WorksheetsSpesifikasi Teknis Pekerjaan Konstruksi 1
Total questions: 12
Worksheet time: 12mins
What must construction work follow according to the RKS document?
Cost estimates
Standards Quality
Time schedules
Material lists
What is the maximum thickness for each layer of soil during compaction?
10 cm
15 cm
20 cm
25 cm
What is the required quality of concrete unless specified otherwise in the drawings?
fc'30 Mpa
fc'35 Mpa
fc'20 Mpa
fc'25 Mpa
What is the minimum thickness for the layer of sirtu during construction?
10 cm
25 cm
15 cm
20 cm
What should be done if the foundation excavation has roots or loose soil?
Excavate and refill with sand
Fill it with gravel
Cover it with concrete
Leave it as is
What is the required mixture for the Trassram mortar used in brick walls?
1 PC: 5 Sand
1 PC: 4 Sand
1 PC: 3 Sand
1 PC: 2 Sand
What is the minimum thickness for plastering walls?
1 cm
2 cm
0.5 cm
1.5 cm
What must be done before installing the ceiling?
Finish the exterior
Lay the flooring
Install electrical systems
Paint the walls
What is the purpose of the specifications in the RKS document?
To outline project costs
To ensure quality construction
To schedule project timelines
To select construction materials
What is the maximum depth for the layer of loose soil during compaction?
15 cm
10 cm
20 cm
25 cm
What should be done to areas with water accumulation during construction?
Create temporary drainage
Fill them with concrete
Ignore them
Cover them with tarps
What is the required ratio of PC to sand for ceramic tile adhesive?
1:4
1:2
1:3
1:1