What is the focus of project initiation?
Conducting project planning
Organizing a team
Developing a communication plan
Identifying project risks
What is the major outcome of the project initiation and planning phase?
System Definition Section
Feasibility Assessment
Baseline Project Plan
Project Scope Statement
What is the process of identifying the financial benefits and costs associated with a development project?
Schedule feasibility
Economic feasibility
Operational feasibility
Technical feasibility
Which of the following is an example of a tangible benefit from the creation of an information system?
Availability of new information
Improved organizational planning
More timely information
Increased accuracy in clerical operations
What is the concept that money available today is worth more than the same amount tomorrow?
Net Present Value
Time Value of Money
Break-Even Analysis
Return on Investment
What is the ratio of the net cash receipts of the project divided by the cash outlays of the project?
Net Present Value
Return on Investment
Break-Even Analysis
Time Value of Money
What is the process of assessing the development organization's ability to construct a proposed system?
Legal and contractual feasibility
Schedule feasibility
Technical feasibility
Operational feasibility
What is the primary concern of assessing technical feasibility?
Failure to integrate the new system with existing hardware
Failure to achieve adequate system performance levels
Inaccurate project cost estimates
Failure to attain expected benefits from the project
What is the process of assessing the degree to which a proposed system solves business problems or takes advantage of business opportunities?
Legal and contractual feasibility
Schedule feasibility
Technical feasibility
Operational feasibility
What is the purpose of a walk-through in the systems development process?
To conduct project planning
To assess project feasibility
To peer group review any product created
To review the baseline project plan
What is the recommended course of action in the Introduction section of the baseline project plan?
Relate to project costs and benefits
Outline alternative solutions
Include managerial concerns
Define project scope
What is the formula for the present value of money?
PVn = Y / (1 + i)^n
PVn = Y * (1 - i)^n
PVn = Y * (1 + i)^n
PVn = Y / (1 - i)^n
What is the cost of owning and operating a system, including the total cost of acquisition and ongoing use and maintenance?
One-time costs
Total cost of ownership
Recurring costs
Tangible costs
What is the process of identifying at what point benefits equal costs?
Break-Even Analysis
Time Value of Money
Return on Investment
Net Present Value
What is the process of evaluating how key stakeholders within the organization view the proposed system?
Political feasibility
Technical feasibility
Operational feasibility