WorksheetsGas Installation Standards Quiz
Total questions: 5
Worksheet time: 3mins
In addition to standard meter labelling/notice(s), where a gas installation in a multi-occupancy building has a volume that exceeds 0.035 m³, what additional information shall be placed near or adjacent to the meter outlet point?
Details of the nearest fire exits from the building.
A notice indicating the installation volume exceeds 0.035 m³.
A label indicating that the meter regulator has been adjusted to 25 mbar.
A notice or label indicating that the installation be tested only to IGEM/UP/1A.
A new or replacement gas cooker hose for a cooker installed in a multi-occupancy building shall conform to what standard?
BS 699-1.
BS 6891.
BS EN 14800.
BS EN 16436-1.
Steel, copper and polyethylene (PE) tube used for gas installations in domestic premises may conform to which standards respectively?
BS 1256, BS EN 1057, BS 5114
BS EN 10255, BS EN 1254, BS EN 1555-1/2
BS EN 10255, BS EN 1057, BS EN 1555-1/2
BS EN 15266, BS 8537, BS EN 1555-1
When joining copper tube that is adjacent to pliable corrugated (stainless-steel) tubing, to prevent the risk of contamination/corrosion, what shall be done?
Only press end joints are to be used in the vicinity.
Only compression joints are to be used in the vicinity.
Soldering is to be completed and the components cleaned of flux after connection.
Soldering is to be completed and the components cleaned of flux before connection.
Mechanical joints shall not be used on gas pipework:
On kitchen and bathroom walls.
Under floorboards with no access.
Surface mounted on an outside wall.
On top of mineral fibre insulation in a roof space.