1.

1) Lines that are parallel in a plan view will be parallel in an isometric view.

a)

True

b)

False

2.

2) Non-isometric lines are easily drawn to scale.

a)

True

b)

False

3.

3) Electrical plans are of no use when installing a plumbing system.

a)

True

b)

False

4.

4) Section drawings show the section of land upon which the structure is to be built.

a)

True

b)

False

5.

5) Plumbing and Mechanical plans are sometimes combined.

a)

True

b)

False

6.

6) Detail drawings take precedent over floor plans.

a)

True

b)

False

7.

7) For positive pressure medical gas systems, piping shall be hard drawn, seamless copper tube, specification

a)

ASTM B88

b)

ASTM B819

c)

ASTM B280

d)

Any of the above

8.

8) Med-Gas joints shall be brazed within _ hours after the surfaces are cleaned for brazing.

a)

One

b)

Four

c)

Eight

d)

Twenty-four

9.

9) Level 1 medical air compressors shall be sized to serve the peak calculated demand and in no case shall there be fewer than ___compressors.

a)

Three

b)

Four

c)

One

d)

Two

10.

10) In a Med Gas System, what valve shall be placed such that a wall intervenes between the valve and outlets/inlets that it controls?

a)

Service

b)

Demand check

c)

Riser

d)

Zone

11.

11) The installation of medical gas and vacuum systems shall be made by experienced, qualified and competent installer. The installers shall meet the requirements of

a)

AWS B3 1.3

b)

ASSE Standard 6010

c)

ASME Section IX

d)

None of the above

12.

12) Medical air sources shall be used only for _____________ and calibration of medical respiratory

devices.

a)

Instrument air

b)

Air-operating devices

c)

Human respiration

d)

All of the above

13.

13) Shutoff valves for positive pressure gases shall

a)

Be cleaned for oxygen service

b)

Be three-piece in construction

c)

Have extensions for brazing

d)

All of the above

14.

14) To assure that all ambient air has been removed from the pipeline prior to brazing,

a/an ____________ shall be used to verify the effectiveness of the purge.

a)

Air analyzer

b)

Nitrogen analyzer

c)

Oxygen Analyzer

d)

Any of the above

15.

15) Backflow Prevention Devices or Assemblies installed in a Potable Water Supply System shall be tested

a)

At the time of installation

b)

A, C, and D

c)

At the time of repair or relocation

d)

Not less than on an annual schedule

16.

16) A certified backflow tester may ______ change the design, material, or operational characteristics of an assembly during maintenance or repair.

a)

Need to

b)

Temporarily

c)

Permanently

d)

NEVER

17.

17) A pressure vacuum breaker must be installed ___ above the highest downstream outlet.

a)

1 inch

b)

6 inch

c)

12 inch

d)

2 feet

18.

18) The term “air gap” in water distribution is

a)

A vent to atmosphere

b)

An air bubble in the piping

c)

An air-line piped to the tank

d)

The unobstructed vertical distance through the free atmosphere between the potable water supply to the flood rim of the vessel or fixture.

19.

19) The minimum air gap separation is

a)

1 inch

b)

3 inches

c)

6 inches

d)

12 inches

20.

20) An RP type back flow assembly should be installed a minimum of __ above a cement slab floor.

a)

6 inches

b)

12 inches

c)

38 inches

d)

60 inches