LDSP ORIENTATION QUIZ

Total questions: 15

Worksheet time: 3mins

Name
Class
Date
1.

ANO ANG TAWAG SA FORM NA ISINA-SUBMIT PARA SA PAGREQUEST NG KONTRATA SA LDSP?

a)

A. RMTP

b)

B. RNTP

c)

C. RTNP

d)

D. RFCA

2.

CATEGORY: BILLING

UPANG MAI-BILL ANG MGA NAGING ACCOMPLISHMENTS NI CONTRACTOR, MARAPAT
LAMANG NA MAI-SUBMIT SA TAKDANG ARAW AT ORAS SA ATING PSD ENGINEER
ANG MGA SUPPORTING DOCUMENTS KAUGANAY NITO.
TUWING KAILAN ANG CUTOFF NG BILLING SUBMISSION NI SITE?

a)

A. THURSDAY,
ON OR BEFORE 5 PM

b)

B. FRIDAY,
ON OR BEFORE 5 PM

c)

C. THURSDAY,
ON OR BEFORE 12 NN

d)

D. FRIDAY,
ON OR BEFORE 12 NN

3.

ILAN ANG RCP OFFSET FROM PROPERTY LINE KUNG ANG WIDTH NG RIGHT OF WAY AY 8 METERS?

a)

A. 2.00 M

b)

B. 1.00 M

c)

C. 1.25 M

d)

D. 0.9 M

4.

CATEGORY: EARTHWORKS

SA MGA AREA NA TATAMBAKAN, KAILANGAN NA ICOMPACT ANG BAWAT LAYER NG
PANAMBAK BAGO PA MAN MAGPATULOY SA SUSUNOD NA LAYER. ANG COMPACTION AY
ISINASAGAWA KADA ILANG CENTIMETER NA KAPAL NG LOOSE FILL?

a)

A. 30 cm

b)

B. 25 cm

c)

C. 20 cm

d)

D. 75 cm

5.

CATEGORY: DRAINAGE WORKS

ALIN SA MGA SUMUSUNOD ANG TAMANG OFFSET DISTANCE NG ATING MANHOLE
MULA SA KATABING PROPERTY?

a)

A. 1.0 m

b)

B. 0.75 m

c)

C. 0.90 m

d)

D. 1.25 m

6.

CATEGORY: DRAINAGE WORKS

SA PAGLALATAG NG RCP, DAPAT NA SIGURADUHIN NA ANG TONGUE NG RCP AY HINDI

NAKAHARAP SA DIREKSYON NG FLOW

a)

TAMA

b)

MALI

c)

PWEDE

7.

CATEGORY: DRAINAGE WORKS

MATAPOS ILATAG ANG RCP, KAILANGANG MAG-BACKFILL SA MAGKABILANG
GILID NG RCP. HANGGANG ILANG PERCENT NG DIAMETER NG RCP
ANG DAPAT NAKA EXPOSE?

a)

A. 65%

b)

B. 80%

c)

C. 70%

d)

D. 75%

8.

ANONG SIZE NG RCP MAGSISIMULA ANG PAGLALAGAY NG COLLARING

SA LOOB AT LABAS NG PIPE?

a)

375 mm ABOVE

b)

450 mm ABOVE

c)

750 mm ABOVE

d)

900 mm ABOVE

9.

CATEGORY: WATERLINE WORKS

PARA SA MGA TUBONG DADAAN SA LOOB NG MANHOLE, ANG PAGLALAGAY

NG COVERING O CASING AY DAPAT NA ISINASAGAWA. ANO ANG RECOMMENDED

SIZE NG CASING NA ITO?

a)

0.50 PIPE SIZE HIGHER

b)

1 PIPE SIZE HIGHER

c)

1.50 PIPE SIZE HIGHER

d)

2 PIPE SIZE HIGHER

10.

CATEGORY: ROADWORKS

ILANG ARAW ANG DAPAT ANTAYIN MATAPOS ANG BUHOS (ROAD CONCRETING) BAGO

TANGGALIN ANG PORMA?

a)

A. 1 TO 2 DAYS

b)

B. 2 TO 3 DAYS

c)

C. 3 TO 4 DAYS

d)

D. 4 TO 5 DAYS

11.

CATEGORY: ROADWORKS

ALIN SA MGA SUMUSUNOD ANG DESIRED DEPTH AND WIDTH SA PAGSASAGAWA

NG CONCRETE CUTTING SA ATING MGA KAKALSADAHAN?

a)

A. 1" X 1/8"-5/16"

b)

B. 1" X 1/8"-3/16"

c)

C. 2" X 1/8"-5/16"

d)

D. 2" X 1/8"-3/16"

12.

CATEGORY: ROADWORKS

ILANG BESES AT HANGGANG ILANG ARAW DAPAT DILIGAN ANG KALASADANG BAGONG BUHOS?

a)

A. AT LEAST ONCE A DAY FOR 7 DAYS

b)

B. AT LEAST ONCE A DAY FOR 5 DAYS

c)

C. AT LEAST THRICE A DAY FOR 7 DAYS

d)

D. AT LEAST THRICE A DAY FOR 5 DAYS

13.

CATEGORY: DAILY ACCOMPLISHMENT LOG

SAANG SHEET SA ATING DAL INILALAGAY ANG EUR?

a)

A. SHEET 4

b)

B. SHEET 7

c)

C. SHEET 10

d)

D. SHEET 13

14.

CATEGORY: PERIMETER FENCE

ANONG DOKUMENTO ANG KAILANGAN NA MAIHANDA BAGO MAGSAGAWA NG

FIRST CONCRETING SA PERIMETER FENCE?

a)

SURVEY TURNOVER FORM NA MAY REMARKS NA "RESURVEY FOR 1ST CONCRETE POURING"

b)

MAPOUT

c)

RFI

d)

BOM

15.

ITO AY KAILANGANG ISAGAWA KUNG ANG PERIMETER FENCE ACCOMPLISHMENT

AY UMABOT NA SA FINISH GRADE ELEVATION.

a)

A. CONCRETING

b)

B. CHB LAYING

c)

C. BACKFILLING

d)

D. FORMWORKS