WorksheetsBuilding Up Rates Quiz: Reinforcement
Total questions: 7
Worksheet time: 4mins
Name
Class
Date
1.
What is the wastage percentage for cutting and damage in reinforcement work?
a)
2%
b)
5%
c)
10%
d)
15%
2.
What is the weight of a 10 mm diameter reinforcement bar per meter?
a)
1.579 kg/m
b)
0.888 kg/m
c)
0.616 kg/m
d)
0.395 kg/m
3.
How many hours does it take for a blacksmith to cut and bend 1 tonne of 16 mm Ø reinforcement?
a)
30 hours
b)
25 hours
c)
20 hours
d)
15 hours
4.
What is the labor output for unloading and sorting output per tonne?
a)
2 hours
b)
1.50 hours
c)
2.50 hours
d)
1 hour
5.
What is the weight of a 25 mm diameter reinforcement bar per meter?
a)
2.466 kg/m
b)
3.854 kg/m
c)
6.313 kg/m
d)
9.864 kg/m
6.
What is the labor output for placing bars in a wall for 1 tonne of 16 mm Ø reinforcement?
a)
30 hours
b)
35 hours
c)
50 hours
d)
40 hours
7.
What is the wastage percentage for ready to use bars (cut and bend)?
a)
5%
b)
2%
c)
15%
d)
10%
100 %