1.

As the CA for the principal, what role are you effectively taking?

a)

Superintendent

b)

Client

c)

Subcontractor

d)

Subservient

2.

The CA for the head contractor primarily deals with?

a)

Supervisor

b)

Head contractor

c)

Consultant

d)

Superman

e)

Subcontractors

3.

The CA for the subcontractor will deal with two main parties?

a)

Contractor

b)

Suppliers

c)

Client

d)

Labourers

4.

What is privity of contract?

a)

Its privilege from being on contract

b)

Privacy of information within the contract

c)

Rights of a contract only available to parties of the contract

d)

All of these

5.

Are suppliers entitled to claim against the contractor if they are not paid by the subcontractor

a)

Yes

b)

No

c)

Depends on the contractual arrangement

d)

None of these

6.

Which of the following are exceptions to privity?

a)

A contracting party acts as an agency to a party

b)

Contractual benefits are novated to a third party

c)

Contracting party holds contractual rights on trust for beneficiary

d)

All of these

7.

What is assignment in a contractual relationship?

a)

Transfer of rights in a contractual relationship to a third party

b)

Transfer of funds shared between two parties of a contract

c)

Transfer of employees temporarily between two contracting parties

d)

None of these

8.

When is assignment permitted in an AS4000 contract ?

a)

When there is mutual benefit

b)

Written approval from the other party

c)

When there are contractual issues

d)

Upon instruction by the client

9.

When does a Contractor need approval from the client for subcontractors under AS4000

a)

When the subcontractor has a criminal history

b)

When a subcontractors price is below market rates

c)

When the contractor has a conflict of interest

d)

None of these

10.

What is one way for a contractor to protect itself against defective work from a subcontractor?

a)

Back to Back contracting

b)

Back to Base contracting

c)

Backhand contracting

d)

Back to front contracting

11.

What is selecting subcontracting?

a)

Principal nominates subcontractors for contractor to choose from

b)

Contractor selects own subcontractors

c)

Subcontractor elects subcontractors

d)

Suppliers proposes the best subcontractors

12.

What are two aspects of back to back contracting ?

a)

Contractor passes head contractor obligations onto subcontractors

b)

Similar clauses in subcontract to head contract

c)

Contractor assigns obligations to external contractor

d)

Contractor adjusts clauses in the head contract

13.

What is a nominated subcontractor?

a)

Principal nominates a particular subcontractor

b)

Contractor nominates subcontractor for client to choose

c)

Subcontractor nominates themselves

d)

All of these

14.

Which of the following subcontractors is the contractor liable for ?

a)

Client selected subcontractor

b)

Nominated subcontractor

c)

Contractor selected subcontractors

d)

All of these

15.

What is the contractors’ obligation if the selected subcontractors won’t do the work

a)

Contend the contract

b)

Propose subcontractors

c)

Pull out fo the contract

d)

Increase the price of the contract

16.

What is novation on construction contracts

a)

Novel way of contracting

b)

All of these

c)

One contract replaces another contract

d)

One consultant works for multiple contractors

17.

What is the most common novation in Design and construct projects

a)

Suppliers

b)

Labourers

c)

Subcontractors

d)

Consultants

18.

Who needs to agree to Novation in construction?

a)

Principal

b)

Contractor

c)

Novated party

d)

All of these