WorksheetsWeek3_Q1_Time Terms in Construction Project
Total questions: 15
Worksheet time: 8mins
George Brown's project is more or less (1) (a)
The procurement (2) (a) was quite tense as -
... was quite tense as the tenders all only arrived (3) (a)
Then the evaluation (4) (a) and a few items had to be negotiated with the lowest bidder.
The pre-start meeting had to be (5) (a) by a week.
Luckily the contractor (6) ...... by bringing ....
(a)
... by bringing the (7) (a) to take possession of the site forward
The (8) (a) set for completion is realistic
The contractor does not want (9).... but make use....
(a)
... but make use of the (10)... before winter sets in.
(a)
The contractor is optimistic and wants (11) (a)
Hopefully nothing unpredictable will (12).... building operations, which....
(a)
...., which would cause (13)... and ....
(a)
... and put work (14) (a)
The contractor is obliged to keep the client and the site engineer (15) (a)