Building Up Rates Quiz: Reinforcement

Total questions: 7

Worksheet time: 4mins

Name
Class
Date
1.

What is the wastage percentage for cutting and damage in reinforcement work?

a)

2%

b)

5%

c)

10%

d)

15%

2.

What is the weight of a 10 mm diameter reinforcement bar per meter?

a)

1.579 kg/m

b)

0.888 kg/m

c)

0.616 kg/m

d)

0.395 kg/m

3.

How many hours does it take for a blacksmith to cut and bend 1 tonne of 16 mm Ø reinforcement?

a)

30 hours

b)

25 hours

c)

20 hours

d)

15 hours

4.

What is the labor output for unloading and sorting output per tonne?

a)

2 hours

b)

1.50 hours

c)

2.50 hours

d)

1 hour

5.

What is the weight of a 25 mm diameter reinforcement bar per meter?

a)

2.466 kg/m

b)

3.854 kg/m

c)

6.313 kg/m

d)

9.864 kg/m

6.

What is the labor output for placing bars in a wall for 1 tonne of 16 mm Ø reinforcement?

a)

30 hours

b)

35 hours

c)

50 hours

d)

40 hours

7.

What is the wastage percentage for ready to use bars (cut and bend)?

a)

5%

b)

2%

c)

15%

d)

10%