UAS KUPEL

Total questions: 29

Worksheet time: 25mins

Name
Class
Date
1.

Software Configuration Management is a set of software engineering activities that occur after software has been delivered to the customer and put into operation

a)

True

b)

False

2.

A specification or product that has been formally reviewed and agreed upon, that thereafter serves as the basis for further development:

a)

Baseline

b)

Configuration object

c)

Source code

d)

Software Configuration Item

e)

Deliverable

3.

A different collection of objects at the same revision level and therefore coexists in parallel with others:

a)

Object

b)

Product

c)

Entity

d)

Version

e)

Variant

4.

The check-in and check-out process helps with which element of change control?

a)

Synchronization control

b)

Version control

c)

Resources control

d)

Budget control

e)

Object control

5.

Mechanism that helps to ensure that parallel changes, performed by two different people, don't overwrite one another.

a)

access control

b)

               synchronization control

c)

parallel control

d)

change control

e)

version control

6.

Configuration Audit focuses on the technical correctness of the configuration object that has been modified

a)

True

b)

False

7.

The followings are the reason of configuration management, except:

a)

Software must run on different machines

b)

Multiple people have to work on software that is changing

c)

Software cannot be changed when it has been released

d)

Software must run on different operating systems

e)

More than one version of the software has to be supported

8.

The activity in software configuration management that is the management of versions intended to coexist:

a)

Branch Management

b)

Promotion Management

c)

Release Management

d)

Change Management

e)

Variant Management

9.

Which configuration objects would not typically be found in the project database?

a)

Test Data

b)

Design specification

c)

Marketing Data

d)

Source Code

e)

Requirement specification

10.

The primary purpose of configuration status reporting is to:

a)

allow revision of project schedule

b)

allow revision of cost estimates by project managers

c)

make sure that change information is communicated to all affected parties

d)

None

e)

evaluate the performance of software developers and organizations

11.

A collection of objects at the same revision level:

a)

Release

b)

Entity

c)

Baseline

d)

Version

e)

Revision

12.

Choose all correct statements regarding Procedure and Work Instruction

a)

Procedure is tend to conform to international or national SQA standards

b)

Procedure is not required to conform to the organization's quality policy

c)

Work Instruction is tend to be universal within the organization

d)

Procedure is tend to be universal within the organization

e)

Work Instruction is a supplement to a procedure

13.

Procedure and Work Instruction are aiming at:

a)

To increase communication path

b)

Performance of tasks, processes or activities in the most effective and efficient way

c)

To simplify coordination

d)

Uniformity in performance

e)

To avoid creativity

14.

The followings are the motivation to update existing procedures, except:

a)

Changes in the organization's area of activity

b)

Analysis of failures as well as successes

c)

Technological changes in development hardware and communication equipment.

d)

Learning from the experience of other organizations

e)

New staff member

15.

Cost of Review is classified as Appraisal Cost:

a)

True

b)

False

16.

The contribution of checklist to software quality are as follows:
i. carrying out self-checks of documents or software code

ii. preparations for tasks

iii. completeness of document reviews

iv. improves efficiency of review sessions

a)

iv

b)

i and ii

c)

iii and iv

d)

iii

e)

i and iii

17.

Choose all the reasons of calculating the cost of SQA:

a)

To evaluate economic damages of software failures

b)

To control the costs associated with error prevention and detection of errors

c)

To calculate the salary of SQA team

d)

To facilitate economic evaluation of planned increase or decrease SQA activities

e)

To stop the increasing of the development cost

18.

Managerial Failure Cost can only be happening during Project Planning

a)

True

b)

False

19.

The followings are the class of cost of software quality assurance in the Classic Model, except:

a)

Internal failure cost

b)

Preventive cost

c)

Managerial failure cost

d)

Appraisal cost

e)

External failure cost

20.

Costs of re-programming or correcting programs in response to test findings can be classified as:

a)

Managerial failure cost

b)

Internal failure cost

c)

Appraisal cost

d)

External failure cost

e)

Preventive cost

21.

Immunity to biased interventions is achieved by choice of metrics and adequate

a)

True

b)

False

22.

Process metrics refer to the software system's operational phase

a)

True

b)

False

23.

The following are the objective of quality measurement, except:

a)

To compare performance with previous project's quality achievement

b)

To facilitate tester to detect failures

c)

To compare performance with software quality standards

d)

To identify situation that enable development process improvement

e)

To facilitate management control regarding deviations of planning

24.

Software quality metric should produces similar result when applied under similar condition. This requirement is known as:

a)

Comprehensive

b)

Relevant

c)

Mutually exclusive

d)

Valid

e)

Reliable

25.

Number of Code Errors (NCE) can be affected by the following factors, except:

a)

Reporting style of review and testing results

b)

Professionalism of software testing team

c)

Volume of comments in the code

d)

Percentage of reuse code

e)

Software complexity

26.

One of the Software Configuration Management tasks is Change Control. Explain the Systematic Change Control Process and how it can control the Access and Synchronization Control

4 lines
27.

Explain the objectives of procedures and work instruction

4 lines
28.
4 lines
29.

Tunjukkan subkelas biaya kualitas perangkat lunak yang termasuk dalam setiap pengeluaran berikut: biaya pencegahan, biaya penilaian, biaya persiapan dan pengendalian manajerial, biaya kegagalan internal, biaya kegagalan eksternal, biaya kegagalan manajerial.

a. Biaya yang dibayarkan kepada pelanggan sebagai kompensasi atas keterlambatan penyelesaian proyek, akibat dari jadwal yang tidak realistis dalam proposal.

b. Biaya proses pengujian integrasi.

c. Biaya pemutakhiran berkala rencana proyek.

d. Biaya pemutakhiran prosedur dan instruksi kerja.

e. Biaya perbaikan bug perangkat lunak yang terdeteksi selama operasi

4 lines