than ______ plus traveling and living expenses shall be chargeable to the owner on any occasion where the Architect or his duly authorized representative shall be required to perform services at a local beyond the radius of _____ kilometers from his established office.
500php/50km.
500php/100km
1000php/50km
1000php/100km
Which of the following does NOT constitute the post-construction services of the architect?
building/equipment maintenance
post‐construction evaluation
real property evaluation
building/ground administration
SPP Document replaced the _________.
IAPOA Documents
1975 UAP Documents
1979 UAP Documents
1979 PIA Documents
For Socialized Housing Projects, minor inter‐connecting roads should have a minimum ROW of ________ mts.
10.5 mts
12.5 mts
6.5 mts
8.5 mts
This shall be issued by the Owner to the Contractor following the execution of the Contract Agreement.
Schedule of Completion
Contract Sum Breakdown
Notice to Proceed
Contract Time
The minimum basic fee for hospitals with a project cost below 50 million pesos.
8%
10%
12%
15%
It was created through Executive Order no. 90. It is the highest policy‐making and coordinating office on shelter programs.
NHA – National Housing Authority
NHMFC – National Home Mortgage Finance Corporation
HUDCC – Housing and Urban Development Coordinating
Council
HGC – Home Guarantee Corporation
Per NBC, what is the minimum clearance in the ground floor of a multi‐storey structure?
2100 mm.
2400 mm.
2700 mm.
3000 mm.
Who accredits the National Organization of Architects?
BOA
PRC
IAPOA
UAP
What is one of the most important benefits of hiring a contractor?
Networking
Cost Reduction
Quality Assurance
Increased Production Speed
Per BP 344, what is the minimum width of the doors and elevator doors?
700 mm.
800 mm.
900 mm.
1100 mm.
The fee of the architect for design‐build services on a guaranteed maximum cost aside from his fee for regular design services
5%
10%
15%
20%
If an architect wants to register as a sole proprietorship firm, where will he register?
IAPOA
UAP
SEC
DTI
After all of the Contract Documents have been given to the owner, how much is the liability from the remaining professional fee?
5%
10%
15%
20%
Per NBC, what is the minimum ratio of openings to the wall area:
10%
12%
15%
20%
Who assumes liability for work‐related injuries when you hire your own subcontractors?
Sub-Contractor
You
The State
Special Case
What can you do to protect yourself from getting cheated by paying for work that doesn't get done?
get notarized contracts
file a case
ask all goods and service providers on your job for a lien
release
Nothing
Per NBC, a building permit is revoked after how many days of work has stopped?
60 days
90 days
100 days
120 days
The main purpose of a contractor is to do which of the following?
Basically a Project Manager
Responsible for the hands- on aspect of the project
as Design specialist
as Consultant
How many percent of the contract amount is the Performance Bond?
5%
10%
15%
20%
Lien laws are designed to protect whom?
Client
Architect
Contractor
Consultant
It is the most common method of compensation which is also fair for both client and architect.
Lump Sum
Percentage Base on Project
Professional Fee plus Expenses
MDPE
Under the NBC, hospitals shall have one parking slot for every how many beds?
15
20
25
30
Minimum floor area for a duplex house in economic housing under BP 220
22 sqm.
24 sqm.
26 sqm.
28 sqm.
Minimum thickness of firewall under Bp 220
100 mm.
150 mm.
200 mm.
250 mm.
What is the main component to be considered by the Architect in the formulation of a master development plan is ?....
Elective Component
Mediation Component
Arbitration Component
Legal & Administration Component
Under Design Services, the minimum basic fee of an Architect for a Laboratories with a project construction cost of 50 million and less is ?
6%
7%
8%
10%
The fee of Architect for Design~Build Services by administration aside from his fee for the Regular Design Services is?....
6%
7%
8%
10%
What is the minimum floor area of the toilet for the handicapped?
1700x2000 mm.
1700x1800 mm.
1200x1800 mm.
1200x2000 mm.
What is the minimum lot area for single detached socialized housing according to BP 220?
54 sqm.
64 sqm.
74 sqm.
84 sqm.
It refers to the portion of a roadway or public way that should be kept open and unobstructed at all times for the expedient conduct of fire fighting operations.
Fire Escape
Fire Lane
Fire Exit
Fire Egress
The minimum basic fee of the Architect in designing parking structure with a project construction cost of 50 million and less is ?....
6%
7%
8%
10%
What is the approved abbreviation for the title of
Architect as mandated by Arcasia?
AR
ARCH'T
ARCH.
ARCT
The duration of time allowed by the contract for the completion of the project in any stipulated portion thereof:
Time Table
Project Duration
Time Limit
Contract Time
What is referred to as an outline specifications enumerating the type or trade names of materials to be used?
Minimum basic fee for Group 5 projects (monumental)
8%
10%
12%
15%
To keep information flowing among members of the project team and management:
What pre‐design service involves investigating, identifying and documenting the needs of the client for use in the design of the project?
Where would you apply for Bldg permit?
DTI
SEC
OBO
PRC
Which is a reason or ground for non‐issuance, suspension or revocation of a building permit?
Failures to commmence construction within six months
Non-payment of corresponding Fees
Errors founds in plans & specifications
Incorrect Assesment
Architects assist in the determination of requirements of lending agencies, income‐expense relationship and relative demand for different building types in actual financing negotiations.
Economic Feasibility studies
Project Financing
Space Management Studies
Site Selection & Analysis
Which is an unethical action with respect to the Architect's responsibility to his client?
Does not offer preliminary sketches & design without agreement
Advise client/owner to forgo unviable project
Guarantee any estimates or costs of the work
Undertakes construction for a fixed contract sum under design build service
Project Financing is one of the Architect' s services that falls under:
Design Services
Pre‐design Services
Specialized Allied Services
Design‐Build Services
BP 344: In the case of buildings, what does the word INGRESS refer to?
Fire Exit Door
Entrance Door
Exit Door
Emergency Door
The ___ is the current law that regulates the practice of Architecture
RA 8266
RA 9266
RA 2266
RA 3266
Under PD 957, minimum dwelling unit for household units in a condominium is how many square meters:
30 sqm.
40 sqm.
50 sqm.
60 sqm.