1.

A project manager received the project charter for a new product. The project is expected to have two main deliveries: the hardware part that has detailed specifications already defined, and the user interface software that has only a basic specification and a requirement for a user experience design approach. Which project management approach should the project manager use?

a)

A hybrid approach will work, using agile for software development and a predictive approach for the hardware deliveries.

b)

The software development has a high uncertainty level, so an agile approach is recommended for the project.

c)

The deliverables are significantly different, so the project should be split into two projects that are driven by a program.

d)

The scope is well defined; therefore, a predictive approach is straightforward and the hardware and software can by synchronized on the gates.

2.

A company initiated a project to introduce a new product to the market. The product must undergo the industry's regulatory process prior to approval and launch. What should the project manager do to realize this opportunity?

a)

Hire a third party who is an expert on the industry's regulations to work out the details.

b)

Escalate the issue to the company's CEO who has experience with the regulations.

c)

Communicate with the industry's regulatory authority to grant the company an exception.

d)

Comply with the regulatory requirements and work to compress the project schedule.

3.

A team member is reporting challenges in handling assigned tasks due to changes in project scope. How should the project manager respond to this issue?

a)

Reassign the tasks to other team members to avoid further delay.

b)

Organize a team meeting to discuss potential ways to deal with the expanded scope.

c)

Revise the project schedule to accommodate the changes in scope.

d)

Submit a change request to align the scope with available resources.

4.

During the planning phase of a project, the project manager discovered that a key stakeholder's expectations were not included in the scope document. What should the project manager do next?

a)

Proceed with the current scope document to avoid delays.

b)

Notify the stakeholder about the omission and work on updating the scope.

c)

Escalate the issue to the project sponsor to avoid taking responsibility.

d)

Request the stakeholder to submit a formal change request.

5.

A project manager is running an agile project and notices the team is not meeting the sprint goals due to a lack of clarity in user stories. What should the project manager do?

a)

Assign more resources to the team to increase their capacity.

b)

Conduct a sprint retrospective to evaluate the quality of the user stories and make improvements.

c)

Request the product owner to define detailed requirements before the next sprint.

d)

Proceed with the current backlog and make adjustments in the next sprint.

6.

The customer has requested a significant change that impacts the project timeline. What should the project manager do first?

a)

Immediately begin implementing the requested changes.

b)

Perform an impact analysis and submit the findings to the change control board.

c)

Ask the customer to prioritize the change for future implementation.

d)

Revise the project schedule to accommodate the change.

7.

In a complex project involving multiple stakeholders, a key stakeholder has conflicting priorities with the project objectives. What should the project manager do?

a)

Exclude the stakeholder from further decision-making to avoid delays.

b)

Escalate the issue to the project sponsor to mediate the conflict.

c)

Schedule a meeting with the stakeholder to align expectations and resolve conflicts.

d)

Adjust the project scope to meet the stakeholder's demands.

8.

During the execution of a project, a project team member has been consistently missing deadlines. What should the project manager do to address this issue?

a)

Report the team member to senior management.

b)

Assign fewer tasks to the team member to reduce the workload.

c)

Have a one-on-one conversation with the team member to identify the underlying causes.

d)

Reassign the tasks to other team members.

9.

A project manager realizes that the cost variance (CV) of the project is negative. What does this mean for the project?

a)

The project is under budget.

b)

The project is over budget.

c)

The project is behind schedule.

d)

The project is ahead of schedule.

10.

A key deliverable has failed the quality inspection and needs to be reworked. What is the project manager’s next step?

a)

Request additional resources to complete the rework as quickly as possible.

b)

Update the risk register with the newly discovered issue.

c)

Conduct a root cause analysis to prevent future quality issues.

d)

Adjust the project schedule to accommodate the rework.

11.

A project team is performing well, but one team member is consistently underperforming, causing delays. What should the project manager do first?

a)

Reprimand the team member in front of the team to set an example.

b)

Reassign the team member to another project.

c)

Meet with the team member privately to understand the reasons for underperformance.

d)

Assign the team member fewer tasks to reduce the pressure.

12.

During project execution, the project manager notices that a key team member is consistently missing deadlines, impacting the project's progress. What should the project manager do first?

a)

Escalate the issue to the sponsor.

b)

Investigate the root cause and address the issue with the team member.

c)

Reassign the team member’s tasks to other team members.

d)

Extend the project deadlines to accommodate the delays.

13.

A stakeholder expresses dissatisfaction with the project’s progress, even though the project is on schedule and within budget. What should the project manager do?

a)

Ignore the feedback since the project is on track.

b)

Meet with the stakeholder to understand their concerns and address them.

c)

Escalate the issue to the project sponsor.

d)

Reassure the stakeholder that the project will be completed as planned.

14.

The project team has encountered an unforeseen technical issue that could delay the project by two weeks. What should the project manager do next?

a)

Extend the project deadline to account for the delay.

b)

Update the risk register and work with the team to implement a mitigation plan.

c)

Escalate the issue to senior management.

d)

Request additional resources to solve the issue faster.

15.

A customer requests a significant change to the project scope, which would impact the project timeline and budget. What should the project manager do first?

a)

Reject the request to maintain the project schedule.

b)

Approve the change immediately to keep the customer satisfied.

c)

Perform an impact analysis and submit the change request for approval.

d)

Ask the customer to wait until the next phase of the project.

16.

The project manager is managing a hybrid project. The hardware portion of the project is following a predictive approach, while the software portion is following an agile approach. What should the project manager do to ensure both portions are aligned?

a)

Treat both portions separately and manage them independently.

b)

Integrate the planning and reporting processes for both approaches to ensure alignment.

c)

Use the predictive approach for the entire project.

d)

Use the agile approach for the entire project.

17.

A project is delayed due to a resource shortage. The project manager has identified that hiring additional resources could bring the project back on schedule but will increase the cost. What should the project manager do next?

a)

Proceed with hiring additional resources to meet the schedule.

b)

Present the trade-off to the sponsor and seek approval before hiring.

c)

Reallocate existing resources to critical tasks to save costs.

d)

Extend the project timeline to avoid additional costs.

18.

During a project review, a stakeholder suggests a feature that was not included in the original scope. What is the best action for the project manager?

a)

Approve the feature and include it in the next phase.

b)

Evaluate the feature’s impact on the project and follow the change control process.

c)

Reject the suggestion to avoid scope creep.

d)

Escalate the suggestion to senior management for a decision.

19.

A project manager discovers that a key deliverable has failed quality inspection. What should the project manager do next?

a)

Escalate the issue to the sponsor.

b)

Conduct a root cause analysis and develop a corrective action plan.

c)

Reassign the task to a more experienced team member.

d)

Ignore the issue as it was an isolated case.

20.

The project team is experiencing difficulties due to unclear requirements. What should the project manager do to resolve this issue?

a)

Ask the customer to clarify the requirements in writing.

b)

Organize a requirements clarification workshop with the stakeholders.

c)

Proceed with the project based on the current understanding of the requirements.

d)

Reassign the task to another team to handle the ambiguity.

21.

A project manager finds that the project is over budget. The cost performance index (CPI) is 0.85. What does this indicate?

a)

The project is under budget.

b)

The project is over budget.

c)

The project is on track.

d)

The project is ahead of schedule.

22.

The cost performance index (CPI) is 0.85. What does this indicate?

a)

The project is under budget.

b)

The project is over budget.

c)

The project is on track.

d)

The project is ahead of schedule.

23.

A stakeholder notices that an important functionality for their area was not tested. Which tool should the project manager have used to prevent this situation?

a)

Project charter

b)

Stakeholder register

c)

Project scope statement

d)

Issue log

24.

A project sponsor has requested that the project manager reprioritize the team's tasks to include a feature that is not part of the minimum viable product (MVP) for the project. How should the project manager address this situation?

a)

Include the feature in the iteration backlog and ask the team to work on it.

b)

Add the feature to the product backlog and discuss it with the team and sponsor for the next iteration.

c)

Include the feature in the iteration backlog and add the tasks after the current tasks are completed.

d)

Add the feature to the product backlog and explain the consequences to the sponsor.

25.

A project manager was recently assigned to a project with a fixed-cost contract. They identified several internal constraints that will prevent the project from being completed on time. What should the project manager do next?

a)

Create a contingency plan.

b)

Create an assumption log and map assumptions to impediments.

c)

Create an issue log template.

d)

Create a schedule management plan.

26.

A project manager is working on a complex transformation project. One of the key resources refuses to approve the project plan. What should the project manager do next?

a)

Communicate with the resource's supervisor.

b)

Speak directly with the resource.

c)

Organize a team meeting.

d)

Reassign the resource.

27.

A project sponsor is promoting the use of new technology that guarantees cost savings but lacks operational support. What should the project manager do to resolve this conflict?

a)

Focus on a resolution that benefits the customer.

b)

Adhere to the original project plans.

c)

Promote the new technology.

d)

Communicate the project's progress.

28.

A project manager is managing an agile project and notices product development issues due to unclear requirements. What should the project manager do?

a)

Review issues and identify opportunities for improvement that add value.

b)

Rework the definition of done before pulling items into the backlog.

c)

Ask the team to re-estimate tasks.

d)

Escalate the issue to the sponsor.

29.

A project manager is tasked with demonstrating the benefits of building a new branch, renting an existing building, or not expanding at all. What should the project manager do?

a)

Perform a gap analysis.

b)

Calculate the costs and compare the net present value (NPV).

c)

Perform a Kano analysis.

d)

Calculate the payback period (PBP).

30.

A project manager notices communication issues among team members distributed across different countries. What should the project manager do to improve communication?

a)

Set up a team communications management plan.

b)

Explain the benefits of common working hours.

c)

Share a contact log document.

d)

Arrange face-to-face meetings.

31.

A key deliverable failed to meet quality expectations and the project sponsor requests immediate corrective action. What should the project manager do?

a)

Conduct a root cause analysis and develop a corrective action plan.

b)

Escalate the issue to the project sponsor.

c)

Reassign the task to a more experienced team member.

d)

Adjust the project schedule.

32.

A project manager is managing a project with a fixed budget. A third-party supplier is demanding immediate payment but the organization has not yet received payment from the client. What should the project manager do?

a)

Reassign resources from other projects.

b)

Explain the situation to the client and request payment.

c)

Process a bank loan to pay the supplier.

d)

Delay the project until payment is received.

33.

A project sponsor is keen on using unapproved technology. What should the project manager do to resolve this?

a)

Acknowledge the lack of approval and focus on a resolution that benefits the customer.

b)

Maintain and adhere to project plans.

c)

Promote the new technology.

d)

Escalate the issue to senior management.

34.

A stakeholder asks the project manager to reprioritize tasks in a way that might cause delays. What should the project manager do?

a)

Explain the impact of the change and ask the team to prioritize the new tasks in the next iteration.

b)

Implement the change immediately.

c)

Escalate the issue to senior management.

d)

Reassign the team to work on the new tasks.

35.

A project team has been using agile methodologies and is transitioning to hybrid. The project manager is asked to demonstrate a quick win. What should the project manager do?

a)

Use an agile approach to deliver working functionality earlier.

b)

Use a predictive approach to ensure detailed upfront planning.

c)

Continue using the current hybrid approach without changes.

d)

Present a detailed cost analysis to stakeholders.

36.

A project manager is working on a project with high uncertainty. A key stakeholder has conflicting priorities with the project objectives. What should the project manager do?

a)

Exclude the stakeholder from decision-making.

b)

Escalate the issue.

c)

Meet with the stakeholder to align expectations.

d)

Adjust the project scope.

37.

A project manager finds that their project is running over budget and behind schedule. The cost performance index (CPI) is 0.85. What does this mean?

a)

The project is under budget.

b)

The project is over budget.

c)

The project is on schedule.

d)

The project is ahead of schedule.

38.

A project manager receives an additional requirement from a stakeholder during the middle of a sprint. What should the project manager do first?

a)

Add the requirement to the current sprint.

b)

Notify the team to adjust their tasks to accommodate the requirement.

c)

Review the impact of the change with the team.

d)

Escalate the requirement to senior management.

39.

A project sponsor wants to add a new feature that will extend the project's timeline. What should the project manager do first?

a)

Implement the feature immediately.

b)

Perform an impact analysis and create a change request.

c)

Reject the feature request to maintain the timeline.

d)

Delay the implementation of the feature until a future phase.

40.

A customer requests a change to the project scope that will impact the project budget. What should the project manager do?

a)

Approve the change to keep the customer satisfied.

b)

Create a change request and perform an impact analysis.

c)

Reject the request to maintain the project budget.

d)

Implement the change and inform the team.

41.

A project team member is consistently failing to meet deadlines. What should the project manager do first?

a)

Reassign the team member to less critical tasks.

b)

Meet with the team member to discuss the issue and find a solution.

c)

Escalate the issue to senior management.

d)

Extend the project timeline to accommodate the delays.

42.

The project sponsor asks the project manager to speed up the delivery of a key milestone. What should the project manager do first?

a)

Compress the schedule and allocate more resources.

b)

Perform a schedule analysis and assess the impact.

c)

Reassign tasks to expedite the delivery.

d)

Inform the sponsor that speeding up delivery is not possible.

43.

During project execution, a stakeholder requests weekly status reports. What should the project manager do?

a)

Provide the reports as requested.

b)

Inform the stakeholder that monthly reports are more appropriate.

c)

Escalate the request to the project sponsor.

d)

Deny the request to avoid additional work.

44.

A key deliverable has failed the quality inspection and needs to be reworked. What should the project manager do?

a)

Update the project schedule to accommodate the rework.

b)

Escalate the issue to the project sponsor.

c)

Conduct a root cause analysis and implement corrective actions.

d)

Reassign the task to a different team member.

45.

A project manager is working on a project with a fixed budget, and the actual costs are higher than planned. What should the project manager do?

a)

Request additional funding.

b)

Perform a cost analysis and adjust the budget.

c)

Implement cost-cutting measures to reduce expenses.

d)

Reallocate resources to critical tasks.

46.

A new development project is about to start, and the project manager knows that a high- profile customer makes very specific and frequent requests in all sprints. This project will demand contract coordination with third parties, and the project manager must find a better way to manage customer and partner expectations.

What strategy should the project manageruse?

a)

Specify the scope and features to be deployed in the contract clearly.

b)

  Change the marketing and product management definitions to meet stakeholder needs.

c)

   Focus on the implementation of a software as a service (SaaS) solution for the customer.

d)

   Work very closely with the customer and third parties to meet their needs.

47.

A project manager is in the middle of a project when one of the key project team members needs to take an unexpected and prolonged leave of absence. The project isahead of schedule and running under budget.

Which two actions should the project manager take initially to resolve this problem? (Choose two)

a)

Check the project's responsibility assignment matrix (RAM) to determine which activities will be affected

b)

Check if the team member's activities are sufficiently documented to facilitate handover.

c)

  Check the risk register for a prepared response to a resource being suddenly unavailable.

d)

Obtain the project sponsor's support to replace the team member on leave.

e)

  Reassign responsibilities across the remaining members using the available float for training.

48.

A team member shares with their functional manager some negative details about the performance of another team member that was discussed during the retrospective.

The project manager finds out about this discussion.

 

What two actions should the project manager take? (Choose two.)

a)

   Meet with the product owner to talk about the situation.

b)

   Contact the team member to explain what information can be shared outside the team.

c)

Contact the team member's functional manager and invite them to the next retrospective.

d)

A.   Meet with the sponsor to review the situation.

49.

  A project for developing software for a retail company's procurement system is in the initiation phase. The project sponsor has expressed concern that the forecasted project implementation date coincides with the company's financial budget planning period.

Which two actions should the project manager take next to address this concern? (Choose two)

a)

Facilitate a risk workshop with all stakeholders in attendance to identify and assess all risks to the project.

b)

Change the project implementation date so that the concern is alleviated and no longer applicable.

c)

  Communicate to the project sponsor that the implementation date is low risk and will not impact the

 

project.

d)

  Advise the sponsor that it is not feasible to determine if the end date will be met as the project is in the initiation phase.

e)

Log the concern as a risk in the project risk register and assess the impact and severity of the risk.

50.

A project has recently kicked off. The project manager observes that there are different expectations among the project team members. These growing misunderstandings are affecting team productivity. Which document should the project manager use as a guide to resolve the issue?

a)

Project organization charts

b)

Team charter

c)

Project charter

d)

Stakeholder register

51.

An organization is using a hybrid delivery approach for a complex project. In the iteration review, a senior manager is asking for a complete redesign of the functionality presented.This may require a significant change in the technical architecture and an additional release. What should the project lead do first?

a)

  Discuss with the solution architect

b)

   Discuss with the development team

c)

Discuss with the product owner

d)

Discuss with the technical lead

52.

A company is transitioning from a predictive approach to an agile approach. The team members work remotely, and some have personal conflicts that make them unavailable for some project ceremonies. The product owner has made it clear that the agenda is very tight and the team should make every effort to participate in all ceremonies.

What should the project manager, as a servant leader, do to address this situation?

a)

  Ask the team members to decide collectively on how to support the team.

b)

Engage in separate ceremonies with these team members to allow them to stay on the project.

c)

  Evaluate alternative options and try to find resources with similar skills.

d)

Perform the ceremonies without the team members and send them notes by email.

53.

A project team consists of members based in country A and subject matter experts (SMEs) based in country B with a 12-hour time difference. What can the project manager do to improve interactions between the team members in both countries?

a)

  Ensure full participation of both the product owner and business SMEs in scope planning sessions.

b)

  Explore the opportunity to have both teams colocated.

c)

Identify virtual communication methods and arrange for regular team meetings accordingly.

d)

Plan for frequent face-to-face meetings.

54.

Two members of a new project team disagree on the best approach to solve a problem.

 

The conflict has been going on for 1 week. The two members are tense around each other and are taking everything personally. What should the project manager do?

a)

Send both team members to the human resources (HR) department for an acceptable resolution

b)

Understand each team member's argument and select the one that results in less risk to the project

c)

Help the team members to resolve the conflict in a way that results in the best team performance

d)

Offer a compromise that is acceptable to both team members, even if it may not be the best solution

55.

A project manager is faced with a situation where a critical vendor is unable to deliver on time. What should the project manager do first?

a)

Seek alternative vendors to fulfill the requirement.

b)

Communicate with the vendor to understand the delay and explore solutions.

c)

Inform the project sponsor about the potential impact on the timeline.

d)

Adjust the project schedule to accommodate the delay.

56.

A project manager is leading a project that requires collaboration with multiple departments. What should the project manager do to ensure effective communication?

a)

Establish a communication plan that outlines roles and responsibilities.

b)

Hold weekly meetings with all departments involved.

c)

Use email as the primary method of communication.

d)

Assign a liaison from each department to facilitate communication.

57.

A project manager is faced with a situation where team members are not meeting deadlines due to unclear task assignments. What should the project manager do to address this issue?

a)

Clarify task assignments and set clear deadlines for each team member.

b)

Ignore the issue and hope it resolves itself.

c)

Reassign tasks to different team members.

d)

Conduct a team-building exercise to improve morale.

58.

A project manager is leading a project that requires collaboration with multiple external vendors. What is the best approach to ensure effective communication?

a)

Establish a communication plan that includes regular updates and meetings with all vendors.

b)

Communicate only when issues arise to avoid overwhelming the vendors.

c)

Assign one vendor to communicate with the others.

d)

Use email as the primary communication method for all updates.

59.

A project manager discovers that a critical task is falling behind schedule due to unforeseen circumstances. What should the project manager do first?

a)

Assess the impact of the delay on the overall project timeline.

b)

Immediately inform the stakeholders about the delay.

c)

Reassign the task to another team member.

d)

Extend the deadline for the task without further analysis.

60.

A project team is in the planning stage and has prepared a list of activities and completed sequencing the

 

activities. During a review, the team noted that there is a dependency missing between:

 

*  Test the product

 

*  Release to customer

 

According to the quality management plan, the product must be tested before being released. How should the project manager enter this dependency?

a)

Start to start

b)

   Start to finish

c)

   Finish to start

d)

   Finish to finish

61.

     A project has been running successfully for 2 months. At a regular project meeting, the team raises several potential obstacles to future progress. The obstacles include vendor delivery performance, technical performance of a subsystem, and conflict with another division of the organization.

What should the project manager do next?

a)

  Determine a change response to identify and resolve the obstacles to move the project forward.

b)

 

   Escalate the obstacles to the project sponsor for assistance with resolution.

c)

  external stakeholders and the other division of the organization to resolve the issues.

d)

Work with the team and others in the network to assess and prioritize the obstacles.

62.

  A project manager is working on a major construction project. Part of the agreed-upon plan was to use a cloud-based system with a server that runs on high-speed internet service since most of the team members work virtually. The company needs to reduce operating costs as much as possible and management insists that the project will now use a system running on a conventional dial-up service. What should the project manager do next?

a)

Meet with management about their decision and ask them to get another project manager

b)

   Agree with management and continue working the project management plan.

 

c)

 

.   Replace some of the team members that work virtually to help the company save money.

d)

Evaluate the impact of this decision and communicate with management

63.

   A team member has experienced personal conflicts on past projects, making them nervous about working on the current project. The project manager knows this team member could add value to the project.

What should the project manager do to get the most value from this team member?

a)

Advise the team member to focus on the current project and consider the past conflicts as lessons learned.

b)

   Advise the team member not to share personal information from past projects with the entire team.

c)

  Consult with the project sponsor to find out if it is allowed to share personal information with the entire team.

d)

Consult with human resources (HR) and check company policies on what is allowed to advise the team member.

64.

A complex project is in the execution phase. A key stakeholder who is new to the project has not been approving project deliverables, which could impact the overall progress.

 

What should the project manager do next?

a)

Meet with the stakeholder to understand what is causing the delays.

b)

  Facilitate a brainstorming session to find potential workarounds.

c)

   Capture this in the issue log and escalate it to the project sponsor.

d)

  Discuss the need to influence this stakeholder with the sponsor.

65.

  A project has been running successfully for 2 months. At a regular project meeting, the team raises several potential obstacles to future progress. The obstacles include vendor delivery performance, technical performance of a subsystem, and conflict with another division of the organization.

What should the project manager do next?

a)

  Determine a change response to identify and resolve the obstacles to move the project forward.

b)

Escalate the obstacles to the project sponsor for assistance with resolution.

c)

  Engage with the external stakeholders and the other division of the organization to resolve the issues.

d)

   Work with the team and others in the network to assess and prioritize the obstacles.

66.

    A project manager is working on a major construction project. Part of the agreed-upon plan was to use a cloud-based system with a server that runs on high-speed internet service since most of the team members work virtually. The company needs to reduce operating costs as much as possible and management insists that the project will now use a system running on a conventional dial-up service. What should the project manager do next?

a)

meet with management about their decision and ask them to get another project manager.

b)

   Agree with management and continue working the project management plan.

c)

  Replace some of the team members that work virtually to help the company save money.

d)

   Evaluate the impact of this decision and communicate with management.

67.

   A project manager is managing a hybrid project. There is software in place to access the repository of project artifacts. However, a few stakeholders are reporting that they are unable to find the latest project schedule. What should the project manager do?

a)

   Send the project schedule via email to the stakeholders who need that information.

b)

Make sure all stakeholders have access to the system and know where to find project artifacts.

c)

  Escalate the issue to the steering committee and ask them to deal with the stakeholders’ lack of training.

d)

Advise the project management office (PMO) that there is a resource gap for sharing project

68.

   A customer support team has planned short, iterative cycles for working on customer- reported issues. Recently, there was a surge of high-priority issues that disrupted the original plan, and the team's manageris finding it difficult to manage the progress.

Which approach should the project manager suggest using?

a)

Agile Scrum approach

b)

   Spiral approach

c)

Agile Kanban approach

d)

  Rapid application development approach

69.

A project manager has been assigned to a global project involving regulatory bodies, government agencies, internal company leaders, the project team, and end users. What should the project manager do to engage them all effectively?

a)

  Analyze the stakeholders.

b)

Check lessons learned from past projects

c)

Gather business requirements

d)

Remove any bias that exists on the team

70.

    In a highly politicized organizational environment, the stakeholders are driven by their own operational or business goals, which results in conflicting interests regarding the project. What should the project manager do to steer the stakeholders toward the collective project goal?

a)

Anticipate, alert, and follow the risk management process

b)

Detect, track, and follow the issue management process

c)

Promote, inspire, and follow the stakeholder engagement process

d)

Discuss, educate, and follow the communications management process

71.

A client has asked the project manager for the program status report. The project manager sends the report and then realizes that they accidentally included another manager from the client's organization on the email.

What should the project manager do?

a)

Wait for the client's feedback regarding the report.

b)

Resend the email to the client, excluding the other manager

c)

  Inform the client and their supervisor about the mistake.

 

d)

Contact the other manager and ask them to delete the email

72.

  A project manager is managing a complex research project with a high level of uncertainty. A request is made to implement a mechanism to measure the quality of the deliverables.

Using a hybrid approach, what techniques can be used to achieve this goal?

a)

Daily Scrum and product owner quality assessments

b)

Paired work and the customer role method

c)

Time-boxed iterations and standup review meetings

d)

   Scrum master reviews and the quality Kanban method.

73.

At a project status meeting, different activities were agreed upon for the following weeks. At the end of the first week, the project team realizes that the activities were executed in the wrong way because each team member had a different understanding. These misunderstandings have caused a delay in the project.

 

Which of the following actions should the project manager take to avoid this situation in the future?

a)

Conduct reviews prior to performing activities

b)

Use a common communication terminology

c)

Monitor the team's performance metrics

d)

Document the agreement in the meeting minutes

74.

The change control board (CCB) rejects a change request submitted by a subject matter expert (SME). The SME refuses to accept thisrejection and does not want tocontinue the project without the change. What should the project manager have done to avoid this situation?

a)

Ensured that the change request was aligned with the project scope

b)

Requested that the sponsor approved the change request first

c)

Submitted the change request directly to the CCB.

d)

Assessed the change's overall impact to the project before submission

75.

  A project manager is using an agile approach. During the sprint planning meeting, the product owner flagged a backlog item as high business value and easy to implement.

However, the other team members identified a high dependency between this item and another item that is flagged as low business value and high complexity.

What should the project manager do to support the backlog prioritization?

a)

Facilitate the discussion until the team reaches an agreement about the two items

b)

Prioritize the item flagged as a dependency with low business value and high complexity

c)

Prioritize the item flagged as high business value and low complexity for this sprint.

d)

  Support the team to move both items to the next sprint when the team will know more

76.

  A project manager was recently assigned to a project that is in the execution phase and is experiencing roadblocks. During a review of the processes and procedures, the project manager notices similarities to a previous project that experienced similar roadblocks. The project manager reviews the task schedule and finds that certain tasks are well behind expectations. In speaking with the project team, the project manager confirms that the team is following the processes exactly.

What should the project manager do?

a)

Review the resources allocated to the project and change accordingly

b)

   Review and amend the processes to ensure only value-adding activities are present.

 

c)

  Update the variation register to account for the extended project time.

 

d)

Update the schedule to account for the unexpected delays in the project tasks

77.

A stakeholder on a project has a reputation for being easily angered and unreasonably difficult on projects. The project manager would like to minimize the impact of the stakeholder's behavior on the

 

development team.

 

What training should the project manager choose for their team to help with this situation?

 

a)

Agile training

b)

Emotional intelligence training

 

c)

  Communication training

d)

  Negotiation training

78.

   A leader from project B consistently reaches out to a team member in project A for assistance. What should project A's project manager do?

a)

Ensure project A's team member can finish thework committed to project

b)

Talk with project B's leader to discuss possible impacts to both projects

c)

Allow project B's leader to continue building relationships

d)

Tell project A's team member to ignore project B's leader

79.

    An agile coach and technical writer for a globally distributed agile team are in a country with a 9-hour time zone difference from the agile team. The agile coach and project lead disagree on the timing for the daily standup. The project lead thinks the standup should be at 10:00 am local time, but the agile coach and technical writer feel that is an inconvenient time for them.

How does the project lead ensure adherence to agile practices?

a)

Escalate to management that the agile process is not going to work and ask them to speak to the agile coach.

b)

Inform the agile coach that the daily standup will be at 10:00 am local time and ensure all parties can attend.

c)

Have two separate daily standups, one for the agile coach and technical writer and one for the agile development team

d)

  Have a discussion with the team on the approach and come to a decision on when the daily standups should be.

80.

    A project manager joins an existing project. One project stakeholder is unhappy with the frequency and types of project updates received and has made a request for more information to be shared. What should the project manager do next?

a)

Schedule a meeting with the stakeholder to better understand their request

b)

Update the project communications management plan immediately

c)

Inform the stakeholder to wait for the annual stakeholder review meeting

d)

Consult the scope baseline document to track project updates

 

81.

     Team members of a new scrum team are skilled and excited about the project, despite never having worked together before. The project leader requested an offsite team building activity to talk about the project and get familiar with each other, but the activity was not approved by the sponsor who is trying to save money. The project leader believes it is important to hold a team building activity to bring the team together.

What should the project leader do?

a)

Explain the financial constraint and ask each team member to pay their own share for the event

b)

Use the office facilities and support to organize an interactive event for the team members in-house

c)

Tell the team that the event will be handled at the end of the project due to current financial constraints

d)

Bypass the event because the team members’ seniority is enough to engage without further activities

82.

     Stakeholders in some industries prefer to deal with programmers and system analysts directly, bypassing project managers. This complicates managing resources on projects.

How should a project manager solve thisissue

a)

Promote adoption of the communications management plan with the project team

b)

Request a meeting with senior management to escalate the situation

c)

Host a team-building event to develop team cohesion and improve communication

d)

  Propose implementing a new project management information system (PMIS).

83.

After meeting with stakeholders, a project manager working at a computer gaming company is creating a project management plan for the company's newest offering. The project manager learns that the company's main competitor is scheduled to release a similar offering leveraging the newest technology. Theproject manager fears that the competitor's offering is better in multiple ways compared to the project manager's project.

What should the project manager do?

a)

  Perform a Kano analysis factoring in the competitor's offering and present it to the stakeholders.

b)

Meet with the development team to see what changes will improve the project compared to the competition's deliverable

c)

Meet with the project team to discuss the concerns and determine how to ensure the project's deliverable can compete with the competitor's

d)

Note this concern in the risk register and meet with the sales team to identify mitigation options factoring in the competitor's offerings

84.

  In the daily check-in meeting, a team member informs the project team that the licenses for one of the components that will be used will expire in a couple of months. The licensing cost is significant.

What should the project manager do next?

a)

Escalate the licensing issue to the product owner

b)

Evaluate the impact of nonrenewal of the license

c)

Add a spike to the backlog for an alternative design

d)

   Raise a change request to secure the renewal.

85.

   A project manager held a meeting and framed the project schedule. A critical stakeholder, who was not consulted at the time of theschedule discussion, complained that the published dates are not agreeable due to a prescheduled task for another assignment.

What should the project manager do first?

 

a)

  Reach out to the project sponsor and request additional resources.

b)

Analyze the root cause of the issue and update the communications management plan.

c)

  Organize a new schedule framing meeting with the critical stakeholder to obtain input.

d)

Discuss with the project sponsor and create a new project schedule.

86.

An agile project team discovers that they are unable to implement a feature completely in the first iteration. The team believes it may not be able to complete the tasks in the second iteration. The feature is

 a critical component that the customer has prioritized. What should the team do?

a)

Reduce the scope of the feature to fit into one iteration and deliver it to the customer.

b)

Go back to the customer and explain that they cannot implement the feature completely in one iteration

c)

Split the feature into smaller subfeatures, implement them, and then deliver them incrementally in multiple iterations.

d)

Ask the customer to simplify the feature so that it can be implemented in one iteration.

87.

An intern is replacing a critical resource midway through a sprint. To help the intern get up to speed, the project manager assigns a senior engineer in the team as the intern's mentor. Two months later, the project goes into critical status, delaying the release milestone by a month.

What should the project manager have done to avoid this scenario?

a)

   Requested an experienced resource as a replacement

b)

  Convinced the critical resource to remain on the project

c)

   Allocated additional time for mentoring

d)

  Negotiated additional time to complete the project

88.

   After 35 years of service, a company's CEO has retired. The new CEO is planning to digitally transform the company and has assigned a new project manager to assist in this endeavor. The initial backlog has been created and agreed upon, and the team members have been assigned.

What should the project manager do before the project kick-offmeeting?

a)

  Conduct a backlog refinement and identify the key activity to start with.

b)

Compare the team's expertise against the project requirements

c)

Perform integration management activities to consolidate the plans

d)

  Review the project's environment to understand the organizational culture.

 

89.

   A project manager is leading a hybrid project. The only available resources that have experience with agile are not at the project manager's location. The project has a strict schedule and budget, and the project manager is concerned about their ability to deliver it. What should the project manager do?

a)

A.   Plan to have the agile resources temporarily relocate to the project manager's location.

b)

Advise the sponsor that the project will be delayed as agile training will be required

c)

Engage the agile resources through video conferencing on a daily basis.

d)

  Request a budget extension to get local resources experienced in agile.

90.

        A project team member is having difficulty delivering assigned tasks for a project that is at risk of being delayed. The main issue is that the team member does not understand a new

system that was recently implemented. What should the project manager do?

a)

Escalate the team member's performance to the project sponsor

b)

Ask the team member to learn the new system as on-the-job training.

c)

Issue a change request to extend the project schedule

d)

   Assign an experienced resource to support the team member.

91.

   A product owner is trying to understand how many of the user stories have been completed within a 2-week sprint. How should the project manager approach this situation?

a)

Invite the product owner to regular standup meetings

b)

Use retrospectives to deliver the finished products

c)

Have a face-to-face conversation with the product owner

d)

Share the burndown chart with the product owner

92.

       A project is about to start with a global project team. Travel is not a viable option for project team members, so most will participate virtually.

What should the project manager do to engage the team?

a)

Invest in a virtual collaboration/colocation environment.

b)

Ask human resources (HR) for team-building recommendations

c)

Schedule weekly team meetings to encourage collaboration

d)

Have one-on-one meetings with team members to improve communication

93.

  A project manager is assigned midway through a project. The team members are in different locations across the country and they are unable to meet in-person often. During a status review meeting, one of

the stakeholders highlighted that they were unaware of the status for the project deliverables. What should the project manager do first?

a)

Request the project team include the stakeholder's details and make sure the project status reports are shared with the stakeholder

b)

Schedule a meeting with the stakeholder, and include the stakeholder’s needs in the project management plan

c)

Review the stakeholder management plan and update the stakeholder register for incorporation in the project management plan.

d)

  Review the communications management plan and verify whether the stakeholder's needs are captured in the project management plan.

94.

  A project involves exporting 150 packages to the customer. However, only 30 packages have been cleared by the customer for shipment. The logisticsmanager provided details to the customer 2 weeks ago and set up a weekly conference call to effectively communicate with them, but the customer has notbeen participating in the calls.

How should the project manager handle this situation?

a)

  Find the root cause of the issue and discuss the customer's current engagement.

 

b)

Inform the customer that subsequent packages cannot be manufactured

c)

  Request a change in the contract to include the shipment in the project management plan.

d)

Request a delivery date extension from the customer

95.

A project manager is faced with a situation where a critical team member is frequently absent due to personal issues. What should the project manager do to ensure project continuity?

a)

Ignore the absences and continue with the project.

b)

Discuss the situation with the team member to understand their challenges.

c)

Reassign the team member's tasks to others without consulting them.

d)

Report the team member's absences to HR.

96.

A project manager notices that the project is falling behind schedule due to unforeseen circumstances. What is the best course of action?

a)

Extend the project deadline without consulting stakeholders.

b)

Analyze the project schedule and identify tasks that can be expedited.

c)

Communicate the delay to stakeholders and request additional resources.

d)

Ignore the delay and hope the team catches up.

97.

A project manager is implementing a new software tool for project tracking, but the team is resistant to change. What should the project manager do to facilitate the transition?

a)

Force the team to use the new tool immediately.

b)

Provide training sessions and highlight the benefits of the new tool.

c)

Continue using the old tool until the team is ready.

d)

Ignore the team's concerns and proceed with the implementation.

98.

   A project manager is part of a cross-functional agile team. Throughout the project, it has become obvious that team members from different functional units have different perspectives of what the outcome should be.

What should the project manager do to resolve this?

a)

Schedule a meeting with the stakeholders to determine a consensus regarding the outcome

b)

  Invite the project sponsor to the sprint review to provide clarity on the sprint outcome.

c)

  Ask the product owner to address the concerns about the project outcome during the sprint retrospective.

d)

Check to ensure the project outcome aligns with the project charter and statement of work (SOW).

99.

A project manager is faced with a situation where team morale is low due to recent project setbacks. What should the project manager do to improve team morale?

a)

Organize a team-building activity to boost morale.

b)

Ignore the issue and focus on project tasks.

c)

Reassign team members to different projects.

d)

Conduct a meeting to discuss the setbacks and gather feedback.

100.

A project manager notices that the project scope has expanded significantly without formal approval. What should the project manager do?

a)

Document the changes and seek retrospective approval.

b)

Continue with the expanded scope to meet deadlines.

c)

Inform the team to adjust their tasks accordingly.

d)

Escalate the issue to senior management immediately.

101.

A project manager is preparing for a project kickoff meeting and realizes that not all stakeholders have been identified. What should the project manager do?

a)

Proceed with the meeting and address stakeholders later.

b)

Identify all stakeholders and reschedule the meeting.

c)

Invite only the known stakeholders to the meeting.

d)

Send an email to stakeholders after the meeting.

102.

In a complex project with several subcontractors, one subcontractor reports a likely delay in the schedule. This could affect the other subcontractors and impact their ability to deliver on time. 

What should the project manager do first?

a)

Report the delay to all other subcontractors

b)

Change the milestones and sequence of work

c)

Escalate to senior management and the stakeholders

d)

Assess the schedule and update the risk register

103.

A new project has been kicked off following a planning session. The project is under direct oversight of an executive in the organization. After a review meeting, the project manager overhears an executive request a dashboard from one of the team members to show the overall project status.

What should the project manager do?

a)

Ask the team member to develop a dashboard to fulfill the request.

b)

  Tell the team member to route the request through the project manager.

c)

Update the communications management plan to include informal requests

d)

Update the stakeholder engagement assessment matrix

104.

A project manager is faced with a situation where team members are not collaborating effectively. What should the project manager do to enhance teamwork?

a)

Implement team-building activities to foster collaboration.

b)

Assign tasks individually to avoid conflicts.

c)

Monitor team interactions closely and intervene when necessary.

d)

Conduct a survey to identify team members' concerns.

105.

A project manager is reviewing the project timeline and realizes that a critical task is behind schedule. What is the best course of action?

a)

Reassess the project timeline and adjust deadlines accordingly.

b)

Communicate with the team to understand the reasons for the delay.

c)

Escalate the issue to senior management for guidance.

d)

Implement overtime for the team to catch up on the task.

106.

A project manager is preparing for a project kickoff meeting and wants to ensure all stakeholders are aligned. What should the project manager do?

a)

Send out a detailed agenda and project overview to all stakeholders.

b)

Hold individual meetings with key stakeholders before the kickoff.

c)

Prepare a presentation to share during the meeting.

d)

Request feedback from stakeholders on the project plan.

107.

A highly skilled team resource received a job offer and is leaving the project soon. What should the project manager do to maintain project performance while a new team member is being onboarded?

a)

Offer cross-training and mentoring to the new team member

b)

Log a risk in the risk register and work with the new team member to mitigate it.

c)

Motivate the new team member to perform

d)

Share project documents with the new team member

108.

     A team is not delivering the committed work. Cards are not moving on the kanban board, and the burndown chart shows that the sprint progress is slow.

What should the agile project manager do?

a)

   Change the work in progress (WIP) limit to reflect the team's capacity.

b)

  Discuss the performance with senior leadership.

c)

  Meet with the project team members who are slow in delivering tasks.

d)

  Consider the use of alternative performance metrics.

109.

A project manager notices that team members are frequently missing deadlines due to poor communication. What should the project manager prioritize to address this issue?

a)

Set up a new communication tool for the team.

b)

Discuss the missed deadlines in the next team meeting.

c)

Send individual reminders to each team member about their tasks.

d)

Conduct a survey to understand the communication barriers.

110.

A project manager is evaluating the performance of a vendor who has consistently delivered late. What should the project manager do to address this issue?

a)

Terminate the contract immediately.

b)

Schedule a meeting with the vendor to discuss performance issues.

c)

Ignore the delays if the project is still on track.

d)

Request a discount for the late deliveries.

111.

A project manager is preparing for a project kickoff meeting and realizes that not all stakeholders have been identified. What should the project manager do?

a)

Proceed with the meeting and address stakeholders later.

b)

Identify all stakeholders and reschedule the meeting.

c)

Invite only the known stakeholders to the meeting.

d)

Send an email to stakeholders after the meeting to inform them of the outcomes.

112.

      A project manager has recently joined a small company. The company's chief operating officer (COQ) asked the team to skip some steps in the process inorder to work more quickly. The project manager wants to ensure that these steps are not skipped in the future.

What should the project manager do?

a)

   Escalate the issue to the other executive leadership members.

b)

  Notify all team members that all steps in the process must be completed.

c)

Schedule a review of the process steps with the team and the COO.

d)

  Redesign the process so the team can move more quickly.

113.

       An oil and gas project started without having acquired full funding for the project. The remaining funds were to be acquired during project execution. The acquisition of the remaining funds was delayed several months, resulting in a suspension of work by all contractors.

What should the project manager have done to prevent this from happening?

a)

Ensured the stakeholder anticipated obstacles to achieving financial closure on the remaining funds

b)

Ensured the stakeholder who was providing additional funds remained interested in the project.

 

c)

Ensured the risk was adequately assessed and mitigated by the appropriate stakeholders.

d)

Ensured the project team monitored and reviewed the project risk register periodically

114.

A project manager is faced with a situation where a key team member is consistently underperforming, affecting the overall project timeline. What should the project manager do first?

a)

Provide additional training to the team member.

b)

Have a discussion with the team member to understand the issues.

c)

Reassign the team member's tasks to others.

d)

Document the performance issues and escalate to senior management.

115.

During a project review, a team member suggests a new tool that could improve efficiency but requires additional budget approval. What should the project manager do?

a)

Implement the tool immediately to enhance productivity.

b)

Evaluate the tool's benefits and present a proposal for budget approval.

c)

Reject the suggestion to avoid budget overruns.

d)

Discuss the tool with the project sponsor for further guidance.

116.

A project manager is managing a project with multiple dependencies. A delay in one task threatens the entire project timeline. What should the project manager do?

a)

Ignore the delay and continue with other tasks.

b)

Communicate with the team to identify solutions to mitigate the delay.

c)

Request an extension from the project sponsor.

d)

Reassign resources from other tasks to the delayed task.

117.

During project execution, a project manager discovers that the budget at completion has shifted significantly and is higher than expected.

What should the project manager do?

 

a)

Adjust the original budget estimates with the current cost variance.

b)

  Perform a root cause analysis of the project performance.

c)

   Review the activity duration to reforecast the project completion date.

d)

  Negotiate the project changes and adjust stakeholder expectations.

118.

A project manager is faced with a situation where a team member is not following the established communication protocols. What should the project manager do first?

a)

Ignore the issue as it may resolve itself.

b)

Schedule a meeting with the team member to discuss the importance of communication protocols.

c)

Escalate the issue to senior management.

d)

Reassign the team member to a different project.

119.

During a project, a critical supplier fails to deliver materials on time. What is the best course of action for the project manager?

a)

Wait for the supplier to resolve the issue.

b)

Contact the supplier to understand the delay and explore alternative solutions.

c)

Immediately find a new supplier without consulting the team.

d)

Inform the project sponsor about the delay and request additional resources.

120.

A project manager notices that team morale is low due to increased workload. What should the project manager do to address this?

a)

Ignore the issue and focus on project deliverables.

b)

Organize a team-building activity to boost morale.

c)

Reassign tasks to lighten the workload for the team.

d)

Communicate with the team to understand their concerns and find solutions.

121.

A project manager is assigned to a project in a company that is transitioning to agile. Not all stakeholders believe in the project, and some stakeholders would like the entire project defined an 

planned out early in the project. However, the project sponsor needs a quick win to ensure the continuation of the project.

What approach should the project manager use?

 

a)

  An agile approach as this would provide working functionality earlier.

b)

A predictive approach as this would please the senior stakeholders

c)

Ahybrid project as this will mitigate stakeholders’ concerns

d)

  A predictive approach as this will show benefits for all stakeholders.

122.

A project manager is faced with a situation where team members are not communicating effectively, leading to misunderstandings. What should the project manager do to improve communication?

a)

Implement regular team meetings to facilitate open communication.

b)

Assign a communication lead to handle all team interactions.

c)

Limit communication to formal emails only.

d)

Ignore the issue as it will resolve itself over time.

123.

A project manager discovers that a critical task is behind schedule due to unforeseen circumstances. What is the best course of action?

a)

Reassess the project timeline and adjust deadlines accordingly.

b)

Ignore the delay and focus on other tasks.

c)

Request additional resources to expedite the task.

d)

Communicate the delay to stakeholders and seek their input.

124.

During a project, a team member expresses doubts about the timeline for a critical task. What should the project manager do?

a)

Ignore the doubts and stick to the original timeline.

b)

Ask the team member to elaborate on their concerns in a discussion.

c)

Delegate the task to another team member.

d)

Review the timeline and adjust it based on the team member's feedback.

125.

A project manager has access to risk management tools but chooses to use a quantitative method to evaluate the project risks. During project execution, the project sponsor asks for an updated risk matrix. What should the project manager do next?

a)

  Use integrated risk management software to evaluate the risks.

b)

Use their own professional knowledge to reassess the risks.

 

c)

Add new risks and send the risk matrix to leadership for approval

d)

Trust in the quantitative method already chosen as it is a precise method

126.

A project manager is faced with a situation where the project scope has expanded significantly due to stakeholder requests. What should the project manager do first?

a)

Document the changes and update the project scope statement.

b)

Reject the requests to maintain the original scope.

c)

Communicate the impact of the changes to the stakeholders.

d)

Implement the changes immediately to satisfy the stakeholders.

127.

During a project, the project manager realizes that the team is not following the established communication plan. What should the project manager do?

a)

Reinforce the communication plan with the team and provide training if necessary.

b)

Ignore the issue as long as the project is progressing.

c)

Change the communication plan to fit the team's preferences.

d)

Escalate the issue to senior management for intervention.

128.

A project manager is reviewing the project performance metrics and notices that the schedule performance index (SPI) is below 1. What does this indicate?

a)

The project is ahead of schedule.

b)

The project is on schedule.

c)

The project is behind schedule.

d)

The project is over budget.

129.

        A project manager has received a new request to integrate more features to a product. The team is fully allocated, and there is no budget to acquire new resources.

What strategy should the project manager implement to deal with this situation?

a)

Ask the team to accelerate the iterations and avoid interruptions.

b)

Verify team performance and ask for improvement during daily standup meetings

c)

  Recommend that the project sponsor increases the budget to bring new resources.

 

d)

Discuss the problem with the team and decide how to do the work together

130.

       A project team is having difficulties understanding technical details regarding requirements. The information was not initially provided by the customer, butthe information is critical in the current iteration for clarification on how tasks need to be accomplished.

How should the project manager approach this situation?

a)

Educate the customer and have them participate in daily standup meetings.

b)

Request that the customer reviews and clarifies feature definitions for the current sprint.

c)

  Send a burndown chart of the current sprint to the customer and seek clarifications.

d)

  Schedule weekly meetings and product reviews with the customer to clarify requirements.

131.

       A project manager is leading an agile project in an organization that has not executed this type of project before. In order to ensure the project is following the compliance requirements, what should the project manager do?

a)

  Use the risk register to document all of the compliance vulnerabilities generated by the project so that all decisions are well documented and approved by stakeholders.

b)

  Meet with the project management office (PMO)/compliance entity to work on process tailoring to ensure that the agile deliverables support the compliance requirements of the organization.

c)

   Follow the organization's process and deliverables for predictive projects, even if they compromise the agility and performance of the project.

d)

  Coach upper management on agile practices, explaining that an agile project is concerned with value

 

delivery, and negotiate a way out of the compliance requirements.

132.

A project manager is faced with a situation where team members are not collaborating effectively, leading to misunderstandings. What should the project manager do to improve team collaboration?

a)

Implement stricter deadlines to enforce accountability.

b)

Organize team-building activities to foster better relationships.

c)

Assign tasks individually to minimize conflicts.

d)

Hold regular meetings to discuss progress and address issues.

133.

A project manager discovers that a critical risk was not identified during the planning phase. What should the project manager do to address this oversight?

a)

Update the risk management plan and communicate the new risk to stakeholders.

b)

Ignore the risk since it was not identified earlier.

c)

Escalate the issue to senior management for guidance.

d)

Conduct a team meeting to discuss the implications of the oversight.

134.

       A network transformation project to increase efficiency and return on investment (ROI) is in the implementation stage. A conflict between the head of the network and the transformation manager arises. What should the project manager do to manage this?

a)

  Analyze the context of the issue.

b)

  Evaluate the influence of the parties involved.

c)

  Lead the parties to find a compromise.

d)

Escalate the problem to the project sponsor.

135.

  The product team is progressing with a prototyping approach to deliver a multiyear business initiative. A few user stories are taking longer to be delivered.

What should the project manager do?

 

a)

  Inform stakeholders about the delay during project updates.

b)

Determine cross-dependencies and plan a spike in the next sprint.

c)

  Discover the gaps in the communications management plan and address them accordingly.

d)

  Determine the risks and identify a resolution during the retrospective meeting.

136.

     Afew key team members recently left the project team. The remaining members took time to understand the details and found it difficult to make progress. As a result, the project schedule is seriously delayed.

What should the project manager do?

 

a)

Request additional resources to be incorporated to the project team.

b)

  Observe the project team and give them time to catch up before escalating.

c)

  Review the issues and adjust the project plan to give a realistic schedule.

d)

   Escalate to the project sponsor and seek alternatives to resolve the issue.

137.

  By the end of the first sprint, a project lead notices that one of the team members is not performing very well. Which form of communication should the project lead use to handle the situation?

a)

Informal written communication, such as a friendly reminder

b)

  Formal verbal communication, such as a conversation at the end of the sprint retrospective

c)

 

   Formal written communication, such as an email with a copy sent to the manager

d)

Informal verbal communication, such as a conversation

138.

Several components of an expensive manufacturing project have been returned by the customer. The customer is complaining that the quality of thecomponents is poor and is concerned that, as a result, their products will be returned due to quality issues. The project manager is certain that quality has been maintained.

How should the project manager communicate with the customer to help assure them that the project has produced quality products?

a)

  Show the customer the tolerance and control limits.

b)

  Show the customer sample results from the current batch.

c)

Show the customer a sample history of quality.

d)

Show the customer the quality control measurements.

139.

    A risk was raised during the initiation of a project. The supplier discontinued software support for one of the project's required inputs. The project manager planned a reserve budget to allow the project to continue in the event of this occurrence. What should the project manager do?

a)

Ask the supplier to continue providing software support until the end of the project

b)

  Inform the sponsor that the risk has been realized and that a decision has to be made for the project to continue.

c)

Tell the project team to stop work, as software support will be canceled and the project cannot continue

d)

Advise the supplier that the sponsor will pay for software support as previously planned.

140.

     A project manager assigned team members to work in pairs on a large amount of technical reports. At times, the project manager noticed that important information was not shared properly among the team. This has caused delivery delays and, ultimately, the failure to complete the project. What is the root cause of this issue?

a)

  Lack of team member training on documentation planning

b)

  Team cohesiveness was lost because team members worked in pairs

c)

   Improper assignment of tasks to team member pairings

d)

   Incorrect communication techniques applied during implementation

141.

A project manager is assessing the impact of a new regulation on the project timeline. What should be their first step?

a)

Update the project schedule immediately.

b)

Conduct a thorough impact analysis.

c)

Inform the stakeholders about the new regulation.

d)

Request additional resources to accommodate the changes.

142.

A project manager is faced with a situation where a key team member is frequently absent, impacting the project timeline. What should the project manager do first?

a)

Discuss the issue with the team member to understand the reasons for their absence.

b)

Reassign the team member's tasks to others immediately.

c)

Ignore the issue as it may resolve itself.

d)

Escalate the issue to senior management.

143.

A project manager is reviewing the project performance and notices that the team is consistently missing deadlines. What should the project manager do to address this issue?

a)

Conduct a performance review with the team to identify the root causes.

b)

Implement stricter deadlines to enforce accountability.

c)

Ignore the issue as it may improve over time.

d)

Reassign tasks to different team members.

144.

      A company just started managing a project using an agile approach. Due to this change, the general manager is worried about the scope definition process for upcoming projects.

What should the project manager do to ensure the project scope is completely defined?

a)

   Ask for a budget increase to implement a double-check process to ensure every business need is included in the requirements.

b)

  Help sponsors and stakeholders craft the product vision, and bring the team and product owner together to clarify expectations.

c)

Ask the general manager to review every requirement to ensure all projects will deliver the requested products

d)

  Meet with the general manager and convince them to return to using predictive approaches to avoid any risk.

145.

During the execution of a project, a key stakeholder complains to the project manager about recent communications. The key stakeholder explains that the relevant information from the project team was incomplete and late. As a result, the key stakeholder is beginning to disengage from the project.

What should the project manager do?

a)

Send relevant information to all key stakeholders simultaneously to ensure consistent communication

b)

Update the communications management plan to fulfill the key stakeholder's expectations about relevant information

c)

Explain to the key stakeholder the way in which the project team communicates information.

d)

  Ask the project sponsor to hold a meeting with the key stakeholder to ensure that the stakeholder is engaged in the project.

146.

    A project manager is preparing the business case for a project in a not for profit organization. The  project manager justifies the cost of the project to a group of sponsors. Which benefits realization metric should the project manager use?

a)

  Total value of ownership

b)

Budget at Completion (BAC)

c)

  Payback period

d)

  Return of investment (ROI)

147.

A project manager has been assigned to a corporate project management office (PMO). They are responsible for leading the development and rollout of updated project management procedures and templates that would include both predictive and agile approaches.What should the project manager do after the documents are completed?

a)

  Hire an external consultant to monitor the execution of the new procedures.

b)

   Upload the files to the corporate website to be available for internal use.

c)

Meet with the department managers to help them roll out the new procedures.

 

d)

Develop a training plan for all of the stakeholders to learn about the updates

148.

The client will not agree to closure, claiming that the project team has not performed the code inspections mandated in the development contract. The project team has performed the code inspections, however the records are not complete. What should the project manager do?

a)

Hold a meeting with the project team, project sponsor, and the client to agree to the further work required to close the project and add to lessons learned.

b)

  Close the project and hand over the deliverables to the client.

c)

   Hold a lessons learned workshop with the project team and project sponsor to avoid contractual compliance issues arising in future projects.

d)

Seek expert legal advice on the interpretation of the clauses in the contract.

149.

An agile senior project team member suddenly resigns from the organization. Following this departure, the remaining team members are having difficulty accessing information and are unable to complete a deliverable.

What should the project manager have done to avoid this situation?

a)

Updated the job descriptions for all team roles.

b)

  Ensured the project repository is up to date.

c)

Made an effort to reemploy the senior project team member.

d)

   Provided specialist training for all team members.

150.

A research and development team is finishing up a two year initiative The project manager is focused on the closing activities for the project.Which activity should be considered as a priority?

a)

Mark the product backlog completion status and update the communications management plan.

b)

Ensure that knowledge transfer activities are executed as planned

c)

Release the resources and plan for a project completion celebration.

d)

Hold a steering committee meeting to inform them of the project completion

151.

A junior staff member was recently assigned to the team. The new team member tells the project manager that they are confused because they are not familiar with what is expected of them on the project.What should the project manager do to assist the new team member?

a)

Advise the new team member to enroll in project management training.

b)

Instruct the new team member to review the responsible, accountable consult, and inform (RACI) matrix before asking for help

c)

Advise the new team member to review the project charter and stakeholder engagement plan.

d)

Review the resource management plan and provide mentoring to the new team member if necessary

152.

Early in the execution phase, a project manager discovers that recent changes in enterprise environmental factors (EEFs) will severely reduce the implementation cost and shorten the project schedule. How should the project manager address this situation?

a)

Meet with the project team to decide how the remaining budget will be spent.

b)

Keep the extra budget as management reserve until project closeout

c)

Give the team extra time to finish tasks within the original timeline

d)

Follow the project escalation policy and communications management plan

153.

A project manager has team members around the world in many different time zones Project work frequently stalls because people in one office need to wait until another office is awake to have questions answered.What should the project manager have done to avoid this?

a)

Used communication tools, such as video conferencing so different offices could communicate.

b)

Learned more about how each team member prefers to communicate before assigning project work

c)

Planned and scheduled tasks and work packages to overcome geographical and time zone challenges

d)

Ensured that the project would be the highest priority for all team members

154.

After a project has been approved, a key stakeholder tells the project manager that the current project management strategy is not well defined The project manager is also informed that the key stakeholder does not want to hold a working session.What should the project manager do first?

a)

Share the project documents and invite the key stakeholder to discuss any concerns

b)

Ask the project sponsor to exert authority on the key stakeholder in order to maintain the approved timeline

c)

Proceed with a working session for teams that do not belong to that key stakeholder

d)

Invite the key stakeholder to the project's change control board (CCB) to discuss adjustment of the project strategy

155.

During the implementation stage of a project. a newly appointed team leader approaches the project manager to verify the team's tasks and schedule. The work did not go as planned due to the team leader's lack of management experience. This could cause delays for the project.What should the project manager do?

a)

Ask the human resources director to appoint a senior team leader

b)

Inform the project sponsor about the possible delay

c)

Directly manage the project team to avoid project delays

d)

Provide mentoring to the newly appointed team leader

156.

A project manager is acting as a scrum master in a hybrid project and is dealing with a conflict between team members What strategy should be used to handle this conflict?

a)

Sort conflicts into two groups: positive and negative

b)

Place conflicts into categories: structural and interpersonal.

c)

Place conflicts on a shared conflict list and ensure it is visible

d)

Review conflicts during daily Scrum so they are handled in a timely manner

157.

A verbal announcement is made that the new team member joining the Scrum team has limited mobility The scrum master is aware that some team members are unsure how the dynamics of the team will change What should the scrum master do?

a)

Create a stakeholder engagement plan

b)

Design a communications management plan

c)

Update the team charter accordingly.

d)

Set up a meeting to discuss accommodations the team will have to make

158.

A learn has been working for two months and has consistently missed planned user stories How should the project manager address this issue?

a)

Ensure the sprint size is appropriate for the iteration duration.

b)

Promote changing the iteration duration in order to commit as planned.

c)

Engage in recruiting a highly skilled resource to reinforce the skills.

d)

Consider using a reward system to encourage timely delivery

159.

The project team finds that the latest delivery from a vendor is missing a critical component, which will likely delay the project in split of corrective measures. What should the project manager do to communicate this message?

a)

Ask the vendor to identify the stakeholders affected, create an action plan and determine an implementation date

b)

Draft a warning letter to the vendor ask internal stakeholders to comment, and solicit stakeholder support to hold the vendor accountable

c)

Identify the worst-case scenario, put it into the project risk register, share the register with all project stakeholders, and raise an alert.

d)

Contact department managers who are identified as stakeholders, solicit concern, and provide updates to the situation

160.

In a hybrid project, the customer has issued a contract that specifies the deliverables for each quarter The customer wants to show their stakeholders a tangible outcome in the first quarter and wants to move the second milestone to the first quarter The project manager explains to the customer that it is not feasible unless the requirements for the second milestone are changed.Which two actions should the project manager take? (Choose two)

a)

Convince the customer to leave the second milestone in place and not change it.

b)

Escalate the issue to upper management to resolve the problem and suggest a plan.

c)

Go back to the development team and discuss which second milestone requirements can be performed in the first quarter.

d)

Ask the customer for their priorities regarding the requirements for the second milestone

e)

Tell the customer that moving the milestone has a very high impact on the cost of the project

161.

A new project manager is assigned to lead an agile project The project manager wants to use motivation to encourage the team to perform well throughout the project.What should the project manager do?

a)

Use the management reserves to fund some team-building activities

b)

Inflate project estimates to provide a financial buffer for team activities.

c)

Find another method to increase the team's performance

d)

Implement a reward system aimed to keep the team engaged and motivated

162.

During the implementation phase of a construction project the customer asked a key subcontractor to deliver a work package ahead of time The subcontractor was not prepared for it and asked the project manager for additional budget What should the project manager do first?

a)

Ask upper management for more funds and update the project budget

b)

Revise the project scope accordingly to cope with the budget changes

c)

Update the risk register and project log. and manage the budget closely.

d)

Submit a change request to accelerate the project as requested

163.

Development team members are located in three different time zones It is difficult to find a suitable time to hold the daily standup for all team members.What should the project manager do?

a)

Encourage frequent small team meetings with two or three team members.

b)

Give up the daily standup and replace it with a daily report

c)

Let the team members decide themselves if they want to join the meeting.

d)

Require all team members to join the daily standup regardless of the meeting time

164.

As a member of an organizational change management team, a project manager must pass on any changes to the project team The project manager needs to avoid any misunderstandings or resistance to help ensure that the project team will support any organizational change.What should the project manager do?

a)

Conduct meetings with resistant members to facilitate smooth project implementation

b)

Meet with the team on a regular basis to ensure they are aware of changes.

c)

Influence the team to communicate any changes

d)

Check with the team

165.

A project manager is in a learn meeting and the project team requires a decision to be made about a new suggested timeline due to an impact from a potential scope change.What should the project manager do?

a)

Make the decision on behalf of the organization

b)

Review the stakeholder map along with the organizational chart and delegate the most senior person to make the decision

c)

Schedule a project decision meeting with all stakeholders to discuss the decision.

d)

Follow the stakeholder engagement plan

166.

At the end of a meeting a functional manager takes the project manager aside to raise some concerns on behalf of a project team member who is unclear about their role and responsibilities for the project What should the project manager do in this situation?

a)

Develop a work plan for the project team member with the help of the resource manager

b)

Advise the functional manager and the project team member to review the resource management plan

c)

Tell the functional manager and the project team member to review the project charter

d)

Ask the functional manager to create a specific responsible, accountable, consult, and inform (RACI) chart for the team member

167.

A new agile team is forming and the project manager notices that the team is struggling in many areas The team is experiencing both the inability to meet iteration commitments and team member conflicts.What should the project manager do next?

a)

Raise the issues in the retrospective and propose solutions

b)

Inform management that commitments will not be met.

c)

Involve management to help resolve the conflicts

d)

Coach the team both as a whole and individually

168.

A team is holding the first demonstration of the software built to date on a medium-sized project The product owner has uncovered a number of issues they would like to be addressed before providing approval.How should the project manager approach this problem?

a)

Plan to address the issues through backlog grooming and incorporate them into the next sprint

b)

Refer the product owner to the change management plan, then escalate to the steering committee

c)

Refer the product owner to the signed business requirement document and explain that the current plan cannot facilitate these changes

d)

Tell the product owner the issues will be addressed in the second version of the software

169.

A project manager receives a voicemail from a business analyst on the project team The business analyst indicates that an internal stakeholder is upset that they were not included before the project began The stakeholder is asking for an addition to the requirements traceability matrix.What should the project manager do to improve the stakeholder relationship?

a)

Consult the project scope document to make sure the addition is in scope.

b)

Update the stakeholder engagement plan to ensure the stakeholder is included in the project stakeholder list

c)

Initiate a project change request so the change control board (CCB) can decide if it is in scope.

d)

Engage the stakeholder to solicit more information before responding to the request

170.

The resource management plan is already done, and the team is located in different countries around the world Team members are in multiple time zones and they use different languages for communication The project manager needs to keep the team organized and avoid misunderstandings and miscommunication that may produce a negative impact to the project.What should the project manager do to reduce negative impacts to the project?

a)

Modify the communications management plan to account for regional differences

b)

Conduct cultural awareness seminars

c)

Hold a virtual meeting to discuss the political environment.

d)

Conduct a multigenerational management training session

171.

Two weeks after the approval of the project management plan for a global project, the project manager noticed that it was approved based on a different level of understanding by international stakeholders and is not what the project manager presented for approval.What should the project manager have done to prevent this from happening?

a)

Sent the meeting minutes to the stakeholders after the kick-off meeting

b)

Reviewed all the approvals immediately after the kick-off meeting was over

c)

Ran separate kick-off meetings for each culture and time zone

d)

Validated each stakeholder's understanding during the kick-off meeting

172.

A project manager is tracking a project, but a key stakeholder will not accept the project's key performance indicator (KPI) results Which tool or technique should the project manager use?

a)

Autocratic decision making

b)

Expert judgment

c)

Context diagram

d)

Change control tools

173.

After gathering all the requirements for a project with dependencies on external stakeholders, the project team is finishing the second iteration At this point, the project manager learns about a possible change in regulations that would prevent the product launch.What should the project manager do to realize benefits?

a)

Add an entry in the risk log

b)

Implement the changes

c)

Review target benefits.

d)

Improve the team's velocity

174.

An organization is embarking on the deployment of a new digital solution that will revolutionize purchasing services The project manager has created all the necessary plans and activities to ensure a successful integration and solution launch There is a risk of a partner’s system being unavailable which could impact the project negatively.What key activity is needed to ensure the project's success?

a)

Communicate to the project stakeholders that full integration may not be possible and that the project will potentially be delayed as a result.

b)

Eliminate the risk by mandating the partner to change the system settings to facilitate an easier integration with the new solution

c)

Continuously monitor the risk of the partner system's unavailability, and put the proper resolution plans in place in case the risk materializes into an actual issue

d)

Mitigate the risk by developing alternative plans to make the solution ready and available without full integration capabilities

175.

A project manager is struggling to figure out the performance of the project teams in an agile environment for the same scope of work, team A has calculated 100 story points and team B has calculated 125 story points.Which team is performing better?

a)

Team A as they have calculated fewer story points than team B.

b)

Team B as they have calculated more story points than team A

c)

The team that completes the most stories selected from the sprint backlog

d)

The team with the least amount of defects in their deliverables

176.

During a project’s third iteration, two of the existing team members were replaced As the project entered the next iteration, the team velocity dropped and the performance started to slip.What should the project manager do?

a)

Guide the team to revert back to the forming and storming stages

b)

Escalate the issue to the project sponsor.

c)

Convene a team building event to address key performance indicators (KPIs).

d)

Discuss the decrease in productivity with human resources

177.

An organization is introducing agile to its projects. During an informal discussion the project manager learned that team members who are currently working on different teams are discussing how they would like to be together on the same team.What should the project manager do?

a)

The project manager should not allow resources to choose teams because the project manager assigns the resources based upon project needs

b)

The project manager should not allow resources to choose on which team they would like to work because they will always choose their favorite team

c)

The project manager should allow the resources to periodically choose on which team they would like to work.

d)

The project manager should indicate that the team members have already been assigned to a team through workforce optimization

178.

A project manager is faced with a situation where team members are not adhering to the established communication protocols. What should the project manager do to address this issue?

a)

Ignore the issue as long as the work is being completed.

b)

Implement stricter communication rules and monitor compliance.

c)

Reiterate the importance of communication protocols in a team meeting.

d)

Escalate the issue to senior management for further action.

179.

A project manager discovers that a critical task is falling behind schedule due to unforeseen circumstances. What is the best course of action?

a)

Escalate the issue to the project sponsor for guidance.

b)

Ignore the delay and hope the team catches up.

c)

Communicate with the team to identify solutions and reallocate resources.

d)

Reassess the project timeline and adjust deadlines accordingly.

180.

A project manager is evaluating the performance of a vendor who has consistently delivered late. What should the project manager do next?

a)

Conduct a performance review and discuss the issues with the vendor.

b)

Continue working with the vendor and hope for improvement.

c)

Terminate the contract immediately.

d)

Escalate the issue to senior management without addressing it with the vendor.