MCQ- SLIP TEST

Total questions: 10

Worksheet time: 5mins

Name
Class
Date
1.

No machine can process more than --------------- operation at a time.

a)

One

b)

Two

c)

Three

d)

Four

2.

The time required to transfer the jobs between machines is -----------------.

a)

High

b)

Low

c)

Moderate

d)

Negligible

3.

In a sequencing problem, --------------- rule is mentioned

a)

Johnson

b)

Time

c)

No passing rule

d)

Job changing

4.

In a sequencing problem the total elapsed time should be-----------------.

a)

Maximum

b)

Negligible

c)

Minimum

d)

Not be defined

5.

In sequencing problem, the order of completion of jobs is called

a)

completion sequence

b)

job sequence

c)

processing order

d)

job order

6.

Forward pass calculations are done to find occurrence times of events.

a)

exact

b)

earliest

c)

latest

d)

approximate

7.

The second longest path in the network diagram is called path.

a)

alternate

b)

feasible

c)

sub-critical

d)

critical

8.

The shortest possible completion time of an activity in PERT is called time.

a)

pessimistic

b)

optimistic

c)

most likely

d)

expected

9.

Floats for critical activities will be always.

a)

one

b)

zero

c)

highest

d)

same as duration of the activity

10.

Which algorithm is used in sequencing problem to optimize the total elapsed time?.

a)

Job

b)

Machine

c)

Optimization

d)

Johnson