CIV3CPM Review

Total questions: 31

Worksheet time: 18mins

Name
Class
Date
1.

Top-down estimates are most likely to occur during the ______ phase

a)

Conceptual

b)

Planning

c)

Execution

d)

Delivery

2.

Which of the following describes the "six-tenths" rule?

a)

Project Evaluation based on price inflation over time

b)

Cost estimation method based on size or capacity

c)

Project Evaluation based on probability pricing

d)

Cost estimation method based on price index of an item

3.

How many activity duration estimates are used for Program Evaluation & Review Technique?

a)

One

b)

Two

c)

Three

d)

Four

4.

Label the work breakdown structure (WBS) according to its hierarchy level.

5.

What is the most effective communication channel?

a)

Email

b)

Face-to-face

c)

Social Media

d)

Written letter

6.

For the PERT Analysis, the calculation of the duration of each activity follows:

a)

te=(2a+4m+2b)/6

b)


te=(a+4m+b)/6

c)


te=(a+4m+b)/3

d)


te=(a+4m+b)/2

7.

Which of the following key characteristics of a task is false?

a)


Be unambiguous

b)


Be continuous in time

c)

Be longer than a standard reporting period

d)

Be performed at a single site

8.

Why does expected value not work as well with extreme events?

a)


Extreme events have an immeasurable outcome

b)


Extreme events never happen

c)

Past performance is not an indicator of future returns

d)

Probability related to extreme events are not reliable

9.

What is true about Benefit-Cost Ratio (BCR)?

a)

Gives comparative value on whether a project should be taken up

b)

Gives a true and absolute value on whether a project should be taken up

c)

Gives an indication whether if the project can be completed within a given timeframe

d)


None of the above

10.

Types of business structure are all of these except:

a)

Simple

b)

Functional

c)

Network

d)

General

11.

Which of the following is NOT one of Australia's main types of businesses?

a)
Sole Proprietorship
b)
Partnership
c)

Public Company

d)
Cooperative
12.

Which components define the risk?

a)


Probability

b)

Severity

c)

Duration

d)

Cost

13.

Which is not the advantage of dividing project scope into work packages?

a)

Prepare project schedules and cost estimates

b)

Assign human resource responsibilities

c)


Improve the relationship within the workspace

d)

Define a baseline for performance assessment and control

14.

Employees work as specialists for the entire company. What is the type of Organisational Structure?

a)


Functional

b)


Matrix

c)

Projectized

d)

None of the above

15.

CTE can be obtained by the following formula:

a)


(Cn-Cc)/(Tn-Tc)

b)


(Cc-Cn)/(Tn-Tc)

c)

(Tn-Tc)/(Cn-Cc)

d)

None of above

16.

Which of the following statement is true about the Work Breakdown Structure (WBS)?

a)


Identifies the project elements that require resources.

b)


Used to organize the cost estimates.

c)

Shows the critical path of a project

d)

All of the above

17.

What is the type of business structure used in this diagram?

a)

Network

b)

Simple

c)

Matrix

d)

Projectized

18.

Which of the following steps are involved in human resource planning?

a)


Assess current human resources

b)


Assess future human resources need

c)

Develop programs to satisfy future human resources need

d)

All of the above

19.

Which of the following is the main process in project communications management?

a)


Planning communication management

b)

Managing communications

c)

Monitoring communications

d)


All of the above

20.

Projects are characterized by four elements: Purpose, Complexity, Uniqueness, and Life cycle.

a)

True

b)

False

21.

Reorder the project life cycle.

a)

Initiating process

b)

Planning process

c)

Executing process

d)

Controlling and monitoring process

e)

Closing process

1)
2)
3)
4)
5)
22.

What is Budgeted Cost of Work Performed (BCWP) also known as?

(a)  

23.

Top-down estimation is also known as (a)   estimation.

24.

In decision making, what criteria assumes that each outcome is equally likely?

(a)  

25.

Reorder the list of risk response strategies from least to highest level of risk:

a)

Accept the risk

b)

Monitor the risk

c)

Transfer the risk

d)

Mitigate the risk

1)
2)
3)
4)
26.

Based on Maslow's Hierarchy of Needs, label the following:

27.

In a team of 4 people, how many communication channels are required?

a)

2

b)

4

c)

6

d)

8

28.

Which of the following is a key benefit of using the Critical Path Method (CPM) in project management?

a)

It helps in identifying the shortest path to complete a project

b)

It provides a detailed cost analysis of the project

c)

It identifies the longest sequence of dependent tasks

d)

It ensures all team members are equally utilized

29.

"To deliver a functional road that reduces existing traffic congestion".

Is this a well-written project goal in the SOW?

a)

Yes, it is!

b)

No, it is not!

30.

Is this a well-designed RACI matrix?

a)

Yes, it is!

b)

No, it is not!

31.

What improvements can be made for this subject?

2 lines