SE2 (LEC) Week 1-2 Project Management Essentials

Total questions: 21

Worksheet time: 11mins

Name
Class
Date
1.

Imagine the company you work with is beginning an initiative to audit and update internal training resources. Once this initiative is completed the company will present a new training library to employees as a resource for tasks they should complete.

Which of the following terms best describes this initiative?

a)

A program

b)

An inventory of assets

c)

A project

d)

A portfolio

2.

You are the project manager for implementing a new IT ticketing system at your company.

Which of the following tasks best demonstrates the "organized execution" characteristic of project management in this scenario?

a)

Identifying potential risks associated with the implementation, such as data migration issues.

b)

Defining the desired features and functionalities of the ticketing system.

c)

Creating a detailed project plan with assigned tasks, milestones, and deadlines.

d)

Securing necessary

budget approval and equipment for the project team.

3.

Which of the following is most likely to be part of a program, but not a project?

a)

Implementing a company-wide training program

b)

Launching a marketing campaign for a specific product

c)

Creating a website for a specific event

d)

Developing a new software feature

4.

Which of the following definitions best describes project management?

a)

Project management is the ongoing management of a team of skilled workers that deliver a product to a client.

b)

Project management is a detailed scheduling of multiple tasks within a project.

c)

Project management uses specific knowledge, skills, tools, and techniques to deliver valuable projects to clients.

d)

Project management coordinates with stakeholders in a project to obtain feedback on deliverables.

5.

Which two of the following are benefits of project management?

a)

Project management increases customer satisfaction by planning and meeting expectations.

b)

Project management predicts profits, margins and issues payments to people working on projects.

c)

Project management improves communication within teams and overall satisfaction for employees.

d)

Project management improves productivity, efficiency, and quality of work.

6.

Which of the following is NOT a key characteristic of project management?

a)

Proactive risk identification and mitigation

b)

Delivery of value to people

c)

Organized execution with defined constraints

d)

Ongoing management of a team or department

7.

Which of the following statements best identifies the role of project management in projects?

a)

Scoping out and creating the initial statement of work for a project.

b)

Processing the budget and payments from the client.

c)

Ensuring quality of deliverables.

d)

Balancing the scope of work, resources, timelines and budget

8.

Imagine you're working at a technology company developing a new e-commerce platform. Choose the most appropriate category (project, program, or portfolio) for each scenario:

You're responsible for ensuring all IT systems, including the e-commerce platform, CRM, and internal communication tools, align with the company's overall digital strategy.

a)

Portfolio

b)

Program

c)

Project

d)

none of the above

9.

Which of the following is NOT a characteristic of a project?

a)

Is ongoing and continuously evolving

b)

Has a defined start and end date

c)

Aims for a unique product, service, or result

d)

Involves managing resources and tasks

10.

Imagine you're working at a technology company developing a new e-commerce platform. Choose the most appropriate category (project, program, or portfolio) for each scenario:

You manage a team developing several new e-commerce features, such as personalized product recommendations and a subscription box service.

a)

Program

b)

Project

c)

Project

d)

none of the above

11.

Imagine you're working at a technology company developing a new e-commerce platform. Choose the most appropriate category (project, program, or portfolio) for each scenario:


You oversee a team working on multiple projects related to customer experience improvements, including the e-commerce platform's user interface and loyalty program.

a)

Program

b)

Project

c)

Portfolio

d)

none of the above

12.

A software development project is nearing completion, but the team has encountered unexpected technical challenges that require additional resources beyond the budgeted amount. These challenges also push the projected deadline past the initial due date. To prioritize solutions, the project manager should first consider:

a)

Focusing on accelerating development tasks through overtime or outsourcing to meet the original deadline, even if it exceeds the available budget.

b)

Negotiating with stakeholders for additional funding to cover the increased resource needs while holding the deadline firm.

c)

Reducing the project scope by removing some planned features, allowing for available resources to be directed towards resolving the technical challenges.

d)

Accepting the delay and communicating it to stakeholders, prioritizing quality and resource availability within the existing budget, even if it means adjustments to the initial scope

13.

Who is the responsible person?

Building a roadmap for all research and development initiatives within the organization, allocating funding across different projects based on potential impact and aligning them with long-term strategic goals.

a)

Portfolio Manager

b)

Program Manager

c)

Project Manager

d)

None of the above

14.

Who is the responsible person?


Overseeing the progress of all software development projects within a company, identifying resource bottlenecks, and implementing improvements to streamline project delivery.

a)

Portfolio Manager

b)

Program Manager

c)

Project Manager

d)

None of the above

15.

Who is the responsible person?

Monitoring the performance of several marketing programs across different product lines, analyzing their contribution to overall company revenue, and recommending adjustments to optimize portfolio ROI.

a)

None of the above

b)

Project Manager

c)

Program Manager

d)

Portfolio Manager

16.

Who is the responsible person?

Balancing budget constraints and project scope to ensure a new advertising campaign stays within financial limits while achieving its target audience reach.

a)

Portfolio Manager

b)

Program Manager

c)

Project Manager

d)

None of the above

17.

Who is the responsible person?

Managing the day-to-day tasks of a website redesign project, coordinating with developers, designers, and content creators, and ensuring timely completion according to specifications.

a)

Program Manager

b)

None of the above

c)

Project Manager

d)

Portfolio Manager

18.

Match the correct distinction:

New Product Launch: A tech company starts a project to develop and launch a groundbreaking smartphone. This involves hardware and software development, marketing campaigns, and creating a robust supply chain

a)

Portfolio

b)

None of the above

c)

Program

d)

Project

19.

Match the correct distinction:

Green Energy Initiative: A company launches a comprehensive initiative to reduce its carbon footprint across all operations. This includes various projects like installing solar panels in facilities, developing biofuel alternatives for transportation, and implementing energy-efficiency measures in buildings.

a)

Portfolio

b)

Project

c)

None of the above

d)

Program

20.

Match the correct distinction:

Research & Development: A pharmaceutical company has an ongoing portfolio of research projects investigating potential treatments for various diseases. Each project explores a specific avenue but contributes to the company's long-term goal of advancing healthcare.

a)

Portfolio

b)

Program

c)

Project

d)

None of the above

21.

Match the correct distinction:
Digital Transformation: A bank undertakes a multi-year program to modernize its technology

infrastructure, improve customer experience, and increase operational efficiency. This program includes various smaller projects like adopting cloud computing, developing mobile banking apps, and revamping online banking interfaces.

a)

Project

b)

Portfolio

c)

Program

d)

None of the above