1.

Which one of the following earthing arrangements is shown in the diagram.

a)

TNCS

b)

TT

c)

TNC

d)

TNS

2.

Which item of information is NOT illustrated on a bar chart work schedule?

a)

Start and finish dates

b)

hours worked per day

c)

plant/equipment delivery dates

d)

labour requirement at contract stage

3.

The insulation material in mineral insulated cable is

a)

manganese oxide

b)

magnesium dioxide

c)

manganese dioxide

d)

magnesium oxide

4.

The preferred method of instructing the client in the correct use and maintenance of electrical equipment used within an installation would be to?

a)

provide them with an operations and maintenance manual

b)

provide them with a guided tour and verbal instructions during the handover period

c)

provide them with the manufacturers catalogue

d)

leave relevant manufacturers literature next to the equipment

5.

The typical cabling for use in electrical installations in domestic premises would be

a)

SWA

b)

PVC/PVC

c)

MICC

d)

PVC Single

6.

Which one of the following is a transmission voltage?

a)

400 KV

b)

33 KV

c)

11 KV

d)

400 V

7.

What do the letters T, N, C and S stand for with regard to earthing systems?

a)

Totally Necessary Combination and Safe

b)

Terra Neutral Combination and Separate

c)

Totally Neutral Combined and Separate

d)

Terra Neutral Combined and Separate

8.

What is the current carrying capacity (It) of a 1 mm^2 single core thermoplastic PVC non armoured cable, that is installed in conduit?

a)

11 A

b)

44 A

c)

13 A

d)

6 A

9.

The Health and Safety at Work Act?

a)

Is for the guidance of employers

b)

Is for the guidance of employees

c)

Explains the duties of employers

d)

Explains the duties of employers and employees

10.

The disconnection time for ring or radial socket outlet circuits is

a)

4 seconds

b)

5 seconds

c)

0.4 seconds

d)

0.5 seconds

11.

Under the EAWR 1989, before work may commence, it must be shown that a person is what?

a)

Confident

b)

Competent

c)

Compliant

d)

Competitive

12.

The minimum bending radii of Mineral insulated (MICC) cable is how many times the cable diameter for: rework and (non rework)

a)

4 (1)

b)

5 (2)

c)

6 (3)

d)

7 (4)

13.

When electrical energy is transmitted a t 400 KV, it is known as?

a)

The super grid

b)

The local grid

c)

Medium voltage transmission

d)

Local distribution

14.

A scale drawing of a building is drawn 500 mm x 300 mm. The actual size of the building is 25 m x 15 m. What scale is used?

a)

0.11111

b)

1 : 50

c)

50 : 01

d)

100 : 1

15.

Which one of the following uses sunlight to generate electricity?

a)

photo-voltaic

b)

Biomass

c)

Wind

d)

Air source heat pump

16.

The main purpose of equipotential bonding is to

a)

maintain adjacent metalwork at the same electrical potential

b)

improve the earth loop impedance

c)

increase the impedance of the earth return

d)

prevent earth faults

17.

Cables in wooden joists must beat at least what distance from the top or bottom:

a)

30 mm

b)

45 mm

c)

50 mm

d)

65 mm

18.

Which one of the following earthing arrangements is shown in the diagram?

a)

TNCS

b)

TT

c)

TNC

d)

TNS

19.

The sequence of control for a large installation can be MOST simply shown by?

a)

Wiring diagram

b)

Layout diagram

c)

Circuit diagram

d)

Block diagram

20.

What cable is used to connect lots of computers in a LAN that is suitable for high rates of data transmission:

a)

Mineral insulated

b)

Thermosetting insulated

c)

Fibre Optic

d)

Armoured cable

21.

Which oe of the following is the minimum conduit size suitable for a short straight run containing the following stranded cables: 8 x 1.5 mm2; 2 x 2.5 mm2; 2 x 4 mm2

a)

15 mm

b)

20 mm

c)

25 mm

d)

32 mm

22.

In which of the following parts of the electrical distribution network would a step-down transformer be located?

a)

Power Station

b)

Pylon

c)

Local distribution sub station

d)

Inverter

23.

Which of these systems has the neutral and earth in one conductor?

a)

TT

b)

IT

c)

TNS

d)

TNCS

24.

Underground distribution systems within an industrial estate will most likely use?

a)

MICC

b)

XLPE SWA

c)

FP 200 Gold

d)

Busbar Trunking

25.

When installing equipment, a contracting electrician must be able to ?

a)

Design the installation

b)

Interpret drawings and diagrams

c)

Prepare working drawings

d)

Prepare site specifications

26.

What do the letters CDM stand for?

a)

Control of Demolition and Management Regulations

b)

Control of Dangerous Materials Regulation

c)

Construction (Demolition Management) Regulations

d)

Construction (Design and Management) Regulations

27.

Which one of the following is the maximum current carrying capacity for a single core; 6 mm2, 70 degrees celsius, thermoplastic insulated, non armoured cable, enclosed in conduit on a wall installed for a single phase circuit?

a)

31 A

b)

32 A

c)

36 A

d)

41 A

28.

Which one of the following is an exposed conductive part?

a)

Metal-clad switch

b)

Structural steelwork

c)

Air-conditioning ducting

d)

Metallic oil service pipe

29.

From which regulation does this definition come from and refer to ;

'all equipment which is intended to be worn, or held, to protect against risk to health and safety'?

a)

PUWER

b)

HASAWA 1974

c)

PPE at work regulations 1992

d)

EAWR

30.

The purpose of a protective device in a circuit is to

a)

avoid mechanical damage

b)

allow work to be done on a live circuit

c)

show when there is an open circuit

d)

disconnect a circuit when a fault occurs

31.

25 mm flat twin with cpc cable would normally be used for a?

a)

32 A domestic ring main

b)

1.5 A lighting circuit

c)

17 kW cooker supply

d)

6 kW shower unit circuit

32.

So that all contractors can understand the content of site and other drawings, they are provided with, it is necessary to?

a)

Produce drawings using recognised standards

b)

Explain verbally the content of drawings

c)

Produce large scale drawings

d)

Prepare detailed additional information

33.

In a wet room, where is a bath located?

a)

Zone 0

b)

Zone 1

c)

Zone 2

d)

Zone 3

34.

The main purpose of as fitted drawings is to form part of the?

a)

tender documents

b)

network diagrams

c)

work study schedules

d)

records of work

35.

Area Distribution Boards in large factories and commercial premises should normally be positioned

a)

close together

b)

in inaccessible positions

c)

near to the load centres

d)

near to the supply intake

36.

If a ring main circuit has a 32 A fuse 230 V supply, the maximum power available at any one time is

a)

73.36 W

b)

736 W

c)

7360 W

d)

73600 W

37.

The final conductor by which the connection to the earth electrode or other means of earthing is made is called the?

a)

circuit protective conductor

b)

earthing conductor

c)

earthing strap

d)

earthing bond

38.

What is the Ze for a TNCS system?

a)

0.8 ohm

b)

0.35 ohm

c)

20 ohm

d)

1.75 ohm

39.

One of the main aims of the health and Safety at Work Act 1974 is to secure the health, safety and welfare of people where?

a)

at home and public places

b)

at home

c)

at work

d)

at home and work everywhere

40.

Which one of the following describes Fault Protection?

a)

Preventing contact with parts which are intended to be live

b)

Limiting the risk of electric shock by live parts under fault conditions

c)

Removing the risk of electric shock through separation of circuits

d)

Preventing exposed parts from becoming live under fault conditions