1. The ___ is a pre-design stage of project development wherein the general concepts, other illustrations and typical drawings are presented. Hence, this will be the basis for Detailed Architectural and Engineering Design (DAED) phase where the design is refined, and plans, specifications, and estimates are established.
A. Conceptual Design
B. Innovative Design
C. Abstract Design
D. Theoretical Design
2. Defects Liability Period (DLP) from project completion to final acceptance
1 yr
2 yrs
3 years
5 years
3. The contractor shall undertake the repair works, at his own expense, of any damage to the infrastructure on account of the use of materials of inferior quality, within_ days from the time the Head of the Procuring Entity has issued an order to undertake repair. Failure or refusal to comply with this mandate, the procuring entity shall undertake such repair works and shall be entitled to full reimbursement of expenses incurred therein upon demand.
30
90
60
120
4. The defects liability period shall be covered by the ____ of the contractor which shall guarantee that the contractor performs his responsibilities. If the contractor fails to comply with its obligations, the procuring entity shall forfeit its __ ... and perpetually disqualify it from participating in any public bidding.
Bid Bonds
B. Retention Money
C. Warranty Security
D. Performance Security
For the procurement of goods, to assure that manufacturing defects shall be corrected by the supplier, a warranty security shall be required from the contract awardee for a minimum period of __ months and in the case of Expendable Supplies, or a minimum period of one (1) year.
3
6
7
9
6. The obligation for the warranty shall be covered by either retention money in an amount equivalent to at least of every progress payment, or a special bank guarantee equivalent to at least of the total contract price.
5%
15%
10%
20%
The Module provides a
comprehensive construction
materials prices database that
supports the cost estimation process
from preparation, review/evaluation,
and down to approval of the Detailed
Unit Price Analysis (DUP A), Program
of Works (POW), and Approved
Budget for the Contract (ABC) which
shall commence on the 4th quarter of
calendar year 2023
CMPD
PMPD
MMPD
MCPD
To improve the quality and value of public infrastructures, all DPWH projects that require value engineering studies should involve the participation of DPWH ACCREDITED ___ to ensure that the studies are consistent with internationally accepted value methodology processes and standards
VMA
BMV
VCM
VAM
Monitoring and safekeeping of the Road Signages, Road Lighting, Kilometer Posts, and RROW Boundary Markers affected by the on-going road widening projects is under the responsibility and liability of the _____.
DPWH
LGU
Contractor
IMplementing Office
10. The project billboard shall contain the statement "THIS IS WHERE YOUR TAXES GO". What is the font size of this statement?
50 mm
75 mm
60 mm
10 mm
11. Which of the following word/s is/are not found in the standard project billboard?
A. Project Name
Name of the Contractor
C. Date Started
Contract Completion Date
12. To improve planning and construction of various Rock Fall Netting Projects, all DED plans of 2023 projects and onwards involving Item 522 - Active and Passive Protection Systems for Unstable Slope with total cost of PHP __ and above shall be submitted to Bureau of Design for review and evaluation prior to the approval of the Head of Implementing Office concerned.
25M
50M
75M
100M
13. Outsourced Resource Speakers of DPWH from private sectors shall have Bachelor's/Master's/Doctorate degree with a minimum of_ years' work experience as consultant in a private or public organization, company, or institution, supported by a certification from the organization.
3
5
8
10
Payment for services rendered by Outsourced Resource Speakers of DPWH from the public and private sector shall be computed using the formula:
Honorarium = (X) (MSR) (T)
Where: X is Constant
MSR = monthly salary rate
T= number of actual lecture / training hours + preparation hours
What is the value of X?
0.025
0.023
0.024
0.022
15. A _ withholding tax shall be deducted from the Outsourced Resource Speakers of DPWH honorarium in conformity with the BIR Memorandum Circular No. 5 - 2006.
5%
10%
12%
3%
16. Based on DO18S2022, Revised schedule of Fees and Charges for Laboratory Testing of Construction Materials, what is the new testing rate for Compressive Strength of Concrete Cubes 6"x6", Concrete Cylinder 6"x12" and Drilled Core 4" and 6" diameter in pesos?
150
175
180
210
Based on DO18S2022, Revised schedule of Fees and Charges for Laboratory Testing of Construction Materials, what is the new testing rate for Compressive Strength of Concrete Cylinder 8"x16" and flexural strength of concrete beams 6"x6" in cross section in pesos?
150
175
180
210
18. In DPWH, the origin of any document prepared and acted upon in the Department shall be properly identified using the _ which eliminates misplacement and/or loss of documents and facilitates location and retrieval of documents.
A. Office Code Alphabetizing
B. Office Code Notation
C. Office Code Sequencing
D. Office Code Numbering
19. Full implementation of Accredited Contractor's Project Engineer, Department Order No. 94, series of 2020 shall take effect on where only accredited project engineers of the contractors and consultants may be assigned to supervise DPWH projects.
A. January 2024
A. January 2022
A. January 2023
A. January 2020
DPWH shall be _____ for the acquisition of Right-of-Way {ROW) in the implementation of projects Local Infrastructure Projects
{LIP), those under
Sustainable Infrastructure Projects Alleviating Gaps {SIPAG), and projects undertaken by the Department through their convergence programs with different agencies.
Not Responsible
Responsible
Maybe
NOTA
112 Right-of-Way {ROW) acquisition for Local Infrastructure Projects of DPWH shall be the responsibility of ______
A. DPWH
B. LGU
C. Contractor
D. LGU and DPWH
11fo On the Standard DPWH Construction Project Logbook - Weather Chart, what is the color signifying a Fair weather?
RED
GREEN
YELLOW
BLUE
23. On the Standard DPWH Construction Project Logbook - Weather Chart, what is the color signifying a cloudy weather?
RED
GREEN
YELLOW
BLUE
24. Based on DO 238 Series of 2022, Mandatory Tree Planting for DPWH Flood Control Projects, all Implementing Offices are required to plant seedlings/trees for contracts with at least P5 Million contract amount and additional of ____ seedlings/trees for every additional P5 Million contract amount, or fraction thereafter which shall be part of the PROGRAM OF WORK (POW) of every flood control projects.
500
1500
1000
750
Based on DO 261 Series of 2022, Subcontracting of DPWH Locally Funded Infrastructure projects, the general contractor may sub-contract portions of the works as may be approved by Procuring Entity, which shall not exceed of the contracted works, however, the general contractor shall be responsible for the acts, defaults, and negligence of any subcontractor - its agents or workmen. This requirement does not apply to labor "pakyaw" contracts.
50%
25%
20%
40%
26. All sheets in the set of Conceptual Design, DED, "As-Staked", Revised and "As-Built" Plans for Highway, Bridge, Water Engineering, and other related projects shall be uniform and of one standard_ size mylar paper.
A1
A2
A3
A4
27. The scale to be used for various parts of the DPWH design plans shall be 1:700 (Plan), 1:70 (Profile) and ___ (horizontal and vertical cross sections of roads).
1:50
1:500
1:100
1:1000
Who is responsible in preparation of Work Suspension Order, Work Resumption Order, and the Contract Time Extension?
A. DPWH PE
B. Contractor's PE
C. DPWH RE
D. DPWH RD/DE
29. It shall be issued instead of a WSO if suspension/unworkable days is due to unfavorable weather condition (Rainy), weather disturbances or its effect.
MSSR
MPSR
MTSR
MTPR
30. For roads and other regular projects of the Regional Offices (ROs), the Regional Directors are authorized to procure, implement, and approve Plans, POW, and ABC of DPWH Infrastructure Projects up to PHP ____ million in cost.
300M
400M
250M
500M
For roads and other regular projects of the District Engineering Offices (DEOs), the District Engineers are authorized to procure, implement, and approve Plans, POW, and ABC of DPWH Infrastructure Projects up to PHP _ million in cost.
75M
150M
100M
200M
A buffer zone is a _____ meter easement measured from the toe of existing riverbanks and/or river structures, such as dikes, revetment, nose of spur dikes and other river training structures, towards the river main channel.
15M
25M
20M
10M
33. It is issued by the DPWH to qualified persons who will conduct dredging with commercial utilization.
A. Dredging Clearance
B. Dredging Permit
C. Notice to Dredge
Permit to Dredge
34. It issued by DPWH to LGUs and other government agencies which will conduct dredging without commercial utilization of dredged materials.
A. Dredging Clearance
B. Dredging Permit
C. Notice to Dredge
Permit to Dredge
35. Dredging works within _ from bridges is prohibited unless prior clearance from the Government agencies concerned is obtained and justification with corresponding analysis that the proposed dredging will not affect the overall stability of the subject bridge is submitted.
1 km
2 km
2.5 km
3.0 km
36. During the implementation period, request for contract time extension (CTE) shall be made within thirty (30) calendar days for locally funded projects, or within ___ for foreign funded projects.
25 CD
30 CD
28 CD
35 CD
37. For critical infrastructure projects, the Regional Directors are authorized to procure, implement, and approve Plans, POW, and ABC of Bridge Projects of more than _ Linear meter in length but not to exceed PHP 400 million in cost.
100 M
50 M
125 M
75 M
38. For critical infrastructure projects, the Regional Directors are authorized to procure, implement, and approve Plans, POW, and ABC of Building Projects of more than_ story but not to exceed PHP 400 million in cost.
3
4
5
6
39. No extraction, removal and/or disposition of materials shall be allowed in offshore areas within ____ distance from the coast to ____ from the mean low tide.
A. 5oom&20om
B. 6oom &3oom
C. 1,ooom & 500m
500m & 250m
40. If the Contractor fails to SHOW CAUSE after the lapse of the_ days period, either by inaction or by default, DPWH shall immediately issue an order terminating the contract.
7 CD
21 CD
14 CD
30 CD
41. What is the frequency of asphalt over laying for road maintenance?
A. Every 3 years
B. Every 5 years
C. Every 4 years
D. Every 6 years
42. What is the mot commonly used pile driver in the Philippines?
A. Drop Hammer
B. Diesel Hammer
C. Single Acting Hammer
Double Acting Hammer
Camber on gravel roads is provided to: ______
A. Establish a smooth riding surface.
B. Prevent Water from stagnating on the carriageway.
C. Provide boundary line for the two lanes.
Plant grass for sodding
44. It is a series of enormous waves created by an underwater disturbance such as an earthquake, landslide, volcanic eruption, or meteorite.
A. Tidal
B. Tsunami
C. Spilling Waves
D. Ocean Waves
It is an average surface level of one or more among Earth's coastal bodies of water from which heights such as elevation may be measured and a type of global vertical datum -a standardized geodetic datum
A. High Sea Level
B. Low Sea Level
C. Above Sea Level
Mean Sea Level
46. How many Girders is designated to a 2 - lane road carriageway width of 7.3 meters?
3
4
5
6
47. What do you call the method of determining stream discharge by measuring the cross - sectional area of the stream and its velocity with a current meter?
A. Velocity - Area Method
Float - Velocity Method
C. Direct
Method
Indirect Method
When the contract us mutually terminated, the contractor is:
A. Blacklisted by the agency.
B. Required to pay LD.
C. Allowed to submit bids"
Disallowed to submit bids.
49. Pursuant to the RA 9184, what is the applicable rate for Liquidated damages (LD)?
A. 1/10 of 1%
B. 1/5 of 1%
C. 1/15 of 1%
D. 1/8 of 1%
50. Excavation of indurated rocks can be undertaken by?
A. Pick and Shovel
B. Ripper
C. Road Grader
Bulldozer