What is the primary purpose of a preliminary cost estimate?

a)

To determine the final project cost

b)

To forecast the probable construction cost before the detailed design

c)

To negotiate contractor payments

d)

To determine profit margins

2.

Which of the following factors influence a cost estimate?

a)

Type, shape, and size of the building

b)

Quality of materials used

c)

Methods of construction

d)

All of the above

3.

What is a consequence of an excessively low preliminary cost estimate?

a)

The design could be inferior

b)

The project cost remains unchanged

c)

The client receives excess funds

d)

The construction is completed faster

4.

Which of the following is NOT a method of preliminary cost estimation?

a)

Floor area method

b)

Storey enclosure method

c)

Approximate quantities method

d)

Net profit method

5.

In the Unit Method of preliminary cost estimation, how is the cost estimated?

a)

Based on the total gross floor area

b)

By multiplying the cost per unit of accommodation by the number of units

c)

Using elemental cost planning

d)

By evaluating composite work items

6.

Which method is commonly used in Malaysia to estimate the cost of air-conditioned spaces?

a)

Floor Area Method

b)

Cubic Method

c)

Storey Enclosure Method

d)

Elemental Estimate

7.

Which of the following is a key disadvantage of the Floor Area Method?

a)

It does not consider differences in building height and shape

b)

It is too complex for clients to understand

c)

It cannot be used for public sector projects

d)

It is the slowest method to obtain cost estimates

8.

Why is the Tender Price Index (TPI) preferred over the Cost Index (CI)?

a)

It is easier to calculate

b)

It takes into account the tendering market and competitiveness

c)

It ignores inflation effects

d)

It is only relevant to the contractor

9.

What is the purpose of cost data in construction?

a)

To create financial statements

b)

To forecast and control construction activities

c)

To replace contract documents

d)

To estimate worker salaries

10.

What is the purpose of cost index adjustments in cost planning?

a)

To convert currency values

b)

To update historical cost data to current values

c)

To eliminate all cost variations

d)

To avoid using preliminary cost estimates